Planning Division .
.
Administrative Design Review .
Single-Family, Additions, Commercial Remodels, Signs, Etc. Planning No No Charge No Charge Each New Development Containing 2-3 Units on a Lot Planning No 2,360.00 Plus 688.00 Per Unit 2,360.00 Plus 688.00 Per Unit Each Multi-Family Residential Planning No 2,360.00 Plus 688.00 Per Unit 2,360.00 Plus 688.00 Per Unit Each Non-Residential Under 10,000 Square Foot Floor Area Planning No 5,400.00 5,400.00 Each Non-Residential Over 10,000 Square Foot Floor Area Planning No 13,560.00 13,560.00 Each Review of Additions, Overlap Parking and/or Signs 1 Planning No 1,145.00 1,145.00 Each .
Appeals .
Appeal of Decision by Director to Planning Commission 2 Planning No 550.00 550.00 Each Appeal of Administrative Design Review/Decision by Director to Planning Commission Planning No 550.00 550.00 Each Appeal of Administrative Design Review to Planning Commission for New Development Containing 2-3 Units on a Lot Planning No 735.00 Plus 735.00 Per Unit (To be Paid by Applicant)
735.00 Plus 735.00 Per Unit (To be Paid by
Applicant)
Each
Appeal of Planning Commission Decision to City Council Planning No 25% of Original Application Fee to a Max of 500.00
25% of Original Application Fee to a Max of
500.00
Each
Business License Administrative Appeal Planning No 550.00 550.00 Each .
Change of Land Use District/Zoning Map Amendment .
Property Outside City's Coastal Zone Planning No 5,507.00 5,507.00 Each Property Within City's Coastal Zone Planning No 8,040.00 8,040.00 Each .
Coastal Development Permit .
Public Hearing Waiver 3 Planning No 340.00 340.00 Each
Public Hearing Planning No 1,605.00 1,605.00 Each
.
Conditional Use Permit .
Category 1 - All Uses Except Multi-Family Residential Planning No 3,208.00 3,208.00 Each Category 2 - Multi-Family Residential and Condominium Projects Planning No 3,208.00 Plus 1,345.00 Per Unit 3,208.00 Plus 1,345.00 Per Unit Each Category 3 - Condominium Conversion Planning No 3,208.00 Plus 1,345.00 Per Unit 3,208.00 Plus 1,345.00 Per Unit Each Development Agreement Planning No 2,069.00 plus Contract Cost 2,069.00 plus Contract Cost Each .
Environmental Review Fees .
Initial Study and Negative Declaration Planning No 2,069.00 plus Contract Cost 2,069.00 plus Contract Cost Each Initial Study and Mitigated Negative Declaration Planning No 2,230.00 plus Contract Cost 2,230.00 plus Contract Cost Each Environmental Impact Report (EIR) Planning No Actual Cost Actual Cost Each Contract Administration Charge for EIR Consultant Planning No 2,069.00 2,069.00 Each Supplemental Fee for Environmental Analysis Based on Prior EIR or Master/Program EIR Planning No 1,840.00 1,840.00 Each .
Plan Check Fees 4 .
New Development Planning No 50% of Building Permit Fee 50% of Building Permit Fee Each Additions of Floor Area to Existing Development Planning No 50% of Building Permit Fee 50% of Building Permit Fee Each Commercial Tenant Improvements Planning No 10% of Building Permit Fee 10% of Building Permit Fee Each Structures Other Than Buildings (e.g., Fences, Walls, Signs) Planning No 115.00 115.00 Each .
Planned Development Review .
In Conjunction With Establishment of Overlay Zone 5 Planning No 5,507.00 5,507.00 Each In Conjunction With Establishment of Overlay Zone Within the City's Coastal Zone5 Planning No 8,040.00 8,040.00 Each Addition/Substantial Alteration to an Existing Development 6 Planning No 1,605.00 1,605.00 Each .
COMMUNITY DEVELOPMENT MASTER FEE SCHEDULE
Resolution No: CC-2406-049
Effective Date: July 10, 2024
Description Dept Change NEW FY 2024-2025 Unit FY 2023-2024
EXHIBIT A
COMMUNITY DEVELOPMENT MASTER FEE SCHEDULE
Resolution No: CC-2406-049
Effective Date: July 10, 2024
Description Dept Change NEW FY 2024-2025 Unit FY 2023-2024
EXHIBIT A
Planning Commission Design Review .
Review of New Construction .
