FTIP#: LA9919399
Subregion ID: South Bay
Project ID#: MM5507.22
Amendment No. 1
FA#: 9200000000M550722
Rev: 03.04.2026 1 Measure M MSP FA Amendment
AMENDMENT No. 1 TO MEASURE M FUNDING AGREEMENT
BETWEEN CITY OF REDONDO BEACH AND THE LOS ANGELES COUNTY
METROPOLITAN TRANSPORTATION AUTHORITY
This Amendment No. 1 to the Funding Agreement (this “Amendment”), is dated July 1, 2026, for reference purposes only, by and between the City of Redondo Beach ("GRANTEE") and the Los Angeles County Metropolitan Transportation Authority ("LACMTA").
RECITALS:
A. GRANTEE and LACMTA entered into that certain Funding Agreement No. 9200000000M550722 dated January 1, 2025, (the "Existing FA"), which Existing FA provides for the Traffic Signal Communications and Network System Phases 2, (the “Project”); and
B. WHEREAS, the LACMTA Board on September 23, 2021, delegated administrative authority to staff to extend the funding lapsing date of the Measure M Funds previously approved to meet environmental, design, right-of-way and construction time frames; and
C. WHEREAS, the GRANTEE and LACMTA desire to extend the lapse date of FY 2023-24 and FY 2024-25 funds to June 30, 2028; and D. GRANTEE and LACMTA desire to amend the Existing FA as provided herein.
FTIP#: LA9919399
Subregion ID: South Bay
Project ID#: MM5507.22
Amendment No. 1
FA#: 9200000000M550722
Rev: 03.04.2026 2 Measure M MSP FA Amendment
AGREEMENT:
NOW, THEREFORE, for good and valuable consideration, the receipt and adequacy of which are hereby acknowledged, the parties hereby agree as follows:
1. Part II, Section 9.1 (v) of the Existing FA is hereby amended by deleting it in its entirety and replacing it with the following: “(v) Expending the Funds granted under this FA for allowable costs by the lapsing date. All Funds programmed for FY 2023-24 and FY 2024-25 are subject to lapse by June 30, 2028.
2. Attachment B of the Existing FA is hereby replaced by Attachment B-1- 1, attached.
3. Attachment C of the Existing FA is hereby replaced by deleting the Project Detailed Schedule and replacing it with the following Revised Project Schedule.
FA Milestones
Original Funding
Agreement Amendment 1 Revised
Project Schedule Project Schedule
Start Date End Date Start Date End Date
Design Solicitation and
Award July 2024 February 2025 April 2024 February 2025
Planning/Preliminary
Design
February
2025 April 2026 February 2025 April 2026
PS&E/Project Closeout May 2026 June 2027 May 2026 June 2028 Total Project Duration
(Months)
35 50
4. Except as expressly amended hereby, the Existing FA remains in full force and effect as originally executed. All rights and obligations of the parties under the Existing FA that are not expressly amended by this Amendment shall remain unchanged.
FTIP#: LA9919399
Subregion ID: South Bay
Project ID#: MM5507.22
Amendment No. 1
FA#: 9200000000M550722
Rev: 03.04.2026 3 Measure M MSP FA Amendment
IN WITNESS WHEREOF, the parties have caused this Amendment No. 1 to the FA to be executed by their duly authorized representatives as of the dates indicated below:
LACMTA:
LOS ANGELES COUNTY METROPOLITAN TRANSPORTATION AUTHORITY By: ________________________________________ Date: ____________________ Stephanie Wiggins
Chief Executive Officer
