FTIP#: N/A
Subregion ID: South Bay
Project ID#: MM4602.09
Amendment No. 2
FA#: 9200000000M460209
Rev: 05.20.2025 1 Measure M MSP FA Amendment
AMENDMENT No. 2 TO MEASURE M FUNDING AGREEMENT
BETWEEN CITY OF REDONDO BEACH AND THE LOS ANGELES COUNTY
METROPOLITAN TRANSPORTATION AUTHORITY
This Amendment No. 2 to the Funding Agreement (this “Amendment”), is dated as of November 3, 2025 by and between the City of Redondo Beach ("GRANTEE") and the Los Angeles County Metropolitan Transportation Authority ("LACMTA").
RECITALS:
A. GRANTEE and LACMTA entered into that certain Funding Agreement No. 9200000000M460209, dated September 23, 2022, which was amended on June 5, 2023 (as amended, the "Existing FA"), which Existing FA provides for the North Redondo Beach Bikeway (NRBB) Extension – Inglewood Avenue, (“the Project”); and B. WHEREAS, the LACMTA Board on September 25, 2025 approved the increase to the Measure M Funds by $4,000,000 from $1,735,000 to $5,735,000 for Project Approval/Environmental Document (PAED), Plans, Specifications and Estimates (PS&E), Right-of-Way (ROW), and Construction. This amount is within the Board authorized budget increase for the Project; and
C. WHEREAS, the LACMTA Board on September 25, 2025 approved reprogramming of the Measure M Funds previously approved; and D. WHEREAS, the Funds are currently programmed as follows: $60,000 in Measure M Funds in Fiscal Year 2020-21, $140,000 in FY 2021-22, $1,294,091 in FY 2022- 23, $61,000 in FY 2024-25, $429,909 in FY 2025-26, and $3,750,000 in FY 2026-27. The total designated for PAED, PS&E, ROW, and Construction of the North Redondo Beach Bikeway (NRBB) Extension – Inglewood Avenue is $5,735,000; and
E. GRANTEE and LACMTA desire to amend the Existing FA as provided herein.
FTIP#: N/A
Subregion ID: South Bay
Project ID#: MM4602.09
Amendment No. 2
FA#: 9200000000M460209
Rev: 05.20.2025 2 Measure M MSP FA Amendment
AGREEMENT:
NOW, THEREFORE, for good and valuable consideration, the receipt and adequacy of which are hereby acknowledged, the parties hereby agree as follows:
1. Part I, Paragraph 2.2 of the Existing FA is hereby amended by deleting it in its entirety and replacing it with the following: “To the extent the Measure M funds are available, LACMTA shall make to GRANTEE a grant of the Measure M funds in the amount of $5,735,000 (the “Funds”) for the Project. LACMTA Board of Directors’ actions on August 27, 2020 and September 25, 2025 granted the Measure M Funds for the Project. LACMTA Board of Directors’ action on September 25, 2025 reprogrammed the Measure M Funds for the Project. The Funds are currently programmed over six Fiscal Years (FY): $60,000 in FY2020-21; $140,000 in FY2021-22; $1,294,091 in FY 2022-23; $61,000 in FY 2024-25; $429,909 in FY 2025-26; and $3,750,000 in FY 2026-27.”
2. Part II, Section 9.1 (vii) of the Existing FA is hereby amended by deleting it in its entirety and replacing it with the following: “(vii) Expending the Funds granted under this FA for allowable costs by the lapsing date. All Funds programmed for FY 2020-21, FY 2021-22 and FY 2022-23 have been expended and are no longer available. All Funds programmed for FY2024-25 are subject to lapse by June 30, 2027. All Funds programmed for FY2025-26 are subject to lapse by June 30, 2028. All Funds programmed for FY2026-27 are subject to lapse by June 30, 2029.”
3. Attachment A of the Existing FA is hereby replaced by Attachment A-1, attached.
4. Attachment B-1 of the Existing FA is hereby replaced by Attachment B2- attached.
5. Attachment C of the Existing FA is hereby replaced by Attachment C-1, attached.
6. Except as expressly amended hereby, the Existing FA remains in full force and effect as originally executed. All rights and obligations of the parties under the Existing FA that are not expressly amended by this Amendment shall remain unchanged.
