BASE ADD'L BASE ADD'L BASE ADD'L
PLAN CHK COST PER INSPECT. COST PER INSPECT. COST PER
OCCUPANCY
TYPE DESCRIPTION SQ FT COST 100 SQ FT COST 100 SQ FT COST 100 SQ FT A 500 $7,852 $213.27 $4,236 $115.05 $12,088 $328.31
NEW 5,000 $17,449 $83.37 $9,413 $44.97 $26,862 $128.34
50,000 $54,964 $108.38 $29,651 $58.47 $84,615 $166.84
A2 500 $9,522 $258.63 $5,491 $149.14 $15,013 $407.77
NEW 5,000 $21,161 $101.10 $12,202 $58.30 $33,363 $159.40 50,000 $66,657 $131.43 $38,436 $75.79 $105,093 $207.22
B OR M 1,500 $12,118 $162.93 $9,588 $224.13 $21,705 $387.05 NEW 5,000 $17,820 $383.13 $17,432 $374.79 $35,252 $757.92 15,000 $56,133 $371.64 $54,911 $363.54 $111,044 $735.18 E 500 $7,184 $195.12 $6,119 $166.19 $13,302 $361.30
NEW 5,000 $15,964 $76.27 $13,597 $64.96 $29,561 $141.24 50,000 $50,287 $99.15 $42,831 $84.45 $93,117 $183.61
F1, F2 500 $5,847 $158.82 $9,413 $255.66 $15,260 $414.48 NEW 5,000 $12,994 $62.08 $20,918 $99.94 $33,912 $162.02 50,000 $40,931 $80.71 $65,892 $129.92 $106,823 $210.63
H1-H5 500 $6,516 $176.97 $9,413 $255.66 $15,929 $432.63 NEW 5,000 $14,479 $69.18 $20,918 $99.94 $35,397 $169.12 50,000 $45,609 $89.93 $65,892 $129.92 $111,501 $219.85
I 500 $8,186 $222.33 $6,119 $166.19 $14,305 $388.52
RESOLUTION NO: ____-___
BUILDING PERMIT FEES
INSPECTION
EXHIBIT A
PLAN CHECK & INSPECTION
HAZARDOUS OCCUPANCIES
FACTORY
EDUCATIONAL/DAYCARE
BUSINESS OR RETAIL
ASSEMBLY - RESTAURANT
ASSEMBLY (OTHER THAN A-2)
COMMUNITY DEVELOPMENT MASTER FEE SCHEDULE
PLAN CHECK
EFFECTIVE DATE: JULY 1, 2026
NEW 5,000 $18,191 $86.91 $13,597 $64.96 $31,788 $151.88 50,000 $57,302 $112.99 $42,831 $84.45 $100,132 $197.44
L 500 $6,683 $181.50 $8,001 $217.31 $14,684 $398.81
NEW 5,000 $14,850 $70.95 $17,780 $84.95 $32,630 $155.90 50,000 $46,778 $92.24 $56,007 $110.43 $102,785 $202.67
R-1 1,000 $8,353 $278.44 $7,844 $261.48 $16,198 $539.92 NEW 10,000 $33,413 $79.82 $31,377 $74.96 $64,790 $154.78 100,000 $105,251 $103.77 $98,838 $97.44 $204,089 $201.21 R-2 1,000 $5,569 $185.63 $8,934 $297.79 $14,503 $483.42 NEW 10,000 $22,275 $53.21 $35,735 $85.37 $58,010 $138.58 100,000 $70,166 $69.18 $112,565 $110.98 $182,732 $180.15 R-3 1,000 $6,137 $231.47 $4,989 $221.21 $11,126 $452.67 NEW 3,000 $10,766 $186.61 $9,413 $276.11 $20,179 $462.73 6,000 $16,364 $272.45 $17,696 $295.44 $34,061 $567.89
S-1 500 $4,678 $127.05 $5,648 $153.40 $10,326 $280.45
NEW 5,000 $10,395 $49.67 $12,551 $59.97 $22,946 $109.63 50,000 $32,744 $64.56 $39,536 $77.96 $72,280 $142.52
S-2 500 $4,344 $117.98 $6,668 $181.10 $11,012 $299.08
NEW 5,000 $9,653 $46.12 $14,817 $70.79 $24,470 $116.91
50,000 $30,407 $59.96 $46,674 $92.03 $77,081 $151.99
U 50 $835 $226.84 $353 $95.82 $1,188 $322.67
NEW 500 $1,856 $123.73 $784 $52.27 $2,640 $176.00
5,000 $7,424 $148.48 $3,136 $62.72 $10,560 $211.20
SHELL 500 $6,349 $172.43 $5,334 $144.87 $11,682 $317.30 NEW 5,000 $14,108 $67.40 $11,853 $56.63 $25,961 $124.04 50,000 $44,440 $87.63 $37,337 $73.62 $81,777 $161.25
MULTI-FAMILY RESIDENTIAL/APARTMENT
HOTEL/MOTEL
LABORATORIES
INSTITUTIONAL
SHELL BUILDING - FOUNDATION & EMPTY
STRUCTURE
UTILITY/MISCELLANEOUS STRUCTURE
LOW HAZARD WAREHOUSE/PARKING
GARAGE
MODERATE HAZARD
WAREHOUSE/PARKING GARAGE
SINGLE FAMILY RESIDENTIAL
NOTES:
**** Plan Check and permit fees calculated through this study are in relation to requirements imposed by the California Building Code (CBC).
