Project Details
Title Description Location Component
PriorityStatus
Est. Schedule Useful Life
Start Complete Min Max Assem Senate
CitywideStriping
This project will include: Paving and/orStriping Installation (New Safety), Pavingand/or Striping Rehab/Repair (Existing Safety) Striping will occur in CityCouncil District 4 of theCity. All major arterialsin the City will be stripedand lane lines and legendsin Council District 1 willalso be restriped.
Construction Carried
Over 24/25
07/2025 06/2026
5 10 66 26
SidewalkImprovementsand Repairs
This project will include: Sidewalk and/orCrosswalk Rehab/Repair (Existing) The City will concentrateon repairing the sidewalksaround the schools citywideto ensure pedestriansafety, Remove and replacesidewalks in District 1between Knob Hill, ProspectAve, Catalina Ave, PalosVerdes Blvd; in District 2between Catalina Ave,Prospect Ave, TorranceBlvd, and Anita; inDistrict 3 between 190th,Lilienthal, 182nd, andFirmona; in District 4along Grant Ave, betweenInglewood and Aviation; inDistrict 5 betweenManhattan Beach Blvd, Vail,Robinson, and Inglewood Ave Construction Carried
Over 24/25
07/2025 06/2026
15 20 66 26
ResidentialRehabilitation, Year 2and 3 of2020 Cycle
This project will include: ADA Curb RampInstallation (New), ADA Curb Ramp Rehab/Repair(Existing), Paving and/or Striping Installation(New Safety), Sidewalk and/or CrosswalkRehab/Repair (Existing) Blossom Ln (Blocks 5600-5800); Perkins Ln (8100Block); Huntington Ln(10100-10200 Blocks); andVanderbilt Ln (Block10600); Bataan Rd (Aviationto Vail); Dufour Ave (Greento Vail); Farrell Ave(Aviation to Blossom);Graham St (Aviation toGreen); Green Ln (Matthewsto Nelson); Rindge Ln(Artesia to Gates Ave);Robinson St (Blossom toRindge); and Warfield Ave(Aviation to Vail) Construction In Progress
25/26
05/2025 06/2026
15 25 66 26
ATTACHMENT A