Multi-Family Residential Planning No 3,215.00 3,215.00 Each Non-Residential Under 10,000 Square Foot Floor Area Planning No 3,215.00 3,215.00 Each Non-Residential 10,000 - 49,999 Square Foot Floor Area Planning No 12,900.00 12,900.00 Each Non-Residential 50,000 Square Foot or More Floor Area Planning No 25,800.00 25,800.00 Each Planning Re-Inspection Fee Planning No 230.00 230.00 Each Pre-Application Fee Planning No 695.00 695.00 Each
.
Prior Discretionary Approval .
Amendment Planning No 1,605.00 1,605.00 Each
Extensions 7 Planning No 688.00 688.00 Each
Subdivisions .
Parcel Map Planning No 1,605.00 1,605.00 Each
Tract Map Planning No 2,490.00 2,490.00 Each
Lot Line Adjustment Planning No 1,605.00 1,605.00 Each
Other Planning Fees .
Variance Planning No 3,200.00 3,200.00 Each
Modification Planning No 920.00 920.00 Each
Administrative Use Permit (AUP) Fee for Personal Improvement Services Planning No 1,605.00 1,605.00 Each Wireless Telecommunications Facilities Supplemental Application Planning No 3,210.00 Plus 1,335.00 Per Supplemental Application
3,210.00 Plus 1,335.00 Per Supplemental
Application
Each
Zoning Compliance Report Planning No 230.00 230.00 Each Planning/Zoning Code W/Cover Planning No 0.17 0.17 Each Planning/Zoning Code Yearly Supplements Planning No 0.17 0.17 Each General Plan Planning No 55.00 55.00 Each
Harbor/Civic Center Specific Plan Planning No 18.00 18.00 Each Temporary Use Permit Planning No 230.00 230.00 Each
Temporary Use Permit for Watersport Instruction and Equipment Rental Planning No 1,000.00 1,000.00 Each/Per Month Temporary Banners - Private Property (Temporary - Does Not Include Deposit) Planning No 70.00 70.00 Each .
Massage Permit Application Fee .
Business Location Planning No 275.00 275.00 Each
.
Entertainment Permit .
Level I Planning No 365.00 365.00 Each
Level II Planning No 805.00 805.00 Each
Renewal - Level I and Level II Planning No 205.00 205.00 Each .
Tobacco Retail Permits .
Tobacco Retail Permit Planning No 260.00 260.00 Each
.
Preservation Fees .
Landmark Designation or District Addition Planning No No charge No charge Each Certificate of Appropriateness- Restoration or Addition Planning No No charge No charge Each Mills Act Contracts Planning No No charge No charge Each Historic Variance Planning No 2,570.00 2,570.00 Each
Certificate of Appropriateness - Demolition or List Removal Planning No 5,175.00 5,175.00 Each .
Plan and Data Maintenance Fees .
General Plan Planning No 100,000.00 Per Year - 1.70 Per 1,000.00 Valuation 100,000.00 Per Year - 1.70 Per 1,000.00 Valuation Each .
COMMUNITY DEVELOPMENT MASTER FEE SCHEDULE
Resolution No: CC-2406-049
Effective Date: July 10, 2024
Description Dept Change NEW FY 2024-2025 Unit FY 2023-2024
EXHIBIT A
Building Division .
.
Miscellaneous Fees/Charges .
Address Change Building Yes 1,123.38 1,045.00 Each
Certificate of Occupancy Building No Included in Permit Fee Included in Permit Fee Each Certificate of Occupancy (Temporary) Building No Deposit Required as determined by Chief Building Official
Deposit Required as determined by Chief Building
Official
Each
Appeals of Administrative Decision Board of Appeals "Uniform Codes, Disabled Access Appeals Board" Building Yes 655.75 610.00 Each Deputy Inspector Certification Registration Building Yes 185.98 173.00 Each Grading Refundable Bond Building No Bond Amount Determined by Chief Building Official
Bond Amount Determined by Chief Building
Official
Each
Job Card Replacement Building Yes 118.25 110.00 Each
Report of Residential Building Yes 147.28 137.00 Each
Report of Residential - Expedited Additional Fee Building Yes 231.13 215.00 Each State Energy Plan Check Fee Building No 25% of Building Check Fee as Allowed by Section 25402.0 of Public Resources Code
25% of Building Check Fee as Allowed by Section
25402.0 of Public Resources Code
Each
Construction Site Sign Building Yes 95.68 89.00 Each
Contractor Transfer Fee Building Yes 29.03 27.00 Each
.
Inspection Fees .
Inspection Outside Normal Business Hours (Minimum 2 - Hour Charge) Building Yes 135.45 126.00 Per Hour Re-Inspection Fees Assessed Under Provisions of Section 305(G) Building Yes 215.00 200.00 Flat Rate Inspections for Which No Fee is Indicated (Minimum 1 - Hour Charge) Building Yes 197.80 184.00 Per Hour Plan Check/Review Fees 1 .
