Subregion ID: South Bay Project ID#: MM5508.13
Amendment No. 3
FA#: 9200000000M550813
Rev: 05.20.2025 1 Measure M MSP FA Amendment
AMENDMENT No. 3 TO MEASURE M FUNDING AGREEMENT
BETWEEN CITY OF REDONDO BEACH AND THE LOS ANGELES COUNTY
METROPOLITAN TRANSPORTATION AUTHORITY
This Amendment No. 3 to the Funding Agreement (this “Amendment”), is dated as of December 30, 2025, by and between the City of Redondo Beach ("GRANTEE") and the Los Angeles County Metropolitan Transportation Authority ("LACMTA").
RECITALS:
A. GRANTEE and LACMTA entered into that certain Funding Agreement No. 9200000000M550813, dated September 1, 2021, which was amended on September 30, 2023 and October 1, 2024 (as amended, the "Existing FA"), which Existing FA provides for the Traffic Signal Communications and Network System, (“the Project”); and B. WHEREAS, the LACMTA Board on September 25, 2025 approved the increase to the Measure M Funds by $300,000, from $5,000,000 to $5,300,000 for Project Approval/Environmental Document (PAED), Plans Specifications, and Estimates (PS&E), and Construction. This amount is within the Board authorized budget increase for the Project; and
C. WHEREAS, the Funds are currently programmed as follows: $200,000 in Measure M Funds in Fiscal Years (FY) 2020-21, $1,800,000 in FY 2021-22 and $246,672 in FY 2023-24, $654,703 in FY 2024-25, and $2,398,625 in FY 2025-26. The total designated for PAED, PS&E and Construction of the Traffic Signal Communications and Network Systems is $5,300,000; and
D. GRANTEE and LACMTA desire to amend the Existing FA as provided herein.
Subregion ID: South Bay Project ID#: MM5508.13
Amendment No. 3
FA#: 9200000000M550813
Rev: 05.20.2025 2 Measure M MSP FA Amendment
AGREEMENT:
NOW, THEREFORE, for good and valuable consideration, the receipt and adequacy of which are hereby acknowledged, the parties hereby agree as follows:
1. Part I, Paragraph 2.2 of the Existing FA is hereby amended by deleting it in its entirety and replacing it with the following: “To the extent the Measure M funds are available, LACMTA shall make to GRANTEE a grant of the Measure M funds in the amount of $5,300,000 (the “Funds”) for the Project. LACMTA Board of Directors’ actions on August 27, 2020, September 28, 2023, and September 25, 2025 granted the Measure M Funds for the Project. The Funds are currently programmed over five (5) Fiscal Years: $200,000 in FY 2020-21; $1,800,000 in FY 2021-22; $246,672 in 2023-24; $654,703 in FY 2024-25; and $2,398,625 in FY 2025-26.
2. Part II, Section 9.1 (vii) of the Existing FA is hereby amended by deleting it in its entirety and replacing it with the following: “(vi) Expending the Funds granted under this FA for allowable costs by the lapsing date. All Funds programmed for FY 2020-21, FY 2021-22, FY 2023-24, and FY 2024-25 have been expended and are no longer available. All Funds programmed for FY 2025-26 are subject to lapse by June 30, 2028.”
3. Attachment A-1 of the Existing FA is hereby replaced by Attachment A2, attached.
4. Attachment B-1 of the Existing FA is hereby replaced by Attachment B2, attached.
5. Attachment C-1 of the Existing FA is hereby replaced by Attachment C2, attached.
6. Except as expressly amended hereby, the Existing FA remains in full force and effect as originally executed. All rights and obligations of the parties under the Existing FA that are not expressly amended by this Amendment shall remain unchanged.
