Anita St at PCH to Maria CCO 1 Signed

Redondo Beach City Council
June 18, 2024

Document
Anita St at PCH to Maria CCO 1 Signed
Meeting
June 18, 2024
Body
Redondo Beach City Council
Pages
3
Original file
122 KB
Text extracted from the city's file for reading and search. Open the original on redondo.legistar1.com. That file is the official record.

DO
Sabotecoo

CITY OF REDONDO BEACH

DEPARTMENT OF PUBLIC WORKS
Anita Street at PCH to Maria Ave Street Improvements Job No. 41240 CHANGE ORDER No 1
June 11, 2024
Description of work included in the contract:

The work includes roadway grinding and asphalt resurfacing, construction of asphalt pavement over crushed miscellaneous base over unclassified soil, restriping, median modifications, tree removal, removal of raised median and replace with both raised and painted median, remove and install modified traffic channelization signs, install new signs, landscaping and irrigation improvements at existing raised center median, curb and gutter repairs and construct new curb and gutter, relocate electrical pull boxes, and other items per plans and specifications.

Il. Changes ordered:

In regards to construction and other construction related changes that were required at this project site, the following change order was negotiated with the contractor, Hardy & Harper, Inc.:

1. CCO #1 - Median Hardscape Design Modifications to Match Existing Pattern Ill. Reasons for the changes:

The above changes were requested by City staff, following an inspection with the contractor. Contractor issued RFI #2 requesting clarification on the improvements of the median island, with dilapidated conditions of the decades old colored concrete. In order to maintain consistency with the median of the west leg of the intersection, City staff proposed to replace the colored concrete of the east leg of June 11, 2024
the intersection with similar pavers, crushed miscellaneous base, compact sub- base, with proper construction joints, the details of which are provided by the City, throughout the entire length of the median, at the following negotiated cost:

1. Median Hardscape Design Modifications to Match Existing Pattern ($104,597.00)
IV. Contract Adjustment:

Work Authorized in the Base Contract $213,800.00
Change Order No. 1 - Median Hardscape Design
Modifications to Match Existing Pattern Total. $104,597.00 Revised Contract Amount ...... $318,397.00
...

Contract time:

The above changes will increase the contract duration by Five (5) non- compensable working days. Considering time required to obtain specified pavement material, the substantial completion date is now August 12, 2024.

VI. Compensation:

This change order includes $104,597.00 in negotiated value for the completion of the task described above. Payment made in association with this change order will be only for work actually performed and materials actually applied to the project, as determined by the City Engineer or his designee. This change order constitutes full and complete payment for all costs associated with the above changes inclusive of contractor's profit, direct and indirect overhead, insurance, supervision, labor, material, equipment, and lost business opportunities.

Change Order No. 1 June 11, 2024
Hardy & Harper, Inc

Page 2 ends

Hardy & Harper, Inc.

By:

Corporate Secretary

CITY OF REDONDO BEACH
By. Lamen Sablan
Lauren Sablan,
Acting City Engineer
Change Order No. 1 June 11, 2024
Hardy & Harper, Inc.

Page 3 of 3 ends