N1-Stormwater Capture Policy and Projects
City Council
February 11, 2025

Stormwater Capture & Infiltration
Benefits:

Flood Control – stormwater capture reduces likelihood stormdrains will become overwhelmed Urban Runoff Water Quality – reduces pollutant loading into receiving waters Santa Monica Bay
Dominguez Channel
Conservation of Resources – drought resilience by storing water in the soil and recharging groundwater Meets regulatory compliance commitments

Regulatory Compliance
LARWQCB NPDES Permit
Requires BMPs to reduce pollutant loading into receiving waterbodies (trash, bacteria, metals, nutrients, oil, pesticides) Requirements apply to both private developments and City owned parcels and CIP Projects included in the WMP Typical private property LID capture & infiltrations strategies Infiltration galleries & wells
Permeable pavers/surfaces
Bioswales
Permeable drain pipes
Roof downspouts being directed into planter areas

Typical Private Property LID Strategies

Regional Stormwater Capture Projects

Cost Estimate for Redondo’s WMP Projects
Project:

Updated
Capital Cost
Unfunded
Capital Cost
Regulatory Compliance Year
Fulton Playfield Infiltration Project

PARTIALLY FUNDED
$10,000,000
$5,600,000*
2027
Herondo Watershed Distributed Infiltration
$5,000,000
$5,000,000*
2029
Beach Cities Green Streets Project

FUNDED BY GRANTS
$7,800,000
N/A
2026
Dominguez Channel Distributed Infiltration Project
$5,000,000
$5,000,000
2032
Glen Anderson Infiltration Park Regional Infiltration Project

PROJECT DESIGN FUNDED
$10,000,000
$10,000,000
2028
Trash Screens for Dominguez Channel Watershed
$500,000
$500,000
2029 (50%)

REDONDO TOTAL
$26,100,000
County Alondra Park Regional Stormwater Capture Project

FUNDED - GRANTS
$30,000,000
(County led)
2026
* - Grant Funds being pursued

Possible Options to Expand Stormwater Capture
Direct more discretionary capital resources to the unfunded stormwater capture projects in the CIP and WMP Update the Council’s 2006 Administrative Policy and Municipal Code to require stricter requirements by lowering the threshold of specific project types that require LID measures Codify an in-lieu fee option for applicants to fund a larger, regional stormwater capture BMP vs smaller, localized BMPs Pursue additional grant funding
Direct staff to study potential fees to fund future stormwater capture projects