Subregion ID: South Bay Project ID#: MM5508.13
Amendment No. 3
FA#: 9200000000M550813
Rev: 05.20.2025 3 Measure M MSP FA Amendment
IN WITNESS WHEREOF, the parties have caused this Amendment No. 3 to the FA to be executed by their duly authorized representatives as of the dates indicated below:
LACMTA:
LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY By: ________________________________________ Date: ____________________ Stephanie Wiggins
Chief Executive Officer
APPROVED AS TO FORM:
DAWYN R. HARRISON
County Counsel
By: ________________________________________ Date: ____________________ Deputy
GRANTEE:
CITY OF REDONDO BEACH
By: _______________________________________ Date: ____________________ James A. Light
Mayor
APPROVED AS TO FORM:
By: _______________________________________ Date: ____________________ Joy A. Ford
City Attorney
By: _______________________________________ Date: ____________________ Eleanor Manzano
City Clerk
‹·¹·¨ø¥¥ß ·¹²ªº æßÊ ÏººËøÏæÍÛøÔðÏÛÏÓÁøÛÁÁðÈÛ
ÁæÍºÍºªÈ½ÍÁÍ
‹“Ê ›“ „ ϺºËøÏæÍÛøÔðÏÛÏÓÁøÛÁÁðÈÛ
ÁæÍºÍºªÈ½ÍÁÍ
‹ø¨ªÊ ÓðÓÍÚðÓÚÓð ÔÍÊðÔÊÎÈ Ûðˢðð˘
By: ________________________________________
SOURCES OF FUNDS FY2020-21 FY2021-22 FY2022-23 FY2023-24 FY2024-25 FY2025-26 Total Budget % of Budget
LACMTA PROGRAMMED FUNDING
MEASURE M MSP FUNDS $200,000 $1,800,000 $246,672 $654,703 $2,398,625 $ 5,300,000 SUM PROG LACMTA FUNDS $ 200,000 $ 1,800,000 $ - $ 246,672 $ 654,703 $ 2,398,625 $ 5,300,000 100% OTHER NON LACMTA FUNDING:
LOCAL: $ - 0%
STATE: $ - 0%
FEDERAL: $ - 0%
PRIVATE OR OTHER: $ - 0%
SUM NON-LACMTA FUNDS $ - $ - $ - $ - $ - $ - $ - 0
TOTAL PROJECT FUNDS $ 200,000 $ 1,800,000 $ - $ 246,672 $ 654,703 $ 2,398,625 $ 5,300,000 100% ATTACHMENT A-2 - PROJECT FUNDING
Measure M MSP - South Bay Highway Operational Improvements Program - Funding Agreement Project - FA#: 9200000000M550813 Project Title: Traffic Signal Communications and Network System Project ID#: MM5508.13
PROGRAMMED BUDGET - SOURCES OF FUNDS
03.01.19 Measure M Funding Agreement - MSP
Attachment A - Project Funding
SOURCES OF FUNDS FY 2023-24
Qtr 1
FY 2023-24
Qtr 2
FY 2023-24
Qtr 3
FY 2023-24
Qtr 4
FY 2024-25
Qtr 1
FY 2024-25
Qtr 2
FY 2024-25
Qtr 3
FY 2024-25
Qtr 4
TOTAL
BUDGET
LACMTA PROGRAMMED FUNDS:
MEASURE M MSP FUNDS:
Planning Activities/Prog Dev $0
Environmental $0
Design and PS&E $0
Right-of-Way Acquisition $0
Construction $1,009,753 $990,247 $161,369 $618,902 $129,460 $154,025 $371,218 $128,096 $3,563,070 Vehicle Purchase $0
Others $0
Total Measure M $1,009,753 $990,247 $161,369 $618,902 $129,460 $154,025 $371,218 $128,096 $3,563,070 SUM PROG LACMTA FUNDS: $1,009,753 $990,247 $161,369 $618,902 $129,460 $154,025 $371,218 $128,096 $3,563,070 SUM NON-LACMTA FUNDS : $0 $0 $0 $0 $0 $0 $0 $0 $0
PROJECT FUNDING
FY2023-24 and FY2024-25 $1,009,753 $990,247 $161,369 $618,902 $129,460 $154,025 $371,218 $128,096 $3,563,070 SOURCES OF FUNDS FY 2025-26
Qtr 1
FY 2025-26
Qtr 2
FY 2025-26
Qtr 3
FY 2025-26
Qtr 4
FY 2026-27
Qtr 1
FY 2026-27
Qtr 2
FY 2026-27
Qtr 3
FY 2026-27
Qtr 4
TOTAL
BUDGET
LACMTA PROGRAMMED FUNDS:
MEASURE M MSP FUNDS:
Planning Activities/Prog Dev $0
Environmental $0
Design and PS&E $15,000 $80,000 $60,000 $30,000 $15,000 $200,000 Right-of-Way Acquisition $0
Construction $200,000 $200,000
Vehicle Purchase $0
Others $0
Total Measure M $0 $0 $15,000 $80,000 $60,000 $30,000 $15,000 $200,000 $400,000 SUM PROG LACMTA FUNDS: $0 $0 $15,000 $80,000 $60,000 $30,000 $15,000 $200,000 $400,000 SUM NON-LACMTA FUNDS : $0 $0 $0 $0 $0 $0 $0 $0 $0
PROJECT FUNDING
PROJECT FUNDING
FY2025-26 and FY2026-27 $0 $0 $15,000 $80,000 $60,000 $30,000 $15,000 $200,000 $400,000 SOURCES OF FUNDS FY2027-28
Qtr 1
FY2027-28
Qtr 2
FY2027-28
Qtr 3
FY2027-28
Qtr 4
FY2028-29
Qtr 1
FY2028-29
Qtr 2
FY2028-29
Qtr 3
FY2028-29
Qtr 4
TOTAL
BUDGET
LACMTA PROGRAMMED FUNDS:
MEASURE M MSP FUNDS:
Planning Activities/Prog Dev $0
Environmental $0
Design and PS&E $0
Right-of-Way Acquisition $0
Construction $1,000,000 $336,930 $1,336,930
Vehicle Purchase $0
Others $0
Total MEASURE M $1,000,000 $336,930 $0 $0 $0 $0 $0 $0 $1,336,930 SUM PROG LACMTA FUNDS: $1,000,000 $336,930 $0 $0 $0 $0 $0 $0 $1,336,930 SUM NON-LACMTA FUNDS : $0 $0 $0 $0 $0 $0 $0 $0 $0
