Attachment 2 - Aviation at Artesia Project Budget and Expenditure Plan - as of 9-30-25

Redondo Beach City Council
October 21, 2025

Document
Attachment 2 - Aviation at Artesia Project Budget and Expenditure Plan - as of 9-30-25
Meeting
October 21, 2025
Body
Redondo Beach City Council
Original file
61 KB
Text extracted from the city's file for reading and search. Open the original on redondo.legistar1.com. That file is the official record.

Date of Estimate Prepared: 9/30/2025
Budget:

Metro Measure R Funds:

Total
8/15/2011 Original Funding Agreement 847,000 Original FA7/22/2021 Metro Board approved 1,060,000 FA Amendment #66/14/2023 Metro Board approved 550,000 FA Amendment #77/17/2024 Metro Board approved 1,000,000 FA Amendment #8 Feb-25 Metro Board approved 1,500,000 FA Amendment #8
Jun-25 Metro Board approved 400,000 Current FA Amendment #9 Total: 5,357,000
Expenditure:

As of 9/30/25 Total Expenditure, billed to date to Metro 3,546,400 Includes RW Payment in full Michael Baker remaining balance 16,800Construction Estimate with 20% contin. 737,400 DASH Construction Co.Construction Management & Inspection 273,000 Southstar EngineeringPM Cost till project completion 47,400Total Projected Expenditure 4,621,000 As of 9/30/25 Budget Surplus/Shortfall: 736,000
Aviation at Artesia RTO
Total Project Budget and Expenditure Plan
Approved Funds