FTIP#: N/A
Subregion ID: South Bay
Project ID#: MM4602.09
Amendment No. 2
FA#: 9200000000M460209
Rev: 05.20.2025 3 Measure M MSP FA Amendment
IN WITNESS WHEREOF, the parties have caused this Amendment No. 2 to the FA to be executed by their duly authorized representatives as of the dates indicated below:
LACMTA:
LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY By: ________________________________________ Date: ____________________ Stephanie Wiggins
Chief Executive Officer
APPROVED AS TO FORM:
DAWYN R. HARRISON
County Counsel
By: ________________________________________ Date: ____________________ Deputy
GRANTEE:
City of Redondo Beach
By: _______________________________________ Date: ____________________ James A. Light
Mayor
APPROVED AS TO FORM:
By: _______________________________________ Date: ____________________ Joy A. Ford
City Attorney
ATTEST:
By: _______________________________________ Date: ____________________ Eleanor Manzano
City Clerk
2/9/2026
SOURCES OF FUNDS Prior Years FY2021-22 FY2022-23 FY2023-24 FY2024-25 FY2025-26 FY2026-27 Total Budget
% of Budget
LACMTA PROGRAMMED FUNDING
MEASURE M MSP FUNDS $ 60,000 $ 140,000 $ 1,294,091 $ - $ 61,000 $ 429,909 $ 3,750,000 $ 5,735,000 SUM PROG LACMTA FUNDS $ 60,000 $ 140,000 $ 1,294,091 $ - $ 61,000 $ 429,909 $ 3,750,000 $ 5,735,000 100% OTHER NON LACMTA FUNDING:
LOCAL: $ - 0%
STATE: $ - 0%
FEDERAL: $ - 0%
PRIVATE OR OTHER: $ - 0%
SUM NON-LACMTA FUNDS $ - $ - $ - $ - $ - $ - $ - 0
TOTAL PROJECT FUNDS $ 60,000 $ 140,000 $ 1,294,091 $ - $ 61,000 $ 429,909 $ 3,750,000 $ 5,735,000 100% ATTACHMENT A -1 PROJECT FUNDING
Measure M MSP - Transporation System & Mobility Improvements Program - Funding Agreement Projects - FA#: 9200000000M460209 Project Title: NORTH REDONDO BEACH BIKEWAY (NRBB) EXTENSION -- INGLWOOD AVE Project ID#: MM4602.09
PROGRAMMED BUDGET - SOURCES OF FUNDS
03.01.19 Measure M Funding Agreement - MSP
Attachment A - 1 Project Funding
SOURCES OF FUNDS FY 2023-24
Qtr 1
FY 2023-24
Qtr 2
FY 2023-24
Qtr 3
FY 2023-24
Qtr 4
FY 2024-25
Qtr 1
FY 2024-25
Qtr 2
FY 2024-25
Qtr 3
FY 2024-25
Qtr 4 TOTAL BUDGET
LACMTA PROGRAMMED FUNDS:
MEASURE M MSP FUNDS:
Planning Activities/Prog Dev $0
Environmental $0
Design and PS&E $36,503 $24,556 $61,059
Right-of-Way Acquisition $47,938 $1,445,307 $528 $1,493,773 Construction $0
Vehicle Purchase $0
Others $0
Total MEASURE M $47,938 $1,445,307 $528 $0 $0 $36,503 $24,556 $0 $1,554,832 SUM PROG LACMTA FUNDS: $47,938 $1,445,307 $528 $0 $0 $36,503 $24,556 $0 $1,554,832 OTHER NON LACMTA FUNDING:
LOCAL: [INSERT SOURCE]
Planning Activities/Prog Dev $0
Environmental $0
Design and PS&E $0
Right-of-Way Acquisition $0
Construction $0
Vehicle Purchase $0
Others $0
Total LOCAL $0 $0 $0 $0 $0 $0 $0 $0 $0
STATE: [INSERT SOURCE]
Planning Activities/Prog Dev $0
Environmental $0
Design and PS&E $0
Right-of-Way Acquisition $0
Construction $0
Vehicle Purchase $0
Others $0
Total STATE $0 $0 $0 $0 $0 $0 $0 $0 $0
FEDERAL: [INSERT SOURCE]
Planning Activities/Prog Dev $0
Environmental $0
Design and PS&E $0
Right-of-Way Acquisition $0
Construction $0
Vehicle Purchase $0
Others $0
Total FEDERAL $0 $0 $0 $0 $0 $0 $0 $0 $0
PRIVATE: [INSERT SOURCE] $0
Planning Activities/Prog Dev $0
Environmental $0
Design and PS&E $0
Right-of-Way Acquisition $0
Construction $0
Vehicle Purchase $0
Others $0
Total PRIVATE $0 $0 $0 $0 $0 $0 $0 $0 $0
SUM NON-LACMTA FUNDS : $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECT FUNDING
PROJECT FUNDING