The CBC dictates the types of development projects and applications, which require different permits. The plan check and inspection fees are to review those **Residential Additions is charged at 40% of New Construction Fee. of the projects listed above.
projects and applications to ensure conformance with those building code requirements.
Building Official and Community Development Director have the discretion to charge time and materials for any project considered outside the scope *** Foundation only is charged as 10% of the Building Permit Fee. *Production Homes are charged full fee for plan review. Inspections are not discounted. *****For previously adopted fees, please refer to prior fee schedules.
Each $63.00
Building Each 65% of New Construction
Fee
Building Each 65% of New Construction
Fee
Building Each 40% of New Construction
Fee
Building Linear Feet $406.00
Building Each $170.00
Building Linear Feet $468.00
Building Each $170.00
Building Linear Feet $674.00
Building Each $170.00
Building Sq Ft $674.00
Building Sq Ft $761.00
Building Sq Ft $312.00
Building Sq Ft $486.00
Building Sq Ft $202.00
EFFECTIVE DATE: JULY 1, 2026
RESOLUTION NO: ____-___
MISCELLANEOUS & MEP FEES
Proposed Fee
Tenant Improvements
Single Family Dwelling renovation and repair - interior only nonstructural with PME Fence First 100 lineal feet(wood,vinyl,w.iron etc)
Patio Cover, Pergola, Gazebo, Porch, Deck-First 500 sq ft each additional 100 ft
Retaining wall-Special design-over 6 ft high per 1000 sq ft Retaining Wall-Special Design-≤6 ft high-First 100 lineal feet each additional 500 sq ft
each additional 100 ft
Patio Enclosure First 500 sq ft - ICC
Unit
Permit Issuance
Fee Type
Kitchen/Bathroom Remodel
EXHIBIT A
Description
Masonry Wall- ≤ 6ft high-First 100 lineal feet
each additional 100 lineal feet
All masonry wall heights measured from top of footing to top of wall:
each additional 500 sq ft
COMMUNITY DEVELOPMENT MASTER FEE SCHEDULE
Building Sq Ft $624.00
Building Sq Ft $312.00
Building Sq Ft $1,073.00
Building Sq Ft $257.00
Building Percentage 65% of New Construction
Fee
Building Percentage 65% of New Construction
Fee
Building Each $1,298.00
Building Each $1,834.00
Building Each $2,008.00
Building Each $2,582.00
Building Each $1,073.00
65% of U Occup New
Construction Fee
Building Each $449.00
Building Linear Feet $624.00
Building Each $624.00
Building Each $811.00
Patio Enclosure First 500 sq ft - Conventional/Special Design Window/Doors Residential-new/changeout/skylights (greater than 5 windows)
Residential
Window/Doors Residential-new/changeout/skylights (up to 5 windows)
each additional 500 sq ft
Swimming pool misc structure or code upgrade/modifications Foundation Repair /seismic upgrade/per 200 lineal ft of foundation
Loft - Special Design - first 500 sq ft
Residential
Ponds/Fountains 200 sq ft or less
each additional 500 sq ft
Swimming pool grotto or additional structural/water features - each
New Pool/Spa
Combination Permits:
Garage Conversion - Conventional Construction
New Pool/Spa with Vault
Garage Conversion - Special Design
Commercial
Commercial
Building Percentage 65% of New Construction
Fee
Building Each $711.00
Building Each $711.00
Building Each $798.00
Building Each $131.00
Building Linear Feet $1,036.00
Building Each $486.00
Building Each $1,797.00
Building Each $312.00
Building Each 65% of New Construction
Fee
Building Each $362.00
Building Each $500.00
Building Each $587.00
Building Each $142.00
Sign - Non-Electrical 200 sq ft or less:
each additional 500 ft
Storage Racks 6 ft and higher:
Cell Site/commercial antenna structure - each
each additional 200 sq ft and/or each additional 20 ft height first 500 lineal ft
Flag pole
plus actual cost over 3 plan checks/inspections
Pole sign 200 sq ft or less and 20 ft high or less
Up to 1,500 sq ft
Window Non-Residential-new/changeout/skylights (Each 50) to ensure compliance with CBC & RBMC:
monument 6 ft high or less
1,501 - 5,000 sq ft
Miscellaneous - includes 3 plan checks/inspections only Sign - Electrical - see Electrical fees
Re-Roof - MultiFamily Residential, Commercial, Industrial Demolition: Review and inspection of demolition
Re-Roof - Single Family Residential
Wall mounted
Greater than 5,000 sq ft - Each add'l 1,000 sq ft (additional over base)
Building Each $449.00
Building Each $449.00
Building Each $660.00
Building Each $811.00
Building Each $181.00
Building Each $587.00
Building Each $674.00
Building Each $761.00
Building Each $761.00
Building Each $899.00
Building Each $667.00
Building Percentage 65% of New Construction
Fee
Building Each $1,100.00
Building Each $1,375.00
Building Each $413.00
Building Each $550.00
Building Each $413.00
Building Each $620.00
Building Per Day $275.00
Building Each $1,100.00
Building Each $1,100.00
Building Each $1,100.00
each additional section
Address Change (Each Application plus Hourly for large projects) Residential Staging (No Gas Release)
Deputy Inspector Certification Registration
Bleachers per 1000 sq ft
Accelerated Building Records Report
Bleachers each additional 1000 sq ft
Commercial Coach / Manufactured Bldg
above ground
Foundation System for Commercial Coach/Manufactured Bldg Residential Building Records Report
Pool Demolition
Partial Demolition
underground
Vault:
Temporary Certificate of Occupancy
Building Moving Permit
first Section 12'x60' (720 sq ft)
Permit Transfer Processing
Restucco/Siding/Façade
Appeal of Building Administrative Decision to the Board of Appeals
Full Demolition
Manufactured Home Foundation System:
Construction Operation After Hours Application
Building Each $413.00
Building Each $413.00
Building Each $413.00
Building Percentage $0.05
Building Percentage $0.0025 of Valuation
Building Flat Rate $174.00
Building Per Hour Hourly Rate
Building Per Hour Hourly Rate
Building Per Hour $449.00
Building Percentage 0.013% of Valuation
Building Percentage 0.028% of Valuation
Building Percentage 10% of Building Plan Check
Building Percentage 50% of Plan Check Fee
Building Percentage 35% of Building Plan Check
Fee
Building Percentage 25% of Building Plan Check
Fee
Building Percentage 10% of Building Plan Check
Fee
Building Each $63.00
State Energy T-24 plan check fee 25% of Building Plan Check Fee Permit Extension
Summary of Accessibility Upgrades for Commercial Projects Accelerated Plan Check - 50% of the total Plan Check Fee Technology/Training Surcharge
Permit Issuance
Cal Green Plan Check - 10% of Building Plan Check Fee
Records Retention Surcharge (Percent of the all Permit Fees) Accessibility (Disabled Access) Plan Check - 10% of the Building Plan Check Fee
SB 1473 Green Building Standards (BSA)
Reinspection
After Hours Inspection-Per Hour at OT Rate (2 hour minimum) Residential over 3 Stories and Commercial
CA Strong Motion Instrumentation Program (SMIP) :
Housing, Tract Single-Family Dwelling (Repeat without
modifications) - 35% of the total Plan Check Fee
$1 per each $25,000 of valuation or fraction thereof with a minimum of $1
Grading & Shoring
Plan Review/Inspection services not otherwise identified Plan Check Extension
Residential up to 3 Stories
Non-Compliance Inspection-Per Hour
51-1,000 cubic yards Grading Cubic Yard $1,298.00
Grading Cubic Yard $1,609.00
Grading Cubic Yard $1,921.00
Shoring Sq Ft $1,522.00
Shoring Sq Ft $2,146.00
Shoring Sq Ft $2,371.00
Shoring Sq Ft $3,045.00
Electrical Each $63.00
Electrical Per Hour $275.00
Electrical Each $87.00
Electrical Each $362.00
Electrical Each $117.00
Electrical Each $392.00
Electrical Each $406.00
Electrical Each $117.00
3,000 square feet
Single Family Residential :
New Services-Commercial/Industrial and all three phase
(Circuits, Outlets, Switches, etc no sub-panels included):
10,001+ cubic yards
Permit Issuance
5,000 square feet
1,001-10,000 cubic yards
400 Amps or less
Commercial/Industrial and all three phase - "Service Only" change out
1000 Amps or greater
500 square feet
Stand Alone Plan Check - per hour
Electrical Description
400 Amps or less
Single Family Dwelling - New Service/Sub-Panel/Change-Out - 400 amp or less service (includes Circuits, Outlets, Switches, etc) Shoring Plan Check & Permit
New Service-Single Family Single phase Services 600 amps or more
Grading Plan Check & Permit
600 - 800 Amps
1,000 square feet
Electrical Each $392.00
Electrical Each $406.00
Electrical Each $58.00
Electrical Each $195.00
Electrical Each $362.00
Electrical Each $131.00
Electrical Each $131.00
Electrical Each $131.00
Electrical Each $362.00
Electrical Each $724.00
Electrical Each $44.00
Electrical Each $44.00
Electrical Each $44.00
Solar-Photovotaic - Residential
600 - 800 Amps
Generator - Temporary - more than 8 kW
Sub-panels,motor control panels etc.