Plan Review Fee/Plan Review Revision Fee Building Yes 100% of Building Permit Fee and for Revisions 147.00 Per Hour
100% of Building Permit Fee and for Revisions
137.00 Per Hour
Each
Plan and Permit Retention Fee Building Yes 1.29 1.20 Per Page Accelerated Plan Review Building No 50% of Plan Check Fee 50% of Plan Check Fee Each Disability Plan Review and Permit Fees Building No 10% of Building Permit Fee 10% of Building Permit Fee Each CalGreen Plan Review Building No 10% of Building Permit Fee 10% of Building Permit Fee Grading Plan Check/Review Fees
50 Cubic Yards or Less Building Yes 152.65 142.00 Each
51 to 100 Cubic Yards Building Yes 231.13 215.00 Each
101 to 1,000 Cubic Yards Building Yes 383.78 357.00 Each 1,001 to 10,000 Cubic Yards Building Yes 485.90 452.00 Each 10,001 to 100,000 Cubic Yards Building Yes 642.00 for the First 10,000 Cubic Yards Plus 153.00 for Each Addl 10,000 Cubic Yards or
Fraction Thereof
597.00 for the First 10,000 Cubic Yards Plus
142.00 for Each Addl 10,000 Cubic Yards or
Fraction Thereof
Each
100,001 to 200,000 Cubic Yards Building Yes 2,016.00 for the First 100,000 Cubic Yards Plus 104.00 for Each Addl 10,000 Cubic Yards or
Fraction Thereof
1,875.00 for the First 100,000 Cubic Yards Plus
97.00 for Each Addl 10,000 Cubic Yards or
Fraction Thereof
Each
200,001 Cubic Yards or More Building Yes 2,903.00 for the First 200,000 Cubic Yards Plus 101.00 for Each Addl 10,000 Cubic Yards or
Fraction Thereof
2,700.00 for the First 200,000 Cubic Yards Plus
94.00 for Each Addl 10,000 Cubic Yards or
Fraction Thereof
Each
Plan Check Fees .
Electrical Plan Check Fee (1 Hour Minimum) Building Yes 100% of Electrical Permit Fee or 147.00/Hour 100% of Electrical Permit Fee or 137.00/Hour Each Mechanical Plan Check Fee (1 Hour Minimum) Building Yes 100% of Mechanical Permit Fee or 147.00/Hour 100% of Mechanical Permit Fee or 137.00/Hour Each Plumbing Plan Check Fee (1 Hour Minimum) Building Yes 100% of Plumbing Permit Fee or 147.00/Hour 100% of Plumbing Permit Fee or 137.00/Hour Each Shoring Plan Check Fee (1 Hour Minimum) Building Yes 100% of Shoring Permit fee or 147.00/Hour 100% of Shoring Permit fee or 137.00/Hour Each .
Permits .
Permit Issuance Fee 11 Building Yes 59.13 55.00 Each
Technology Surcharge Fee Building Yes $0.0025 per $1 dollar valuation Each After Hours Permit Building Yes 88.15 82.00 Each Day
Building Moving Permit (Within City, to City or From City) Building Yes 1,012.65 942.00 Each .
COMMUNITY DEVELOPMENT MASTER FEE SCHEDULE
Resolution No: CC-2406-049
Effective Date: July 10, 2024
Description Dept Change NEW FY 2024-2025 Unit FY 2023-2024
EXHIBIT A
Demolition Permit .
Single Family Building Building Yes 152.65 142.00 Each
Accessory Building to Single Family Building Building Yes 123.63 115.00 Each All Other Buildings Building Yes 212.85 198.00 Each
Transfer Fee Permit (In Addition to Issuance Fee) Building Yes 29.03 27.00 Each .
Building Permits .
Total Valuation .
