1. Alley Rehab with PCI<25- Current Phase- One segment
approved with PS&E Dec. 2024 and other two will be
approved in April 2025

2. Aviation Blvd Resurfacing- Artesia to MBB- Pre Design

3. Boat Launch Design & Reconstruction (Relocation of
Boat Launch)- In Design

4. Curb Ramp Improvements- In Design

5. Dominquez Park Dog Park Improvements- 190th SlopePre-design

6. Fulton Playfield Infiltration Project- In Design

7. Glen Anderson Park Regional Stormwater- In Design

8. Green Street Improvements- Current Phase- Pre Design

9. Kingsdale Ave Resurfacing- 182nd to Grant- In Design

10. NRB Bikeway Extension- Inglewood Design/Corner
Parcel Landscaping- In design

11. Pedestrian Enhancement on Aviation- Pre-design

12. Pier Parking Structure Critical Repairs- PS&E approved, bids were rejected and will be rebid.

13. Pier Restroom Improvements- Restroom #3- In Design

14. Pier Solid Waste/Organic Recycling Infrastructure- In design

15. Police Department Shooting Range- In Design

16. Residential Street Rehabilitation- 2020 Year 2 & 3- Year 3 PS&E approval in April 2025

17. Seaside Lagoon- In Design

18. Riviera Village Pedestrian and Multi-Modal
Enhancements- Pre-design

19. Traffic Signal Communication Upgrades (Prospect and Catalina)- In Design

20. Veterans Park Historic Library Upgrades- In design, ADA requirements
FY 2024-25 CIP Projects-Design

1. Alley Rehab with PCI<25- Current Phase- Procurement/Out for Bids

2. Aviation/Artesia NB Right Turn Lane- PS&E Approved 2/4

3. Pier Parking Structure Critical Repairs – PS&E Approved; need to rebid

4. NRB Bikeway Extension- Felton to Inglewood- Bids received/award in March

5. Public Works Yard Infrastructure- In construction

6. Residential Street Rehabilitation- 2020 Year 2- Procurement/Out for Bids

7. Residential Street Rehabilitation - Deferred Maintenance- Phase 2- Procurement/Out for Bids

8. Redondo Beach Performing Arts Center Modernization- In Procurement

9. SCE ROW West of PCH Landscape Improvements- PS&E Approved 2/18

10. Sidewalk Improvements & Repairs- Next Phase- Contract Amendment in Process

11. South Bay Local Travel Network- PS&E Approved 2/18

12. Veterans Park Historic Library Upgrades- Windows- In Procurement

13. Wilderness Park Improvements-Ponds- Design Build Agreement Approved FY 2024-25 CIP Projects- Procurement

1. Artesia Blvd Intersection Safety Improvements- Construction to commence March 2025

2. Bicycle Plan Implementation Grant- In construction

3. Bicycle Transportation Plan Implementation- In construction

4. Beach Bluff Ped Path Light Replacement- In construction

5. Civic Center Courtyard Landscape- In construction

6. Traffic Signal Upgrades- Current Phase- On-going, partly funding Artesia Blvd Improvement Safety Improvements

7. Portofino Water Sewer Pump Station- In construction

9. Redondo Beach Marina Parking Lot Pay Stations – In construction

10.Veterans Park Senior Center Restroom Roof Replacement- In construction

11.Yacht Club Way Sewer Pump Station- In construction
FY 2024-25 CIP Projects- Construction

1. Alta Vista Field Improvements- Completed

2. Anderson Scout House ImprovementsCompleted

3. Anita at PCH Lane RechannelizationSubstantially Complete

4. Aviation Gym Improvements- LightingCompleted

5. Citywide Slurry Seal Program- Phase 4-
Completed

6. City Facility HVAC Replacement- city hallPlanning and Admin Conf Room completed

7. Dominguez Park Play Equipment, Landscape &
Walkways- Substantially Complete

8. Franklin Park Phase 1- Substantially Complete

9. Inglewood/MBB Improvements- Phase 2-
Substantially completed
FY 2024-25 CIP Projects- Completed

10.International Boardwalk Pavers- Completed

11.Grant Ave Signal Improvements- Completed

12.MBB Resurfacing- Aviation to InglewoodSubstantially Complete

13.Perry Park Teen Center Improvements- Completed

14.Play Surface Replacement- Dale Page and
Anderson Park- Completed

15.Police Department Pier Sub-station- Completed

16.Riviera Village Sidewalk Pavers- Completed

17.Shade Structure- Andrews Park- Completed

18. Torrance Blvd Resurfacing- Completed