APPROVED AS TO FORM:
DAWYN R. HARRISON
County Counsel
By: ________________________________________ Date: ____________________ Deputy
GRANTEE:
CITY OF REDONDO BEACH
By: _______________________________________ Date: ____________________ James A. Light
Mayor
APPROVED AS TO FORM:
By: _______________________________________ Date: ____________________ Joy A. Ford
City Attorney
‹·¹·¨ø¥¥ß ·¹²ªº æßÊ ÏººËøÏæÍÛøÔðÏÛÏÓÁøÛÁÁðÈÛ
ÁæÍºÍºªÈ½ÍÁÍ
‹“Ê ›“ „ ϺºËøÏæÍÛøÔðÏÛÏÓÁøÛÁÁðÈÛÁæÍºÍºªÈ½ÍÁÍ
‹ø¨ªÊ ÓðÓÍÚðËÚÓË ÔÔÊÓÌÊðÍ Ûðˢðð˘
SOURCES OF FUNDS FY 2023-24
Qtr 1
FY 2023-24
Qtr 2
FY 2023-24
Qtr 3
FY 2023-24
Qtr 4
FY 2024-25
Qtr 1
FY 2024-25
Qtr 2
FY 2024-25
Qtr 3
FY 2024-25
Qtr 4
TOTAL
BUDGET
LACMTA PROGRAMMED FUNDS:
MEASURE M MSP FUNDS:
Planning Activities/Prog Dev $0
Environmental $0
Design and PS&E $143,662 $143,662
Right-of-Way Acquisition $0
Construction $0
Vehicle Purchase $0
Others $0
Total Measure M $0 $0 $0 $0 $0 $0 $0 $143,662 $143,662
SUM PROG LACMTA FUNDS: $0 $0 $0 $0 $0 $0 $0 $143,662 $143,662 SUM NON-LACMTA FUNDS : $0 $0 $0 $0 $0 $0 $0 $0 $0
PROJECT FUNDING
FY2023-24 and FY2024-25 $0 $0 $0 $0 $0 $0 $0 $143,662 $143,662 SOURCES OF FUNDS FY 2025-26
Qtr 1
FY 2025-26
Qtr 2
FY 2025-26
Qtr 3
FY 2025-26
Qtr 4
FY 2026-27
Qtr 1
FY 2026-27
Qtr 2
FY 2026-27
Qtr 3
FY 2026-27
Qtr 4
TOTAL
BUDGET
LACMTA PROGRAMMED FUNDS:
MEASURE M MSP FUNDS:
Planning Activities/Prog Dev $0
Environmental $0
Design and PS&E $21,961 $148,323 $385,198 $96,997 $275,000 $275,000 $275,000 $275,000 $1,752,479 Right-of-Way Acquisition $0
Construction $0
Vehicle Purchase $0
Others $0
Total Measure M $21,961 $148,323 $385,198 $96,997 $275,000 $275,000 $275,000 $275,000 $1,752,479 SUM PROG LACMTA FUNDS: $21,961 $148,323 $385,198 $96,997 $275,000 $275,000 $275,000 $275,000 $1,752,479 SUM NON-LACMTA FUNDS : $0 $0 $0 $0 $0 $0 $0 $0 $0
PROJECT FUNDING
FY2025-26 and FY2026-27 $21,961 $148,323 $385,198 $96,997 $275,000 $275,000 $275,000 $275,000 $1,752,479 SOURCES OF FUNDS FY2027-28
Qtr 1
FY2027-28
Qtr 2
FY2027-28
Qtr 3
FY2027-28
Qtr 4
FY2028-29 Qtr
1 FY2028-29 Qtr
2 FY2028-29 Qtr
3 FY2028-29 Qtr
4 TOTAL
BUDGET
LACMTA PROGRAMMED FUNDS:
MEASURE M MSP FUNDS:
Planning Activities/Prog Dev $0
Environmental $0
Design and PS&E $183,465 $183,465 $183,465 $183,465 $733,859 Right-of-Way Acquisition $0
Construction $0
Vehicle Purchase $0
Others $0
Total MEASURE M $183,465 $183,465 $183,465 $183,465 $0 $0 $0 $0 $733,859 SUM PROG LACMTA FUNDS: $183,465 $183,465 $183,465 $183,465 $0 $0 $0 $0 $733,859 SUM NON-LACMTA FUNDS : $0 $0 $0 $0 $0 $0 $0 $0 $0
PROJECT FUNDING
FY2027-28 and FY2028-29 $183,465 $183,465 $183,465 $183,465 $0 $0 $0 $0 $733,859 TOTAL LACMTA FUNDS $205,426 $331,788 $568,663 $280,461 $275,000 $275,000 $275,000 $418,662 $2,630,000 TOTAL NON-LACMTA FUNDS $0 $0 $0 $0 $0 $0 $0 $0 $0
TOTAL PROJECT FUNDING $205,426 $331,788 $568,663 $280,461 $275,000 $275,000 $275,000 $418,662 $2,630,000 ATTACHMENT B-1-1 - EXPENDITURE PLAN COST & CASH FLOW BUDGET Measure M MSP - South Bay Highway Operational Improvements Program - Funding Agreement Projects - FA#: 9200000000M550722 Project Title: Traffic Signal Communication and Network System Phases 2 Project ID#: MM5507.22
PROGRAMMED SOURCES OF FUNDS
09.10.19 1 of 1
Measure M Funding Agreement - MSP
Attachment B - Expenditure Plan