$ 1 to 500 Building Yes 59.13 55.00 Each
$ 501 to 2,000 Building Yes 69.00 for First 500 + 10.00 for Each Addl 100 or Fraction Thereof
64.00 for First 500 + 9.00 for Each Addl 100 or
Fraction Thereof
Each
$ 2,001 to 25,000 Building Yes 230.00 for First 2,000 + 26.00 for Each Addl 1,000 or Fraction Thereof
214.00 for First 2,000 + 24.00 for Each Addl 1,000
or Fraction Thereof
Each
$ 25,001 to 50,000 Building Yes 818.00 for First 25,000 + 20.00 for Each Addl 1,000 or Fraction Thereof
761.00 for First 25,000 + 19.00 for Each Addl
1,000 or Fraction Thereof
Each
$ 50,001 to 100,000 Building Yes 1,323.00 for First 50,000 + 15.00 for Each Addl 1,000 or Fraction Thereof
1,231.00 for First 50,000 + 14.00 for Each Addl
1,000 or Fraction Thereof
Each
$ 100,001 to 500,000 Building Yes 2,074.00 for First 100,000 + 13.00 for Each Addl 1,000 or Fraction Thereof
1,929.00 for First 100,000 + 12.00 for Each Addl
1,000 or Fraction Thereof
Each
$ 500,001 and Up Building Yes 7,2300.00 for First 500,000 + 10.00 for Each Addl 1,000 or Fraction Thereof
6,726.00 for First 500,000 + 9.00 for Each Addl
1,000 or Fraction Thereof
Each
Combination Permit for Residential Owner/Builder When Valuation Is Less Than $20,000.002
Building No No Issuance Fee for Plumbing, Electrical and Mechanical Permits
No Issuance Fee for Plumbing, Electrical and
Mechanical Permits
Permit
.
Shoring Permits
Up to 500 Cubic Yards Building Yes 59.13 55.00 Each
500 Cubic Yards to 2,000 Cubic Yards Building Yes 68.00 for the first 500 Cubic Yards plus 9.00 for each additonal 100 cubic yards or fraction thereof
63.00 for the first 500 Cubic Yards plus 8.00 for
each additonal 100 cubic yards or fraction thereof Each 2,000 Cubic Yards to 25,000 Cubic Yards Building Yes 240.00 for the first 2,000 Cubic Yards plus 26.00 for each additonal 1,000 cubic yards or fraction
thereof
223.00 for the first 2,000 Cubic Yards plus 24.00
for each additonal 1,000 cubic yards or fraction
thereof
Each
25,001 Cubic Yards to 50,000 Cubic Yards Building Yes 569.00 for the first 25,000 Cubic Yards plus 19.00 for each additonal 1,000 cubic yards or fraction
thereof
529.00 for the first 25,000 Cubic Yards plus 18.00
for each additonal 1,000 cubic yards or fraction
thereof
Each
50,001 Cubic Yards to 100,000 Cubic Yards Building Yes 1047.00 for the first 50,000 Cubic Yards plus
14.00 for each additonal 1,000 cubic yards or
fraction thereof
974.00 for the first 50,000 Cubic Yards plus 13.00
for each additonal 1,000 cubic yards or fraction
thereof
Each
100,001 Cubic Yards to 500,000 Cubic Yards Building Yes 1744.00 for the first 100,000 Cubic Yards plus
12.00 for each additonal 1,000 cubic yards or
fraction thereof
1,622.00 for the first 100,000 Cubic Yards plus
11.00 for each additonal 1,000 cubic yards or
fraction thereof
Each
500,001 Cubic Yards or more Building Yes 6,470.00 for the first 500,000 Cubic Yards plus
9.00 for each additonal 1,000 cubic yards or
fraction thereof
6,019.00 for the first 500,000 Cubic Yards plus
8.00 for each additonal 1,000 cubic yards or
fraction thereof
Each
Grading Permits9
50 Cubic Yards or Less Building Yes 158.03 147.00 Each
51 to 100 Cubic Yards Building Yes 158.03 147.00 Each
101 to 1,000 Cubic Yards Building Yes 211.00 for the First 100 Cubic Yards Plus 53.00 for Each Addl 100 Cubic Yards or Fraction Thereof
196.00 for the First 100 Cubic Yards Plus 49.00 for
Each Addl 100 Cubic Yards or Fraction Thereof Each
1,001 to 10,000 Cubic Yards Building Yes 677.00 for the First 1,000 Cubic Yards Plus 45.00 for Each Addl 1,000 Cubic Yards or Fraction
Thereof
630.00 for the First 1,000 Cubic Yards Plus 42.00
for Each Addl 1,000 Cubic Yards or Fraction
Thereof
Each
10,001 to 100,000 Cubic Yards Building Yes 1,081.00 for the First 10,000 Cubic Yards Plus
43.00 for Each Addl 10,000 Cubic Yards or
Fraction Thereof
1,006.00 for the First 10,000 Cubic Yards Plus
40.00 for Each Addl 10,000 Cubic Yards or
Fraction Thereof
Each
100,001 or More Cubic Yards Building Yes 1,465.00 for the first 100,000 cubic yards plus
40.00 for each addl 10,000 cubic yards or fraction
thereof
1,363.00 for the first 100,000 cubic yards plus
37.00 for each addl 10,000 cubic yards or fraction
thereof
Each
COMMUNITY DEVELOPMENT MASTER FEE SCHEDULE
Resolution No: CC-2406-049
Effective Date: July 10, 2024
Description Dept Change NEW FY 2024-2025 Unit FY 2023-2024
EXHIBIT A
Electrical Permits .