FY2023-24 and FY2024-25 $47,938 $1,445,307 $528 $0 $0 $36,503 $24,556 $0 $1,554,832 ATTACHMENT B - 2 EXPENDITURE PLAN COST & CASH FLOW BUDGET Measure M MSP - South Bay Transportation System & Mobility Improvements (TSMI) Program 2 Program - Funding Agreement Projects - FA# 9200000000M460209 Project Title: North Redondo Beach Bikeway Extension - Inglewood Avenue Project#:MM4602.09
PROGRAMMED SOURCES OF FUNDS
01.01.2023 1 of 2
Measure M Funding Agreement - MSP
Attachment B -2 Expenditure Plan
ATTACHMENT B - 2 EXPENDITURE PLAN COST & CASH FLOW BUDGET Measure M MSP - South Bay Transportation System & Mobility Improvements (TSMI) Program 2 Program - Funding Agreement Projects - FA# 9200000000M460209 Project Title: North Redondo Beach Bikeway Extension - Inglewood Avenue Project#:MM4602.09
PROGRAMMED SOURCES OF FUNDS
SOURCES OF FUNDS FY 2025-26
Qtr 1
FY 2025-26
Qtr 2
FY 2025-26
Qtr 3
FY 2025-26
Qtr 4
FY 2026-27
Qtr 1
FY 2026-27
Qtr 2
FY 2026-27
Qtr 3
FY 2026-27
Qtr 4 TOTAL BUDGET
LACMTA PROGRAMMED FUNDS:
MEASURE M MSP FUNDS:
Planning Activities/Prog Dev $0
Environmental $0
Design and PS&E $30,000 $30,000 $40,000 $40,000 $50,000 $40,000 $230,000 Right-of-Way Acquisition $0
Construction $2,267,668 $1,682,500 $3,950,168
Vehicle Purchase $0
Others $0
Total MEASURE M $30,000 $30,000 $40,000 $40,000 $50,000 $40,000 $2,267,668 $1,682,500 $4,180,168 SUM PROG LACMTA FUNDS: $30,000 $30,000 $40,000 $40,000 $50,000 $40,000 $2,267,668 $1,682,500 $4,180,168 OTHER NON LACMTA FUNDING:
LOCAL: [INSERT SOURCE]
Planning Activities/Prog Dev $0
Environmental $0
Design and PS&E $0
Right-of-Way Acquisition $0
Construction $0
Vehicle Purchase $0
Others $0
Total LOCAL $0 $0 $0 $0 $0 $0 $0 $0 $0
STATE: [INSERT SOURCE]
Planning Activities/Prog Dev $0
Environmental $0
Design and PS&E $0
Right-of-Way Acquisition $0
Construction $0
Vehicle Purchase $0
Others $0
Total STATE $0 $0 $0 $0 $0 $0 $0 $0 $0
FEDERAL: [INSERT SOURCE]
Planning Activities/Prog Dev $0
Environmental $0
Design and PS&E $0
Right-of-Way Acquisition $0
Construction $0
Vehicle Purchase $0
Others $0
Total FEDERAL $0 $0 $0 $0 $0 $0 $0 $0 $0
PRIVATE: [INSERT SOURCE] $0
Planning Activities/Prog Dev $0
Environmental $0
Design and PS&E $0
Right-of-Way Acquisition $0
Construction $0
Vehicle Purchase $0
Others $0
Total PRIVATE $0 $0 $0 $0 $0 $0 $0 $0 $0
SUM NON-LACMTA FUNDS : $0 $0 $0 $0 $0 $0 $0 $0 $0 PROJECT FUNDING
PROJECT FUNDING
FY2025-26 and FY2026-27 $30,000 $30,000 $40,000 $40,000 $50,000 $40,000 $2,267,668 $1,682,500 $4,180,168 TOTAL LACMTA FUNDS $77,938 $1,475,307 $40,528 $40,000 $50,000 $76,503 $2,292,224 $1,682,500 $5,735,000 TOTAL NON-LACMTA FUNDS $0 $0 $0 $0 $0 $0 $0 $0 $0
TOTAL PROJECT FUNDING $77,938 $1,475,307 $40,528 $40,000 $50,000 $76,503 $2,292,224 $1,682,500 $5,735,000
01.01.2023 2 of 2
Measure M Funding Agreement - MSP
Attachment B -2 Expenditure Plan
FTIP # N/A
Subregion ID: South Bay
Project#: MM4602.09
Amendment No. 2
Funding Agreement#: 920000000M460209
02.05.18 1 Measure M Funding Agreement – MSP
Attachment C –1 Scope of Work
ATTACHMENT C-1
SCOPE OF WORK
(CAPITAL PROJECTS)
PROJECT TITLE: North Redondo Beach Bikeway (NRBB) Extension – Inglewood Ave.
PROJECT LOCATION/LIMITS/AREA:
The project is located along the west side of Inglewood Avenue from the terminus of the North Redondo Beach Bikeway in the Southern California Edison (SCE) right-of-way south to Grant Avenue in the City of Redondo Beach, in the area near the Redondo Beach Galleria. In addition, it includes the proposed “hub” area at the southeast quadrant of the Grant/Inglewood intersection.
