Date:
I. Description of Work Included in the Contract:
II. Changes Ordered:
Item # Unit Qty Unit Price Total
1 LS 1 152,156.50 $ 152,156.50 $
Subtotal 152,156.50 $
III. Reasons for Changes
CITY OF REDONDO BEACH
DEPARTMENT OF PUBLIC WORKS
PROJECT NAME: AVIATION BLVD AT ARTESIA BLVD INTERSECTION IMPROVEMENTS Job No: 40780
Change Order Number: 4
Wednesday, May 6, 2026
The work includes demolition and disposal of abandoned utilities, remove and re-construct existing PCC and AC pavements; construct new PCC and AC pavements with base and sub-base; remove and reconstruct curb & gutter; construct a dual curb ramps per approved Plans and Specifications; remove and re-construct PCC sidewalk, and 4 Concrete Driveways. and any other work required per Plans and Specifications.
Work also includes: at the southeast corner of the intersection, remove and reconstruct traffic signal pull boxes; remove and reconstruct traffic signal poles on new foundations, accessible pedestrian push button (all corners), countdown ped heads (all corners), luminaires, mast arms, conduits, loop detectors and sign post; signing and striping; traffic signal improvements include a new traffic signal controller (procured by the City, contractor to install), new battery backup system, video traffic detection system, yellow retroreflective signal head backplates, new wiring, a new traffic signal communications module and any other work required per Plans and Specifications.
This change order provides for additional work requested by the City. The changes ordered will construct a new PCC Bus Pad and additional AC paving on Artesia Blvd. The changes are the negotiated prices and agreed upon between the Owner and the Contractor. The following changes will be incorporated and completed over the course of the project:
The following items are negotiated prices and agreed upon between the Owner and the Contractor:
Description
New bus pad and PCC Improvements
on PCH at Torrance Blvd
AVIATION BLVD AT ARTESIA BLVD INTERSECTION IMPROVEMENTS PROJECT, JOB NO. 40780 Change Order No. 4
May 6, 2026
IV. Contract Bid Item Adjustments
V. Contract Adjustments
Work Authorized in Base Contract
Revised Contract Amount
VI. Contract Time
4 VII. Compensation:
DASH Construction
By: D.SHAHNAVAZ
Authorized Representative
CITY OF REDONDO BEACH
By:
Lauren Sablan, PE
Change Order No. 001 - Addition of Grant Avenue
Improvements and SBCCOG LTN Project $ 1,156,881.50
The above changes are in response to City requested additional work for DASH Construction to provide costs for a bus pad, curb, gutter and driveway improvements on PCH at Torrance Blvd. Inclusion of this work will allow timely completion of this additional work.
None
$ 611,976.50
Change Order No. 002 - Additional work due to
unforeseen field conditions $ 156,357.18
This change order constitutes full and complete payment for all costs associated with the above changes inclusive of consultant’s profit, direct and indirect overhead, insurance, supervision, labor, material, equipment, and lost business opportunities.
Change Order No. 003 - Bus Pad and AC Paving on
Artesia Blvd $ 125,129.78
Item #1 152,156.50 $
This Change Order Total 152,156.50 $
$ 2,202,501.46
The above change will increase the contract time by working days.
This Change Order Itemized
2 of 3
AVIATION BLVD AT ARTESIA BLVD INTERSECTION IMPROVEMENTS PROJECT, JOB NO. 40780 Change Order No. 4
May 6, 2026
City Engineer
3 of 3