.
System Fee Schedule .
New Residential Buildings .
Multi-Family (Apts and Condos) - If Building Has Three or More Living Units, Not Including Garage, Carports and Other Non-Commercial Auto Storage Areas Constructed at the Same Time.
Building Yes 0.20 0.19 Per Sq. Ft.
Single and Two-Family - If Building Has One or Two Living Units, Not Including Garage, Carport and Other Minor Accessory Constructed at the Same Time.
Building Yes 0.20 0.19 Per Sq. Ft.
Others - Other Types of Residential Occupancies and Alterations, Additions and Modifications to Existing Residential Structures.
Building Yes 0.25 0.23 Per Sq. Ft.
Private Swimming Pools .
For New Private, Residential (Single and Multi-Family) In-Ground Pools, Including a Complete System of Necessary Branch Circuit Wiring, Bonding, Grounding, Underwater Lighting, Water Pumping and Related Electrical Equipment.
Building Yes 127.93 119.00
Each
For Other Types of Swimming Pools, Therapeutic Whirlpools, Spas and Alterations to Existing Swimming Pools. Building No See Unit Fee Schedule See Unit Fee Schedule See Unit Fee Schedule Solar Electric Panel - Residential Building Yes 322.50 300.00 Each Solar Electric Panel - Commercial Building Yes 977.18 909.00 Each Carnivals and Circuses 3 .
Electric Generators and Electrically Driven Rides Building Yes 79.55 74.00 Each Electrical Lighting for Mechanically Driven Rides and Walk - Through Attractions Building Yes 18.28 17.00 Each Area and Booth Lighting System Building Yes 18.28 17.00 Each .
Temporary Power Service .
Temporary Power Service Pole or Pedestal, Including All Pole or Pedestal Mounted Receptacle Outlets and Appurtenances
Building Yes 50.53 47.00 Each
Temporary Distribution System and Temporary Lighting and Receptacle Outlets for Construction Sites, Decorative Light, Christmas Tree Sale Lots, Firework Stands, Etc.
Building Yes 24.73 23.00 Each
.
Electrical Permits (Continued) .
Power Apparatus4 .
Items Rating in HP/ KW .
Up to 1 Building Yes 18.28 17.00 Each
Over 1 and Not Over 10 Building Yes 45.15 42.00 Each
Over 11 and Not Over 50 Building Yes 76.33 71.00 Each
Over 51 and Not Over 100 Building Yes 152.65 142.00 Each Over 101 Building Yes 225.75 210.00 Each
.
Items Rating In KVA/KVAR .
E53 Transformer < 75 KVA Building Yes 45.15 42.00 Each
E54 Transformer > 75 KVA Building Yes 76.33 71.00 Each
Busways - for Trolley and Plug-in Type Busways 5 Building Yes 18.28 17.00 Each .
Signs, Outline Lighting and Marquees .
Supplied From One Branch Circuit Building Yes 49.45 46.00 Each Additional Branch Circuits W/I the Same Sign, Outline Lighting System or Marquee Services Building Yes 18.28 17.00 Each Services .
600 Volts or Less and Not Over 200 Amperes in Rating Building Yes 59.13 55.00 Each 600 Volts or Less and Over 200 Amperes to 1,000 Amperes in Rating Building Yes 169.85 158.00 Each Over 600 Volts or Over 1,000 Amperes in Rating Building Yes 321.43 299.00 Each Miscellaneous Apparatus, Conduits and Conductors for Which a Permit is Required But No Fee is Set Forth. (This Fee is Not Applicable When a Fee is Paid for One or More Services, Outlets, Fixtures, Appliances, Power Apparatus, Busways, Signs or Other Equipment)
Building Yes 38.70 36.00
Each
.
Elevator Permits .
New Installations 6 .
Passenger or Freight Elevator, Escalator, Moving Walk .
Up to and Including $40,000 Valuation Building Yes 592.33 551.00 Each Over $40,000 Valuation Building Yes 592.00 Plus 10.00 for Each 1,000.00 or Fraction Thereof Over 40,000.00
551.00 Plus 9.45 for Each 1,000.00 or Fraction
Thereof Over 40,000.00
Each
.
COMMUNITY DEVELOPMENT MASTER FEE SCHEDULE
Resolution No: CC-2406-049
Effective Date: July 10, 2024
Description Dept Change NEW FY 2024-2025 Unit FY 2023-2024
EXHIBIT A
Dumbwaiter or Private Residence Elevator .