The project limits are from the SCE right-of way to Grant Avenue along the west side of Inglewood Avenue and the southeast quadrant of the Grant/Inglewood intersection.
PROJECT DESCRIPTION INCLUDING MULTI-YEAR SUBREGIONAL PROGRAM AND PROJECT NEXUS:
The NRBB is a lighted concrete path owned and maintained by the City under a license agreement with SCE to support multi-modal travel for cyclists and pedestrians. SCE owns the parcels over which the NRBB runs for the transmission of electric power on elevated high voltage lines. Within the City of Redondo Beach, the NRBB runs in a north-south orientation from Dale Page Park to just south of Rockefeller Lane where it turns to the east and continues to Felton Lane. There is a gap in the NRBB between Felton Lane and Inglewood Avenue. Funding for construction of that gap is submitted for consideration as a separate Measure M project. This project continues the NRBB to points east of Inglewood Avenue, especially the Galleria commercial area and the pending new transit center.
The project includes the design of the NRBB along the west side of Inglewood Avenue between the SCE right-of-way and Ripley Avenue. In addition, the project includes property acquisition and design of the “hub” area at the southeast quadrant of the Grant/Inglewood intersection. Tasks will include property acquisition, development of conceptual plans, community outreach, and preparation of final plans and specifications.
The South Bay Cities Council of Governments (SBCCOG) initially approved the design of the project for $200,000, which was approved by Metro on September 15, 2021.
Subsequently, on July 28, 0222 the SBCCOG amended the FY 22-23 Measure M MultiYear Regional Programs and approved the amendment to add $1,535,000 to the project for amended design and right-of-way (ROW) acquisition. On September 17, 2025, the FTIP # N/A
Subregion ID: South Bay
Project#: MM4602.09
Amendment No. 2
Funding Agreement#: 920000000M460209
02.05.18 2 Measure M Funding Agreement – MSP
Attachment C –1 Scope of Work
Los Angeles County Metropolitan Transportation Authority (LACMTA) Board approved the programming of an additional $4,000,000 to this project for the PA/ED, PS&E, ROW acquisition, and construction phases for a revised total grant of $5,735,000.
PROJECT FUNDING:
PHASE
LACMTA – MEASURE
M FUNDS
LOCAL AGENCY
(IF ANY) TOTAL
PA/ED, PS&E, ROW
Acquisition, and Construction $5,735,000 $0 $5,735,000
TOTAL BUDGET COST $5,735,000 $0 $5,735,000
ESTIMATED PROJECT COSTS:
Item Description Estimated Cost
PA/ED $50,000
PS&E $250,000
ROW Acquisition $1,485,000
Construction $3,900,000
Total $5,735,000
FTIP # N/A
Subregion ID: South Bay
Project#: MM4602.09
Amendment No. 2
Funding Agreement#: 920000000M460209
02.05.18 3 Measure M Funding Agreement – MSP
Attachment C –1 Scope of Work
FTIP # N/A
Subregion ID: South Bay
Project#: MM4602.09
Amendment No. 2
Funding Agreement#: 920000000M460209
02.05.18 4 Measure M Funding Agreement – MSP
Attachment C –1 Scope of Work
PROJECT SCHEDULE:
FA Milestones
Original FA Schedule in
Scope of Work Revised Project Schedule
Start Date End Date Start Date End Date
RIGHT OF WAY
ACQUISITON
Closing/Acquire Property
Relocation
N/A N/A 1/1/2023 9/6/2023
DESIGN MILESTONES
Solicitation for Design
Phase (Bid/Proposal)
7/15/2023 11/15/2023 2/15/2024 7/17/2024
PA/ED 2/1/2024 5/1/2024 10/1/2023 7/31/2024
Preliminary Design 3/1/2023 12/1/2023 8/1/2024 9/30/2025 PS&E
60% PS&E 5/1/2024 7/31/2024 10/1/2025 3/31/2026
90% PS&E 8/1/2024 8/30/2024 4/1/2026 6/30/2026
100% PS&E 9/1/2024 10/1/2024 7/1/2026 8/31/2026
Submittals and Reviews 11/1/2024 1/2/2025 9/1/2026 10/31/2026 Construction N/A N/A 11/1/2026 6/30/2027
Total Project Duration
(Months)
18 Months 55 Months
FTIP # N/A
Subregion ID: South Bay
Project#: MM4602.09
Amendment No. 2
Funding Agreement#: 920000000M460209
02.05.18 5 Measure M Funding Agreement – MSP
Attachment C –1 Scope of Work
PROJECT MAP: