Reduced Scope Design – Cost Estimate, Site Plan and Rendering

Redondo Beach City Council
April 21, 2026

Document
Reduced Scope Design – Cost Estimate, Site Plan and Rendering
Meeting
April 21, 2026
Body
Redondo Beach City Council
Original file
1.2 MB
Text extracted from the city's file for reading and search. Open the original on redondo.legistar1.com. That file is the official record.

ELEMENTAL TRADE PACKAGE
48,718 SF 48,718 SF
Trade Package Total $ / GSF Total $ / GSF

1.0 Site Development $6,517,253 $134 $6,517,253 $134

1.01 Building Demolition $79,010 $1.62 $79,010 $1.62

1.02 Site Preparation & Demolition $68,069 $1.40 $68,069 $1.40

1.03 Hazardous Materials $0 $0.00 $0 $0.00

1.04 Site Survey $7,308 $0.15 $7,308 $0.15

1.05 Earthwork & Grading $329,550 $6.76 $329,550 $6.76

1.06 Erosion Control $19,487 $0.40 $19,487 $0.40

1.07 Traffic Control $0 $0.00 $0 $0.00

1.08 Asphalt Paving $0 $0.00 $0 $0.00

1.09 Paving $55,450 $1.14 $55,450 $1.14

1.10 Site Concrete $0 $0.00 $0 $0.00

1.11 Landscaping $0 $0.00 $0 $0.00

1.12 Irrigation Systems $0 $0.00 $0 $0.00

1.13 Site Structure $0 $0.00 $0 $0.00

1.14 Fencing and Gates $67,400 $1.38 $67,400 $1.38

1.15 Specialties $0 $0.00 $0 $0.00

1.16 Signage $12,180 $0.25 $12,180 $0.25

1.17 Equipment $0 $0.00 $0 $0.00

1.18 Water Feature $4,429,000 $90.91 $4,429,000 $90.91

1.19 Furnishing $0 $0.00 $0 $0.00

1.20 Building $885,815 $18.18 $885,815 $18.18

1.21 Plumbing $0 $0.00 $0 $0.00

1.22 Fire Water $0 $0.00 $0 $0.00

1.23 Domestic Water $16,900 $0.35 $16,900 $0.35

1.24 Sanitary Sewer Systems $16,900 $0.35 $16,900 $0.35

1.25 Storm Drainage Systems $420,185 $8.62 $420,185 $8.62

1.26 Gas Systems $0 $0.00 $0 $0.00

1.27 Site Electrical $70,000 $1.44 $70,000 $1.44

1.28 Site Lighting $40,000 $0.82 $40,000 $0.82

1.29 Site Telecommunications $0 $0.00 $0 $0.00

1.30 Site Security $0 $0.00 $0 $0.00
Sub-Total Direct Construction Cost $6,517,253 $134 $6,517,253 $134 A Design Contingency 15.00% $977,588 $20.07 $977,588 $20.07 B Market Escalation to Buyout 5.05% $378,223 $7.76 $378,223 $7.76 Total Direct Construction Cost $7,873,064 $162 $7,873,064 $162 C General Conditions $59,789 / MO 4.52% $597,886 $12.27 $597,886 $12.27 D General Requirements 4.00% $314,923 $6.46 $314,923 $6.46 E Subcontractor Default Insur. 1.50% $118,096 $2.42 $118,096 $2.42 F General Liability Insurance 1.80% $158,146 $3.25 $158,146 $3.25 G Overhead & Profit 4.50% $407,795 $8.37 $407,795 $8.37 Sub-Total Indirect Construction Cost $1,596,846 $33 $1,596,846 $33 Total Construction Cost $9,469,910 $194 $9,469,910 $194 Cost Summary
Seaside Lagoon Entitlement Package - Phase 1
Concept Design Phase SOPC
April 15, 2026
Site Development Grand Total