Up to and Including $10,000 of Valuation Building Yes 76.33 71.00 Each Over $10,001 Valuation Building Yes 75.00 Plus 10.00 for Each 1,000.00 or Fraction Thereof Over 10,000.00
70.00 Plus 9.50 for Each 1,000.00 or Fraction
Thereof Over 10,000.00
Each
.
Unit Fee Schedule (The Following Do Not Include Permit Issuance Fees) .
Lighting Fixtures, Sockets or Other Lamp-Holding Device .
First 20 Building Yes 3.39 3.15 Each
Additional Fixtures Building Yes 1.72 1.60 Each
Pole or Platform-Mounted Lighting Fixtures Building Yes 3.39 3.15 Each Theatrical-Type Lighting Fixtures or Assemblies Building Yes 3.17 2.95 Each Receptacle, Switch and Lighting Outlets at Which Current is Used or Controlled- Except Service Feeders and Meters .
First 20 Building Yes 3.39 3.15 Each
Additional Outlets 7,8 Building Yes 1.72 1.60 Each
Residential Appliances or Receptacle Outlets for Same, Including Wall-Mounted Electric Ovens, Ranges, Console or Through-Wall Air Conditioners, Space Heaters, Food Waste Grinders, Dishwashers, Washing Machines, Water Heaters, Clothes Dryers, Etc. (Includes Motor Operated Appliances Not Exceeding 1HP Rating) Building Yes 18.28 17.00
Each
Non-Residential Appliances and Self-Contained Factory-Wired, Non-Residential Appliances Not Exceeding 1HP, Kilowatt, or Kilovolt-Ampere in Rating (Includes Medical and Dental Devices; Food, Beverage, and Ice Cream Cabinets; Illuminated Showcases; Drinking Fountains; Vending Machines, Laundry Machines or Other Similar Types of Equipment)
Building Yes 18.28 17.00
Each
.
Mechanical Permits .
.
System and Unit Schedule .
Air-Handling Unit, Up to and Including 10,000 Cubic Feet Per Minute, Including Ducts Attached Thereto 10 Building Yes 29.03 27.00 Each Air-Handling Unit Over 10,000 CFM 10 Building Yes 38.70 36.00 Each Appliance Vent - Installation, Relocation or Replacement, Each and Not Included in an Appliance Permit Building Yes 19.35 18.00 Each Mechanical Exhaust Hood (Type I) Building Yes 82.78 77.00 Each Mechanical Exhaust Hood (Type II) Building Yes 36.55 34.00 Each Miscellaneous Appliances/Equipment/Electric/Gas Building Yes 19.35 18.00 Each .
Boiler .
400,000 BTU/Hour or More Building Yes 118.25 110.00 Each Less Than 400,000 BTU/Hour Building Yes 73.10 68.00 Each FAU 100,000 BTU or Over Building Yes 46.23 43.00 Each
From 3 to 15 HP - 100,000 to 500,000 BTU Building Yes 107.50 100.00 Each Boiler or Compressor13 Over 100,000 BTU/Hour and Including 500,000 BTU/Hour Building Yes 112.88 105.00 Each Boiler or Compressor13 Over 15 HP to and Including 30 HP or Each Absorption System Over 500,000 BTU/Hour Up to and Including 1 Million BTU/Hour
Building Yes 121.48 113.00 Each
Boiler or Compressor13 Over 30 HP to and Including 50 HP or Each Absorption System Over 1 Million BTU/Hour Up to and Including 1.75 Million BTU/Hour
Building Yes 155.88 145.00 Each
Boiler or Compressor13 Over 50 HP or Each Absorption System Over 1.75 million BTU Building Yes 228.98 213.00 Each Evaporation Cooler Other Than Portable Type Building Yes 27.95 26.00 Each Furnace (Forced-Air or Gravity-Type)* Including Ducts and Vents Attached to Such Appliance, Up to and Including 100,000 BTU/Hour
Building Yes 52.68 49.00 Each
Furnace (As Above) Over 100,000 BTU/Hour Building Yes 73.10 68.00 Each Furnace - Including Vent Building Yes 36.55 34.00 Each
Heater (Suspended, Recessed Wall or Floor-Mounted Units) Building Yes 36.55 34.00 Each Incinerator - Industrial Type Building Yes 231.13 215.00 Each Repair of, or Alteration or Addition to Each Heating Appliance, Refrigeration Unit, Cooling Unit, Absorption Unit or Evaporative Cooling System, Including Installation of Controls Regulated by This Code Building Yes 36.55 34.00 Each
Ventilation Fan Connected to a Single Duct Building Yes 27.95 26.00 Each Ventilation System Which is Not a Portion of Any Heating or Air-Conditioning System Authorized by a Permit Building Yes 27.95 26.00 Each Appliance or Equipment Not Regulated by This Code, But Not Classed in Other Appliance Categories, or for Which no Other Fee is Listed in This Code
Building Yes 27.95 26.00 Each
New Multi-Family Building Yes 0.22 0.20 Sq. Ft
New One or Two Family Building Yes 0.22 0.20 Sq. Ft
Other Residential Addition, Alteration, Etc. Building Yes 0.28 0.26 Sq. Ft .
COMMUNITY DEVELOPMENT MASTER FEE SCHEDULE
Resolution No: CC-2406-049
Effective Date: July 10, 2024
Description Dept Change NEW FY 2024-2025 Unit FY 2023-2024
EXHIBIT A
Plumbing Permits .
Abandoned Cesspool / Cap Sewer Building Yes 169.85 158.00 Each Automatic Washer Building Yes 24.73 23.00 Each
Bar Sink Building Yes 24.73 23.00 Each
Bathtub Building Yes 24.73 23.00 Each
Bidet Building Yes 24.73 23.00 Each
Cesspool (Where Permitted) Building Yes 127.93 119.00 Each Dishwasher (No Permit Required for Repair or Replacement) Building Yes 24.73 23.00 Each Dishwasher - Commercial / Garbage Disposal Building Yes 34.40 32.00 Each Drinking Fountain Building Yes 24.73 23.00 Each
Fixture/Trap/Set of Fixtures on One Trap (Including Water, Drainage Piping, and Backflow Protection) Building Yes 27.95 26.00 Each Floor Drain / Floor Sink Building Yes 24.73 23.00 Each
Gas Piping System of One to Four Outlets Building Yes 18.28 17.00 Per Outlet Gas Piping System of Five or More Outlets Building Yes 16.13 15.00 Per Outlet Grease Trap / Interceptor / Clarifier Building Yes 59.13 55.00 Each Kitchen Sink / Kitchen Sink With Garbage Disposal Building Yes 24.73 23.00 Each Laundry Tub or Tray Building Yes 24.73 23.00 Each
Lavatory Building Yes 24.73 23.00 Each
Miscellaneous Building Yes 24.73 23.00 Each
Miscellaneous Electric Building Yes 18.28 17.00 Each
Pool / Spa / Heater / Filter System Building Yes 67.73 63.00 Each Private Sewer Disposal System Building Yes 167.70 156.00 Each Rainwater Systems (Inside Building) Building Yes 30.10 28.00 Per Drain Repair / Alter Vent Drain Sewer Building Yes 24.73 23.00 Per Drain Repipe Per Fixture - First 10 (Each) Building Yes 3.39 3.15 Per Drain Repipe Per Fixture - 11 and Over Building Yes 1.72 1.60 Per Drain .
Sewer .
Building and Trailer Park - Each Building Yes 101.05 94.00 Per Drain Disposal System Building Yes 228.98 213.00 Per Drain
Ejector Building Yes 63.43 59.00 Per Drain
Capping Building Yes 207.48 193.00 Per Drain
Shower Building Yes 24.73 23.00 Per Drain
Solar Plumbing Fee Building Yes 76.33 71.00 Per Drain
Shower Pan Replacement Building Yes 32.25 30.00 Per Drain Sink - Commercial Building Yes 45.15 42.00 Per Drain
Sprinkler (Lawn) on Any One Meter, Including Backflow Protection Devices Building Yes 33.33 31.00 Per Drain Urinal Building Yes 33.33 31.00 Per Drain
Vac Breakers .
Atmospheric - First 10 (Each) Building Yes 3.23 3.00 Per Drain Atmospheric - 11 and Over (Each) Building Yes 1.72 1.60 Per Drain Pressure Type - First 10 (Each) Building Yes 8.60 8.00 Per Drain Pressure Type - 11 and Over (Each) Building Yes 5.11 4.75 Per Drain Reduce Pressure Prin - First 10 (Each) Building Yes 24.73 23.00 Per Drain Reduce Pressure Prin - 11 and Over (Each) Building Yes 14.51 13.50 Per Drain Vent Piping and Drainage Repair or Alteration Building Yes 18.28 17.00 Per Fixture Water Closet Building Yes 24.73 23.00 Each
Water Heater Replacement Building Yes 24.73 23.00 Each
Water Heater (New) Building Yes 45.15 42.00 Each
Water Piping and / or Water-Treating Equipment (Installation / Alteration / Repair) Building Yes 24.73 23.00 Each .
