Cities Index.
Change Order No. 1 - Grant Ave Resurfacing and SBCCOG LTN

Redondo Beach City Council
December 9, 2025

Document
Change Order No. 1 - Grant Ave Resurfacing and SBCCOG LTN
Meeting
December 9, 2025
Body
Redondo Beach City Council
Pages
1
Original file
467 KB
Text extracted from the city's file for reading and search. Open the original on redondo.legistar1.com. That file is the official record.

Date:

I. Description of Work Included in the Contract:

II. Changes Ordered:

Grant Avenue Resurfacing
Item # Unit Qty Unit Price Total
1 LS 1 $ - - $
2 LS 1 $ 4,100.00 4,100.00 $
3 LS 1 $ 46,000.00 46,000.00 $
4 LS 1 $ 23,000.00 23,000.00 $
This change order provides for additional work to be performed by the Contractor under this project. It covers work related to City requested/directed changes and conflicts between design drawings and existing field conditions. The changes ordered are the negotiated prices and agreed upon between the Owner and the Contractor. The following changes will be incorporated and completed over the course of the project:

The following items are negotiated prices and agreed upon between the Owner and the Contractor:

Description

MOBILIZATION/DEMOBILIZATION (NOT
TO EXCEED 5% OF BID)

CITY OF REDONDO BEACH

DEPARTMENT OF PUBLIC WORKS
PROJECT NAME: AVIATION BLVD AT ARTESIA BLVD INTERSECTION IMPROVEMENTS Job No: 40780
Change Order Number: 1
The work includes demolition and disposal of abandoned utilities, remove and re-construct existing PCC and AC pavements; construct new PCC and AC pavements with base and sub-base; remove and reconstruct curb & gutter; construct a dual curb ramps per approved Plans and Specifications; remove and re-construct PCC sidewalk, and 4 Concrete Driveways. and any other work required per Plans and Specifications.

Work also includes: at the southeast corner of the intersection, remove and reconstruct traffic signal pull boxes; remove and reconstruct traffic signal poles on new foundations, accessible pedestrian push button (all corners), countdown ped heads (all corners), luminaires, mast arms, conduits, loop detectors and sign post; signing and striping; traffic signal improvements include a new traffic signal controller (procured by the City, contractor to install), new battery backup system, video traffic detection system, yellow retroreflective signal head backplates, new wiring, a new traffic signal communications module and any other work required per Plans and Specifications.

Friday, November 7, 2025

IMPLEMENTATION OF WATER

POLLUTION CONTROL BMPS

TRAFFIC CONTROL (INCLUDING SIGNS

AND CMS)

CONSTRUCTION SURVEY AND

MONUMENTATION

Page 1 of 5 ends

AVIATION BLVD AT ARTESIA BLVD INTERSECTION IMPROVEMENTS PROJECT, JOB NO. 40780 Change Order No. 1
November 7, 2025
8 EA 1 $ 863.00 863.00 $
9 EA 9 $ 7,830.00 870.00 $
10 EA 8 $ 9,200.00 1,150.00 $
11 EA 1 $ 1,150.00 1,150.00 $
14 LF 561
$ 67,320.00 120.00 $
17 SF 787
$ 25,184.00 32.00 $
21 SF 539 23.00 $ 12,397.00 $
23 SY 3497 $ 40,215.50 11.50 $
24 CY 204 $ 22,644.00 111.00 $
26 SY 9087 $ 54,522.00 6.00 $
28 SF 3522 $ 21,132.00 6.00 $
31 TON 1406 $ 260,110.00 185.00 $
34 LF 641 $ 4,487.00 7.00 $
36 LF 112 $ 560.00 5.00 $
37 SF 614 $ 4,298.00 7.00 $
38 SF 612 $ 4,284.00 7.00 $
40 SF 44 $ 506.00 11.50 $
43 SF 120 $ 1,380.00 11.50 $
45 SF 480 $ 14,400.00 30.00 $
46 EA 1 $ 23.00 23.00 $
48 EA 12 $ 6,000.00 500.00 $
52 CY 340 $ 32,640.00 96.00 $
53 TON 758 $ 116,732.00 154.00 $
54 LF 25 $ 237.50 9.50 $
55 LF 677 $ 6,431.50 9.50 $
56 LF 300 $ 1,800.00 6.00 $
57 LF 2140 $ 5,350.00 2.50 $
58 EA 4 $ 5,200.00 1,300.00 $
59 LF 2324 $ 8,134.00 3.50 $
60 LF 260 $ 15,080.00 58.00 $
THERMOPLASTIC STRIPING - DETAIL 39

