Description Amount
Service Request Number: 3738317 Project:
2506 MANHATTAN BEACH BLVD U PED REDONDO BEACH CA
90278
Install - Billing Option: SCE INSTALL -
415 DIAMOND ST
REDONDO BEACH CA 90277
Telephone: (310)-783-9303
REDONDO BEACH, CITY OF
SCE Contact: Amanda Gayle McEvoy
Invoice Date: 06/21/2024
505 MAPLE AVENUE
TORRANCE CA 90503
Southern California Edison Company
Document # 7590561385
Invoice # 549242
Item # 580895
Design #: 1740884
2275740 - NEW METER & SERVICE
Product: $1,306.32
Previous Payment $0.00
* For Mixed-Fuel projects, payment and signed contracts MUST be received before July 1, 2024, to keep subsidies (allowances, discount/refund options) and estimated cost pricing, otherwise SCE will reprice the project WITHOUT subsidies.
* Effective July 1, 2024, through December 31, 2024, Mixed-Fuel new construction projects (gas or propane in addition to electricity) will not receive subsidies and will be priced as estimated cost. * Effective January 1, 2025, Mixed-Fuel new construction projects will not receive subsidies and will be priced as actual cost billing.
* Enclosed are two copies of your invoice. Please return one copy of the invoice with your payment to Accounts Receivable in the enclosed return-addressed envelope. The other copy of the invoice is for your records. * All payments must be delivered by mail, an alternate postal method, or one of our electronic payment options.
Walk-in payments are no longer accepted at any SCE location, including Accounts Receivable. * Call the Edison company at 1-800-655-4555 to make application for electrical service. * An Edison Inspector must approve all underground systems. Please call your designated inspector 48 hours prior to construction to schedule an inspection.
* Final electrical inspection from the local governmental building and safety department must be received before we can energize your service.
* By paying this invoice, customer acknowledges and agrees that if this project is canceled by customer for any reason or customer does not proceed with the project completion. * Any expense incurred by SCE, including, but not limited to, expenses related to engineering, inspection and construction, prior to the project cancellation or completion will be deducted from any applicable refund due to the customer.
* To ensure worker and public safety, please maintain the appropriate clearance distance from utility infrastructure during your construction project to avoid encroachments that may result in serious injury or damage. * If relocation of existing utility infrastructure is pending, please adjust your work around the proposed relocation schedule as appropriate. If you have any questions, please contact the designated SCE representative assigned to your project.
.
$ 1,306.32
COMMENTS:
TOTAL PROJECT INVOICE AMOUNT:
Description Amount
Service Request Number: 3738317 Project:
2506 MANHATTAN BEACH BLVD U PED REDONDO BEACH CA
90278
Install - Billing Option: SCE INSTALL -
415 DIAMOND ST
REDONDO BEACH CA 90277
Telephone: (310)-783-9303
REDONDO BEACH, CITY OF
SCE Contact: Amanda Gayle McEvoy
Invoice Date: 06/21/2024
505 MAPLE AVENUE
TORRANCE CA 90503
Southern California Edison Company
Document # 7590561385
Invoice # 549242
Please detach and return payment stub with payment
Payment
Stub
REDONDO BEACH, CITY OF
415 DIAMOND ST
REDONDO BEACH CA 90277
Please pay total amount now due:
$ 1,306.32
Thank you for paying promptly
Make check payable to Southern California Edison
Document # 7590561385
ATTN: Remittance Processing
PO Box 800
Rosemead, CA 91771-001
ADDITIONAL PAYMENT INSTRUCTIONS:
If paying by check, please follow instructions on payment stub JP Morgan Chase Bank
New York, NY
ABA#: 021000021 - Acct#: 323-394434
SCE Taxpayer ID No. 95-1240335
Document #: 7590561385
SCE Contact:
Southern California Edison
Attn: Remittance Processing
G.O. 1 Ground Floor, Room G53
2244 Walnut Grove Ave.
Rosemead, CA 91770
Amanda Gayle McEvoy
Instructions for wire or ACH payments:
*** Failure to properly identify your document number and SCE contact may delay the application of funds and initiation of your project
Special Instructions for overnight delivery methods:
Applicant :
Product Number :
Project Specific Location :
SCE’s estimated refundable costs:*
SCE Rule 16 credit amount :*
SCE street light credit amount :*
SCE associated work credit amount :*
SOUTHERN CALIFORNIA EDISON ( "SCE " )
DISTRIBUTION LINE AND/OR SERVICE EXTENSION
APPLICANT'S INSTALLATION OPTION AND
STATEMENT OF APPLICANT'S CONTRACT ANTICIPATED COSTS
REDONDO BEACH, CITY OF
2506 MANHATTAN BEACH BLVD CA 90278
$0.00
$763.61
$0.00
$0.00
2275740
1. INSTALLATION OPTIONS
Applicant understands that in accordance with SCE’s Rule 15 and/or Rule 16, Applicant can elect to have either SCE install the Distribution Line and/or Service Extension or a Qualified Contractor/Subcontractor install the Distribution Line and/or Service Extension.
2. SCE’S ESTIMATED REFUNDABLE COST INFORMATION
SCE’s estimated refundable costs are based on the work that SCE would normally perform that can be performed by a Qualified Contractor/Subcontractor under the provisions of the Applicant Installation Option, Rule 15, Section G, and in accordance with SCE’s Terms and Conditions Agreement for Installation of Distribution Line Extension by Applicant (Form 14-188).
If applicable, other estimated cost information may be provided below. This could include the credit amount for Rule 16, street light, or other associated installation work.
3. APPLICANT SELECTION
Applicant understands the installation options under Section 1 above, and hereby elects the following installation option by initialing the appropriate selection below:
_________ Installation by SCE
_________ Installation by Qualified Contractor/Subcontractor Under installation by Qualified Contractor/Subcontractor, Applicant shall secure project specific bid information from Qualified Contractors/Subcontractors for the installation of the Distribution Line and/or Service extension.
Applicant shall contribute or advance before the start of construction any refundable or non-refundable amounts as specified in Rules 15 and 16.
*Please refer to the specific contract, Appendix A, for detailed financial information.
Form 14-754, Rev. 1/2024
4. APPLICANT'S CONTRACT ANTICIPATED COST INFORMATION (to be completed only if installation is performed by a Qualified Contractor/Subcontractor as selected in Section 3 above) Option 1 Applicant elects to provide SCE with the Applicants Contract Anticipated Costs, which are subject to refund, that are associated with that portion of the new Distribution Line and/or Service Extension normally installed by SCE, and understands that the lower of SCE's estimated refundable cost or the Applicant's Contract Anticipated Costs, which are subject to refund, as submitted below, shall apply to any applicable SCE refunds and allowances provided in accordance with Rule 15 and 16, 1
or
Option 2 Applicant elects not to provide SCE with the Applicants Contract Anticipated Costs, which are subject to refund. The Applicant understands that by selecting this option, the Applicant is directing SCE to use SCE's estimated refundable cost for all billing and accounting.
Applicant understands the Applicants Cost Information, as described above, and hereby elects the following by initialing the appropriate selection below :
________Option 1 - Applicants Contract Anticipated Costs $ _________________ ________Option 2 - SCE's Estimated Refundable Costs $ _________________
5. ITCC
SCE shall value all trenching, conduit, backfill, street repair, substructures, and encasement, based on SCE's estimate of such items, for the purpose of collecting the applicable governmental taxes (ITCC) on contributions to SCE.
7. UTILITY RESPONSIBILITIES
Upon receipt of this completed and signed form, SCE shall begin the process of producing the applicable contracts and forms based on the selection made by the Applicant.
Applicant and/or Applicant’s Qualified Contractor/Subcontractor understands that for the portion of the Electrical Distribution and/or Service Extension that SCE would normally install, in accordance with SCE’s Rule’s 15 and/or 16 and the Terms and Conditions Agreement for Installation of Distribution Line Extension by Applicant, the Applicant, prior to performing any work associated with the installation of these electrical facilities, and for the purpose of utility billing and accounting, shall elect one of the following options, and return this form to SCE prior to SCE proceeding with any further work on the Applicant’s project.
6. MIXED FUEL NEW CONSTRUCTION PROJECTS
Effective July 1, 2024, Allowances will not apply to Mixed-Fuel New Construction unless otherwise approved by the Commission in accordance with Decision 22-09-026. Effective January 1, 2025, any work performed associated with a Mixed-Fuel New Construction Distribution Line Extension2 project will be based on actual installed cost. Estimated costs will initially apply with final actual costs due after project completion. When an Applicant selects the Applicant Installation Option within Rule 15, reimbursable credits for the value of the substructures installed by the Applicant and deeded to SCE will not apply.
Form 14-754, Rev. 1/2024
8. SIGNATURE CLAUSE
The signatory hereto represents that they have been appropriately authorized into this contract on behalf of the party for whom they sign.
I declare under penalty of perjury that the foregoing is true and correct Applicant : ______________________________________________
Corporation, Partnership, or DBA: ____________________________ Name of Authorized Individual: ______________________________ Applicant’s signature: ______________________________________ Title: ___________________________________
Date: _________________________
1 Excludes the estimated costs of work the Applicant cannot perform, such as, work on or in proximity to, energized equipment.
2 As defined in Rule 15, a Mixed-Fuel New Construction is a building that uses gas and/or propane in addition to electricity, and has never been used or occupied for any purpose Form 14-754, Rev. 1/2024
CREW AND CUSTOMER TD2275740 CUSTOMER:DANIEL GRUEZO CONTACT:310-697-3214 UNDERGROUND SERVICE ALERT Contact USA Dial 811 or 800-422-4133 www.digalert.org/contact ····· DocuSign Envelope ID: C4301FBF-24A8-4F73-B148-A227C7C84ED1 CREW AND CUSTOMER TD2275740 CUSTOMER:DANIEL GRUEZO CONTACT:310-697-3214 UNDERGROUND SERVICE ALERT Contact USA Dial 811 or 800-422-4133 www.digalert.org/contact DocuSign Envelope ID: C4301FBF-24A8-4F73-B148-A227C7C84ED1