Cities Index.
N.1 - receive and file powerpoint

Redondo Beach City Council
April 21, 2026

Document
N.1 - receive and file powerpoint
Meeting
April 21, 2026
Body
Redondo Beach City Council
Original file
979 KB
Text extracted from the city's file for reading and search. Open the original on redondo.legistar1.com. That file is the official record.

Fulton Playfield Multi-Benefit
Infiltration Project
Public Works Department
Engineering Services Division
April 21, 2026
Background
Beach Cities Watershed Management Group
High-Priority Project
• Primary pollutant of concern: bacteria
Project Lead: City of Redondo Beach
2 Project
Location
Existing Site Conditions
3 Ex.

Detention
Basin
Ex. Diversion
Chamber
Rindge
Pump
Station
Project Drainage Area = 465 Acres
4 Fulton
Playfield
Retrofits Existing Facility
• Retrofits existing 6.6 AF
diversion chamber
• Adds underground
infiltration elements
• Enhances surface
landscaping
Key Benefits:
• Pollution Capture
• Flood Management
• Park Enhancement
• Heat Island Effect
Reduction
• Vegetation Increase
Number of
Drywells
13 Footprint of
Bioretention and
Ocean Friendly
Garden
794
ft2
5 Project Components (north)
Ocean
Friendly
Garden
Pretreatment
System
Drywells
Bioretention
Parkway
Diversion
Chamber
Retrofit
6 Project Components (south)
Drywell branch
2 (Cont.)
Bioretention
Parkway
(Cont.)
7 Project Achievements
24-hr Stormwater
Management
Capacity

19.2 ac-ft
Average Annual
Runoff Captured
150 acft/year
Average Annual
Bacteria Captured

3.33 E+13
MPN/year
Average Annual Zinc
Captured

19.2 lbs/year
Ocean Friendly Garden
13 Drywells
350 Linear Feet of
Bioretention Parkway
Community Outreach
Project Introduction Meeting - February 2024 at Valor Christian Academy Topics Presented
• Need and Reason for the Project
• Design elements and construction activities
• Impacts on playfield and parking
Resident Feedback & Design Integration:
• Residents preferred preservation of all existing green space • No preference for additional park improvements - exercise equipment • Final design includes community preferences
Next Meeting - Project Construction Details – Date TBD
8 9
Measure W Funding Schedule
Fiscal Year Awarded Funding Cumulative
Funding
FY 22-23 $93,000 $93,000
FY 23-24 $2,073,000 $2,166,000
FY 24-25
$1,683,000 $3,849,000
FY 25-26 $2,500,000 $6,349,000
FY 26-27
$46,500 $6,395,500
FY 27-28 $1,906,638 $8,302,138
TOTAL $8,302,138
The project is funded entirely from Regional Safe
Clean Water Grant Funds
Estimated Project Schedule
Bid Phase April – May 2026
Award Construction Contract June 2026
Construction Phase September 2026 – April 2027
(120 working days)
Accept Project as Complete Summer 2027
10 RECOMMENDATION
11 • Approve plans and specifications for the project
• Authorize the City Clerk to advertise the project for competitive bids

← All documents from this meeting