THERMOPLASTIC STRIPING - MEDIAN

THERMOPLASTIC BIKE BUFFER

DASHED GREEN MMA BIKE LANE
CONSTRUCT HMA BASE COURSE (3.5"
DEPTH)
THERMOPLASTIC STRIPING - DETAIL 21
THERMOPLASTIC STRIPING - DETAIL 32
THERMOPLASTIC STRIPING - DETAIL 38

REPLACE STREET NAME SIGN

GREEN MMA BACKING

FIRE HYDRANT BLUE MARKER

THERMOPLASTIC WHITE CONTINENTAL

CROSSWALK

THERMOPLASTIC YELLOW

THERMOPLASTIC PAVEMENT MARKING -
"STOP"
REMOVE SURFACING AND BASE (3.5"
DEPTH)

THERMOPLASTIC LIMIT LINE
BASE REPAIR (4" DEPTH)
CONSTRUCT HMA OVERLAY (2.5"
DEPTH)

THERMOPLASTIC PAVEMENT MARKING -

ARROW IV

REMOVE EXISTING CURB AND GUTTER
AND RECONSTRUCT PER SPPWC STD.

PLAN 120-3 (A2)

ADJUST GAS VALVE BOX AND COVER
TO GRADE [REVOCABLE BID ITEM]

ADJUST WATER VALVE BOX AND

COVER TO GRADE

ADJUST SANITARY SEWER MANHOLE

FRAME AND COVER TO GRADE

ADJUST STORM DRAIN MANHOLE

FRAME AND COVER TO GRADE

SUBGRADE PREPERATION

SUBGRADE OVER-EXCAVATION AND
REPLACEMENT WITH CMB (6" DEPTH)
COLD MILL EXISTING AC (2.5" DEPTH)

REMOVE EXISTING DRIVEWAY APRON
AND RECONSTRUCT PER SPPWC STD.

PLAN 110-2 (TYPE C)

REMOVE EXISTING SIDEWALK UPLIFT
AND RECONSTRUCT PER SPPWC STD.

PLANS 112-2 AND 113-2
THERMOPLASTIC STRIPING - DETAIL 22
2 of 5
AVIATION BLVD AT ARTESIA BLVD INTERSECTION IMPROVEMENTS PROJECT, JOB NO. 40780 Change Order No. 1
November 7, 2025
61 SF 14 $ 728.00 52.00 $
62 SF 28 $ 980.00 35.00 $
64 LS 1 $ 8,000.00 8,000.00 $
Subtotal 832,918.50 $
SBCCOG Local Travel Network (LTN)
Item # Unit Qty Unit Price Total
1 LS 1 $ 15,000.00 15,000.00 $
2 LS 1 $ 87,400.00 87,400.00 $
3 EA 209 $ 76,285.00 365.00 $
4 EA 213 $ 44,730.00 210.00 $
5 EA 83 $ 24,070.00 290.00 $
6 EA 42 $ 12,180.00 290.00 $
7 EA 19 $ 4,940.00 260.00 $
8 EA 33 $ 10,560.00 320.00 $
9 EA 5 $ 1,500.00 300.00 $
10 EA 90
$ 35,100.00 390.00 $
11 EA 57 $ 12,198.00 214.00 $
Subtotal 323,963.00 $
III. Reasons for Changes
IV. Contract Bid Item Adjustments
V. Contract Adjustments
Work Authorized in Base Contract
This Change Order Itemized

FURNISH AND INSTALL WAYFINDING

SIGN DECISION SIGN (SHEET METAL)

FURNISH AND INSTALL WAYFINDING

SIGN CONFIRMATION SIGN (SHEET

METAL) FURNISH AND INSTALL WAYFINDING

SIGN TURN SIGN (SHEET METAL)