Commercial/Industrial and all three phase :
600 Amps
800 Amps or greater
Solar-Photovotaic - Commercial/Industrial
400 Amps or less
Temporary Power Pole plus piggy back
Other misc electrical Items :
1000 Amps or greater
Temporary Lighting - Holiday Sale Lots
Temporary Power Pole- additional receptacle pole
Transformer - each
Generator - Permanent - each 1000 amps
Electrical Each $319.00
Electrical Each $181.00
Electrical Each $536.00
Electrical Each $536.00
Electrical Each $674.00
Electrical Each $140.00
Electrical Each $333.00
Electrical Each $195.00
Electrical Each $126.00
Electrical Each $58.00
Electrical Each $58.00
Electrical Each $58.00
Electrical Sq ft $0.74
Electrical Sq ft $0.58
Plumbing Each $63.00
Battery Backup
Plumbing Description
Electrical Sign-per sign 200 sq ft or less/includes 2 sign transformers :
Monument 6 ft high or less and 200 sq ft or less
Light Standard - First 5 poles
EV Charging Station
Wall mounted 200 sq ft or less
Permit Issuance
Residential
Pole/monument sign 200 sq ft or less and 20 ft high or less Each additional 200 sq ft and/or each additional 20 ft height and/or each additional 2 sign transformers
Electrical Meter Reset
Misc Electrical Circuits (added to existing panel)
Swimming pool pump motor
Commercial
Residential Remodel/Addition - per sq ft
Commercial Tenant Improvement - per sq ft
each additional 5 poles
Plumbing Per Hour $275.00
Each
Plumbing $87.00
Each
Plumbing $87.00
Each
Plumbing $87.00
Each
Plumbing $87.00
Each
Plumbing $131.00
Each
Plumbing $44.00
Each
Plumbing $156.00
Each
Plumbing $87.00
Each
Plumbing $156.00
Each
Plumbing $225.00
Each
Plumbing $87.00
Each
Plumbing $156.00
Each
Plumbing $156.00
Each
Plumbing $174.00
MISC fixtures Per fixture
Sewer Cap
Water Repipe
Each Gas Outlet
Solar or Hydronic systems
Gray Water System
Backflow valves
Sump Pump - Per Building
Stand Alone Plan Check Per Hour
Reclaimed water system
Roof Drains - per building
Lawn Sprinkler valve/Backflow device
Building Sewer/Trailer park sewer-per unit
Misc piping per 300 lineal ft
Sewage Ejection System/Grinder Pump - Per Site
Each
Plumbing $417.00
Each
Plumbing $156.00
Plumbing Sq ft $0.65
Plumbing Sq ft $0.56
Mechanical Each $63.00
Mechanical Per Hour $275.00
Mechanical Each $126.00
Mechanical Each $264.00
Mechanical Each $195.00
Mechanical Each $173.00
Mechanical Each $195.00
Mechanical Each $195.00
Mechanical Sq ft $0.65
Commercial Tenant Improvement - per sq ft Mechanical Sq ft $0.56 Mechanical Description
Type 1 or 2 Hood/Duct system
Swimming pool misc piping/retrofit/repair
Miscellaneous Mechanical Permit
Unlisted Equipment(Minimum or by the hour)
Residential Remodel/Addition - per sq ft
Wall Heater
Commercial Tenant Improvement - per sq ft
Dust Collection System
Permit Issuance
Cesspool/Septic Tank Removal
Stand Alone Plan Check - Per Hour
Residential Remodel/Addition - per sq ft
Residential FAU Change out (Same Location)