Date:
I. Description of Work Included in the Contract:
II. Changes Ordered:
Item # Unit Qty Unit Price Total
1 LS 1 46,179.40 $ $ 46,179.40
2 LS 1 19,850.00 $ $ 19,850.00
3 LS 1 19,122.10 $ $ 19,122.10
4 LS 1 12,900.00 $ $ 12,900.00 Traffic Signal Revision #3 (Unidentified Signal Equipment and connections)
The following items are negotiated prices and agreed upon between the Owner and the Contractor:
Description
24" Storm Drain Encasement
Traffic Signal Revision #1 (added
conductor schedule and conductors)
Traffic Signal Revision #2 (Conduit
Discrepancy)
Change Order Number: 2
Wednesday, May 6, 2026
The work includes demolition and disposal of abandoned utilities, remove and re-construct existing PCC and AC pavements; construct new PCC and AC pavements with base and sub-base; remove and reconstruct curb & gutter; construct a dual curb ramps per approved Plans and Specifications; remove and re-construct PCC sidewalk, and 4 Concrete Driveways. and any other work required per Plans and Specifications.
Work also includes: at the southeast corner of the intersection, remove and reconstruct traffic signal pull boxes; remove and reconstruct traffic signal poles on new foundations, accessible pedestrian push button (all corners), countdown ped heads (all corners), luminaires, mast arms, conduits, loop detectors and sign post; signing and striping; traffic signal improvements include a new traffic signal controller (procured by the City, contractor to install), new battery backup system, video traffic detection system, yellow retroreflective signal head backplates, new wiring, a new traffic signal communications module and any other work required per Plans and Specifications.
This change order provides for additional work to be performed by the Contractor under this project. It covers work related to unforeseen field conditions and conflicts between design drawings and existing field conditions. The changes ordered are the negotiated prices and agreed upon between the Owner and the Contractor. The following changes will be incorporated and completed over the course of the project:
CITY OF REDONDO BEACH
DEPARTMENT OF PUBLIC WORKS
PROJECT NAME: AVIATION BLVD AT ARTESIA BLVD INTERSECTION IMPROVEMENTS Job No: 40780
AVIATION BLVD AT ARTESIA BLVD INTERSECTION IMPROVEMENTS PROJECT, JOB NO. 40780 Change Order No. 2
May 6, 2026
5 LS 1 29,389.25 $ $ 29,389.25
6 LS 1 3,500.00 $ $ 3,500.00
7 LS 1 6,392.53 $ $ 6,392.53
8 LS 1 11,673.90 $ $ 11,673.90
9 LS 1 7,350.00 $ $ 7,350.00
Subtotal $ 156,357.18
III. Reasons for Changes
IV. Contract Bid Item Adjustments
V. Contract Adjustments
Work Authorized in Base Contract
This Change Order Itemized
Revised Contract Amount
Change Order No. 001 - Addition of Grant Avenue
Improvements and SBCCOG LTN Project $ 1,156,881.50
This Change Order Total $ 156,357.18
$ 1,925,215.18
Item #8 $ 11,673.90
Item #9 $ 7,350.00
Item #6 $ 3,500.00
Item #7 $ 6,392.53
Item #3 $ 19,122.10
Item #4 $ 12,900.00
Item #5 $ 29,389.25
Item #1 $ 46,179.40
Item #2 $ 19,850.00
Connect 4" PVC private drain from
Shell Station to trench drain
The above changes are in response to several unforeseen field conditions encountered during construction and responses to RFI's received from the Contractor. Inclusion of this work will allow timely completion of this additional work.
None
$ 611,976.50
Addition of Edgelit LED Street Name
Signs (Aviation Bl, Artesia Bl, Grant Av
& Flagler Ln)
Removal of 18" thick asphalt in Artesia
Blvd median
Additional potholing for Traffic Signal
Poles #6 & #7 due to unforeseen
subsurface conditions
Backfill excavated foundation hole with
slurry and auger for traffic signal
foundations
2 of 3
AVIATION BLVD AT ARTESIA BLVD INTERSECTION IMPROVEMENTS PROJECT, JOB NO. 40780 Change Order No. 2
May 6, 2026
VI. Contract Time
0 VII. Compensation:
DASH Construction
By:
Authorized Representative
CITY OF REDONDO BEACH
By:
Lauren Sablan, PE
City Engineer
This change order constitutes full and complete payment for all costs associated with the above changes inclusive of consultant’s profit, direct and indirect overhead, insurance, supervision, labor, material, equipment, and lost business opportunities.
The above change will increas the contract time by working days. 3 of 3