FURNISH AND INSTALL OTHER SIGN -

LTN LOGO SIGN (SHEET METAL)

FURNISH AND INSTALL OTHER SIGN -

CITY LOGO SIGN

FURNISH AND INSTALL POST

EXTENSION ON EXISTING POST

FURNISH AND INSTALL TELESPAR

BREAKAWAY POST W QUARED BASE

AND RELATED HARDWARE

THERMOPLASTIC PAVEMENT MARKING -

BIKE LANE SYMBOL WITHOUT PERSON

THERMOPLASTIC PAVEMENT MARKING -

BIKE LANE ARROW
None
$ 611,976.50

COORDINATE VIDEO DETECTION ZONE

ADJUSTMENTS
The City of Redondo Beach requested for DASH Construction to provide costs for additional similar scope construction activities on Grant Avenue from Harkness Lane to Green Lane and inclusion of the construction activities of the South Bay Cities Council of Governments Local Travel Network (LTN) project. Inclusion of this work will allow timely completion of these projects.

Description

MOBILIZATION/DEMOBILIZATION (NOT
TO EXCEED 5% OF BID)

TRAFFIC CONTROL (INCLUDING SIGNS

INSTALL SHARROWS IN

THERMOPLASTIC

FURNISH AND INSTALL HALF-DOME

TURTLE SIGN (SHEET METAL)
3 of 5
AVIATION BLVD AT ARTESIA BLVD INTERSECTION IMPROVEMENTS PROJECT, JOB NO. 40780 Change Order No. 1
November 7, 2025
Grant Avenue Improvements
Grant Avenue Sub-Total 832,918.50 $
SBCCOG (LTN) Improvements
Item #1 15,000.00 $
Item #2 87,400.00 $
Item #3 76,285.00 $
Item #4 44,730.00 $
Item #5 24,070.00 $
$ 15,080.00
$ 728.00
$ 980.00
$ 8,000.00
$ 6,431.50
$ 1,800.00
$ 5,350.00
$ 5,200.00
$ 8,134.00
$ 23.00
$ 6,000.00
$ 32,640.00
$ 116,732.00
$ 237.50
$ 4,298.00
$ 4,284.00
$ 506.00
$ 1,380.00
$ 14,400.00
$ 54,522.00
$ 21,132.00
$ 260,110.00
$ 4,487.00
$ 560.00
$ -
$ 4,100.00
$ 46,000.00
$ 23,000.00
$ 863.00
$ 7,830.00
$ 9,200.00
$ 1,150.00
$ 67,320.00
$ 25,184.00
$ 12,397.00
$ 40,215.50
$ 22,644.00
Item #61
Item #62
Item #64
Item #57
Item #58
Item #60
Item #59
Item #54
Item #55
Item #56
Item #48
Item #52
Item #53
Item #40
Item #43
Item #45
Item #46
Item #36
Item #37
Item #38
Item #28
Item #31
Item #34
Item #21
Item #23
Item #24
Item #26
Item #11
Item #14
Item #17
Item #8
Item #9
Item #10
Item #1
Item #2
Item #3
Item #4
4 of 5
AVIATION BLVD AT ARTESIA BLVD INTERSECTION IMPROVEMENTS PROJECT, JOB NO. 40780 Change Order No. 1
November 7, 2025
Revised Contract Amount
VI. Contract Time
60 VII. Compensation:

DASH Construction
By:

Authorized Representative

CITY OF REDONDO BEACH
By:

Lauren Sablan, PE
City Engineer
$ 12,198.00
SBCCOG LTN Sub-Total $ 323,963.00
$ 12,180.00
Item #7 $ 4,940.00
Item #8 $ 10,560.00
Item #9 $ 1,500.00
Item #10 $ 35,100.00
working days.

Item #6
Item #11
This change order constitutes full and complete payment for all costs associated with the above changes inclusive of consultant’s profit, direct and indirect overhead, insurance, supervision, labor, material, equipment, and lost business opportunities.

This Change Order Total $ 1,156,881.50
$ 1,768,858.00
The above change increases the contract time by
5 of 5

← All documents from this meeting