PROJECT FUNDING
PROJECT FUNDING
FY2027-28 and FY2028-29 $1,000,000 $336,930 $0 $0 $0 $0 $0 $0 $1,336,930 TOTAL LACMTA FUNDS $2,009,753 $1,327,177 $176,369 $698,902 $189,460 $184,025 $386,218 $328,096 $5,300,000 TOTAL NON-LACMTA FUNDS $0 $0 $0 $0 $0 $0 $0 $0 $0
TOTAL PROJECT FUNDING $2,009,753 $1,327,177 $176,369 $698,902 $189,460 $184,025 $386,218 $328,096 $5,300,000 ATTACHMENT B-2 - EXPENDITURE PLAN COST & CASH FLOW BUDGET Measure M MSP - South Bay Highway Operational Improvements Program Program - Funding Agreement Project - FA#: 9200000000M550813 Project Title: Traffic Signal Communications and Network System Project ID#: MM5508.13
PROGRAMMED SOURCES OF FUNDS
09.10.19 1 of 1
Measure M Funding Agreement - MSP
Attachment B - Expenditure Plan
Subregion ID: South Bay Project#: MM5508.13
Funding Agreement#: 9200000000M5508.13
03.01.19 1 Measure M Funding Agreement – MSP
Attachment C-1 – Scope of Work
ATTACHMENT C-2
SCOPE OF WORK
CAPITAL PROJECT
PROJECT NAME: Traffic Signal Communications and Network System PROJECT LOCATION/LIMITS/AREA:
This project limits are within City boundaries and at the following arterial roadway corridors:
Manhattan Beach Boulevard between Aviation Boulevard and Inglewood Avenue Inglewood Avenue between Ralston Lane and 182nd Street. Grant Avenue between Aviation Boulevard and Inglewood Avenue
PROJECT DESCRIPTION INCLUDING MULTI-YEAR SUBREGIONAL PROGRAM AND PROJECT NEXUS:
The purpose of this project is to upgrade the City’s traffic signal system technology and use Intelligent Transportation Systems (ITS) to enhance traffic signal infrastructure citywide for integration into an advanced traffic signal network/communications system. The project will construct the advanced traffic signal network/communications system at the first three roadway segments of Manhattan Beach Boulevard, Inglewood Avenue, and Grant Avenue within the City. The project intent is to upgrade in-field traffic signal equipment to help monitor and modify traffic signal operations to streamline mobility and ultimately, enhance traffic safety throughout the City. The project would also include advanced communications in preparation for connected/automated vehicles. The request for additional funding as part of Amendment #2 is to account for the increased construction costs that were originally underestimated when this project was approved.
City will integrate its system with Regional Integration of Intelligent Transportation Systems (RIITS) servers to provide data sharing between adjacent cities, the County, Caltrans, and other participating agencies. City will also coordinate with LA County Department of Public Works regarding adjacent or overlapping projects, traffic signal control and communications cooperative agreements, and signal coordination timing.
The project elements/field equipment may include but is not limited to the following:
Central management software;
Traffic signal interconnections and new communication - wireless modem, switches, router, server, appurtenances etc.
Conflict monitors;
Traffic monitoring video camera;
Traffic signal controllers;
Database server software;
Windows server software;
Data conversion and migration;
Battery backup systems;
Subregion ID: South Bay Project#: MM5508.13
Funding Agreement#: 9200000000M5508.13
03.01.19 2 Measure M Funding Agreement – MSP
Attachment C-1 – Scope of Work
Emergency Vehicle Preemption
PROJECT FUNDING:
PHASE
LACMTA – MEASURE
M FUNDS TOTAL
PS&E $200,000 $200,000
Construction $5,100,000 $5,100,000
TOTAL BUDGET COST $5,300,000 $5,300,000
PROJECT DETAILED SCHEDULE:
Milestones Begin End
Grant Ave Bid 10/6/2022 11/3/2022
Grant Ave Award 2/7/2023 2/7/2023
Grant Ave Construction 6/9/2023 9/3/2024
Manhattan Beach Blvd Bid 10/19/2023 11/16/2023
Manhattan Beach Blvd Award 11/16/2023 12/5/2023
Manhattan Beach Blvd Construction 4/29/2024 8/19/2024
Inglewood Ave Bid 11/2/2026 12/7/2026
Inglewood Ave Award 1/18/2027 1/18/2027
Inglewood Ave Construction 5/3/2027 11/1/2027
PROJECT MAP:
Subregion ID: South Bay Project#: MM5508.13
Funding Agreement#: 9200000000M5508.13
03.01.19 3 Measure M Funding Agreement – MSP
Attachment C-1 – Scope of Work