CITY OF REDONDO BEACH

DEPARTMENT OF PUBLIC WORKS
Anita Street at PCH to Maria Ave Street Improvements Job No. 41240 CHANGE ORDER No 3
October 15, 2024
Description of work included in the contract:

The work includes roadway grinding and asphalt resurfacing, construction of asphalt pavement over crushed miscellaneous base over unclassified soil, restriping, median modifications, tree removal, removal of raised median and replace with both raised and painted median, remove and install modified traffic channelization signs, install new signs, landscaping and irrigation improvements at existing raised center median, curb and gutter repairs and construct new curb and gutter, relocate electrical pull boxes, and other items per plans and specifications.
1l. Changes ordered:

During construction, at City's request, contractor did perform the following additional work over the bid item quantities:
• Proposed CCO #3 - Additional bid item quantities for unclassified excavation, cold mill existing asphalt concrete pavement, 2" asphalt concrete overlay and pavement markings were negotiated under this CCO #3.

IlI. Reasons for the changes:
• Proposed CCO 3:

During construction, following bid item quantities exceeded the scheduled quantities included in this change order:

Item no. 5. Unclassified Full Depth Excavation ($29,509.20) Item no. 6. Cold Mill Asphalt Concrete Pavement ($46,305.00) Item no. 7. 2" Asphalt Concrete Overlay ($41,308.00)
Item no. 19. Install Pavement Markings ($3,324.00)
Change Order No. 3 October 15, 2024
Hardy & Harper, Inc.

Page 1 of 3 ends

Total Proposed CCO 3: $120,446.20
IV. Contract Adjustment:

Work Authorized in the Base Contract . . . . $213,800.00 Change Order No. 1 - Median Hardscape Design
Modifications to Match Existing Pattern Total.. $104,597.00 Change Order No. 2 - Adjust Manhole and
Repair Sinkhole Total.. $22,724.01
Proposed Change Order No. 3 - Additional Bid Item
Quantities Total. $120,446.20
Revised Contract Amount ....... $461,567.21
V. Contract time:

The above changes will increase the contract duration by Five (5) non- compensable working days. However, considering the time required to obtain specified pavers material for the median, the substantial completion date is now October 10, 2024.

VI. Compensation:

This change order includes $120,446.20 in negotiated value for the completion of the task described above. Payment made in association with this change order will be only for work actually performed and materials actually applied to the project, as determined by the City Engineer or his designee. This change order constitutes full and complete payment for all costs associated with the above changes inclusive of contractor's profit, direct and indirect overhead, insurance, supervision, labor, material, equipment, and lost business opportunities.

Change Order No. 3 October 15, 2024
Hardy & Harper, Inc.

Page 2 of 3 ends

Hardy & Harper, Inc.

By:

Michaet Amundson, Vice President

CITY OF REDONDO BEACH
By:

Lauren Sablan,
Acting City Engineer
Change Order No. 3 October 15, 2024
Hardy & Harper, Inc.

Page 3 of 3 ends