FTIP#: F3502 CFP# F3502
AMENDMENT NO. 6
LOA.P00F3502
Rev: 10.31.2022 1 LOA Amendment Lapsing Date Extension
AMENDMENT NO. 6

LETTER OF AGREEMENT

BETWEEN

CITY OF REDONDO BEACH
AND

THE LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY This Amendment No. 6 to Letter of Agreement (this "Amendment"), is dated as of March 17, 2023 , by and between City of Redondo Beach ("Project Sponsor"), and the Los Angeles County Metropolitan Transportation Authority ("LACMTA”).

RECITALS:

A. Project Sponsor and LACMTA entered into that certain Letter of Agreement No. LOA.P00F3502, dated December 27, 2012, which was amended on February 12, 2016; November 1, 2018; February 1, 2019; October 1, 2020; and October 27, 2021 (as amended, the "Existing LOA"), which Existing LOA provides for the Redondo Beach Bicycle Plan Implementation (“the Project”); and
B. Whereas, LACMTA Board on August 25, 2022, desires to extend the lapsing date of Funds programmed for Fiscal Year (FY) 2015-16 to June 30, 2023; and C. Project Sponsor and LACMTA desire to amend the Existing LOA as provided herein.

FTIP#: F3502 CFP# F3502
AMENDMENT NO. 6
LOA.P00F3502
Rev: 10.31.2022 2 LOA Amendment Lapsing Date Extension
AGREEMENT:

NOW, THEREFORE, for good and valuable consideration, the receipt and adequacy of which are hereby acknowledged, the parties hereby agree as follows:

1. Part II, Paragraph 6.1(ii) of the Existing LOA is hereby amended by deleting it in its entirety and replacing it with the following: “Funds programmed for FY 2015-16 are subject to lapse on June 30, 2023. Project Sponsor shall allocate or obligate these Funds by the lapsing date.”

2. Part I, Paragraph 11 of Existing LOA is hereby amended to change LACMTA’s project manager to Cameron Palm, mail stop 99-22-6.

3. “Attachment B – Scope of Work, attached to the Existing LOA is hereby amended by deleting the Project Schedule and replacing it with the following Revised Project Schedule:”
LOA Milestones
Amendment No. 5 Schedule
in LOA
Scope of Work
Revised Project Schedule
Start Date End Date Start Date End Date
Environmental Clearance 11/2021 1/2022 Completed Completed Design Bid & Award Completed Completed Completed Completed Design 10/2020 11/2021 Completed Completed
Right-of-Way Acquisition 1/2022 4/2022 10/2022 03/2023
Construction Bid &
Award (E-76) 5/2022 8/2022 05/2023 08/2023
Construction 8/2022 12/2022 10/2023 01/2024
Total Project Duration
(Months)
13 months 26 months

4. Except as expressly amended hereby, the Existing LOA remains in full force and effect as originally executed. All rights and obligations of the parties under the Existing LOA that are not expressly amended by this Amendment shall remain unchanged.

FTIP#: F3502 CFP# F3502
AMENDMENT NO. 6
LOA.P00F3502
Rev: 10.31.2022 3 LOA Amendment Lapsing Date Extension
IN WITNESS WHEREOF, the parties have caused this Amendment No. 6 to be duly executed and delivered as of the above date.

LOS ANGELES COUNTY

METROPOLITAN TRANSPORTATION AUTHORITY
By: __________________________________ Date: ____________________ Stephanie N. Wiggins
Chief Executive Officer
APPROVED AS TO FORM:

DAWYN R. HARRISON
County Counsel
By: __________________________________ Date: ____________________ Deputy

CITY OF REDONDO BEACH
By: ________________________________ Date: ____________________ Bill Brand
Mayor
APPROVED AS TO FORM:

By: ________________________________ Date: ____________________ Michael W. Webb
City Attorney

← All documents from this meeting