New Residential Building .
Multi-Family Building Yes 0.20 0.19 Sq. Ft.
Single Family and Two Family Building Yes 0.20 0.19 Sq. Ft.
Other Residential Alterations, Additions, Etc. Building Yes 0.24 0.22 Sq. Ft.
SB 1473 Green Building Standards 12 .
$1 - 25,000 of Permit Valuation Building No 1.18 1.18 Location $25,001 - 50,000 of Permit Valuation Building No 2.36 2.36 Location $50,001 - 75,000 of Permit Valuation Building No 3.54 3.54 Location $75,001 - 100,000 of Permit Valuation Building No 4.72 4.72 Location Every $25,000 or Fraction Thereof Above $100,000 Building No Add $1 Add $1 Location
COMMUNITY DEVELOPMENT MASTER FEE SCHEDULE
Resolution No: CC-2406-049
Effective Date: July 10, 2024
Description Dept Change NEW FY 2024-2025 Unit FY 2023-2024
EXHIBIT A
CA Strong Motion Instrumentation Program Fees (SMIP)13
Residential up to 3-stories Building No 0.00013 of Valuation 0.00013 of Valuation Each Residential over 3-stories & Commercial Building No 0.00028 of Valuation 0.00028 of Valuation Each Other Development Impact Fees
Park In-Lieu Fees (Quimby Fees) Building No $25,000 per additional unit built in conjunction with a Tentative Parcel or Tract Map
$25,000 per additional unit built in conjunction
with a Tentative Parcel or Tract Map Each
Parks and Recreation Facility Fee Building Yes 430.00 400.00 Each Public Art Fee (collected under RBMC 10-6.05) Planning No 1% of Building Evaluation above $250,000 1% of Building Evaluation above $250,000 Each .
Planning Division
1 Fee Waived for Signs When in Conjunction With a Cup Application - No Longer Needs Planning Commission Review 2 Not Applicable to Appeal of New 2-3 Unit Residential Development 3 If a Public Hearing is Requested, Applicant Must Pay the Balance of the Public Hearing Fee 4 Fee Waived for Zoning Map Amendment and for Planning Commission Design Review 5 Fee Waived for Planning Commission Design Review
6 Fee Credited Toward Other Application Fees If Project Application is Submitted. 7 No Additional Fee Charged for Extensions of Multiple Approvals in Conjunction With the Same Project.
Building Division
1 Additional Plan Review Required By Changes, Additions and/or Revisions to Approved Plans (1/2 Hour Minimum) 2 No Combination Permit Will Be Issued If Construction Starts Without Proper Permit 3 Applies to Carnivals, Circuses or Other Traveling Shows or Exhibitions Using Transportable-Type Rides, Booths, and/or Attractions. 4 Includes Motors Generators, Transformers, Rectifiers, Synchronous Converters, Capacitors, Industrial Heating, Air Conditioning and Heat Pumps, Cooking or Baking Equipment. • for Equipment or Appliances Having More Than One Motor, Transformer, Heater, Etc., the Sum of the Combined Ratings May Be Used. Fees Include Switches, Circuit Breakers Contacts, Thermostats, Relays and Other Directly Related Controls. 5 An Additional Fee Will Be Charged for Lighting Fixtures, Motors and Other Appliances That are Connected to Trolley and Plug-In Type Busways. No Fee is Required for Portable Tools. 6 Installation Fees Include the First Year's Annual Inspection Fee and Charges for Electrical Equipment or Conveyance Side of Disconnect Switch 7 For Multi-Outlet Assemblies, Each 5 Feet or Fraction Thereof is Considered as One Outlet 8 For Other Types of Air Conditioners and Other Motor-Driven Appliances With Larger Electrical Ratings, See "Power Apparatus" 9 The Fee for a Grading Permit Authorizing Addional Work to That Under a Valid Permit Shall Be:
• The Difference Between the Fee Paid for the Original Permit and the Fee Shown for the Entire Project or • The Total Cost to the Jurisdiction, Whichever is Greater. • The Cost Shall Include Supervision, Overhead , Equipment, Hourly Wages and Fringe Benefits of the Employees Involved 10 This Fee Shall Not Apply to an Air Handling Unit Which is a Portion of a Factory-Assembled Appliance for Which a Permit is Required Elsewhere in This Code. 11 Permit Issuance Fee charged for each Reactivation of an expired permit 12 Monies Collected By These Fees Will Be submiƩed to the State of California Except For 10% retained by the City of Redondo Beach for AdministraƟve Charges and For Code Enforcement EducaƟon.
Notes