January 14, 2021
Tom Crowley, P.E.
Utility Manager
City of Rialto
150 South Palm Avenue
Rialto, CA. 92376
SUBJECT: Proposal to Provide As-Needed Consulting Services
Dear Mr. Crowley,
Dopudja & Wells Consulting (Dopudja & Wells) appreciates the opportunity to submit this proposal to the City of Rialto (City) for the final design of the Lake Rialto Project. A preliminary schematic design has been prepared that demonstrates the conceptual feasibility of the project. Figure 1 represents the approved conceptual design.
Presented below is the proposed final design Scope of Work, estimated budget and schedule. We are proposing to proceed with the same team that assisted us with the preliminary design, which includes, Wilson Mikami, Buck & Associates, A-Teem Electrical Engineers and MNG Geotechnical. Although the City will lead permitting and CEQA efforts, we have also budgeted for our staff to provide as-needed assistance to the City.
Scope of Work
The following tasks comprise the scope of work required for the respective projects outlined above.
Task 1. Civil and Mechanical Construction Plans
Dopudja & Wells’ team members will prepare 90%, 100% and final stamped and signed plans for the LRP, based on the attached Figure 1. We will also prepare a construction cost estimate that will be provided with each of the submittals. The anticipated drawings are as follows:
G01 – Title Sheet with Location Map and Index of Drawings G02 – Abbreviations, General Notes, Legend and Survey Control C01 to C03 – Grading Sheets at a scale of 1 inch – 40 feet C04 to C05 – Grading Details and Cross Sections
C06 to C08 – Pipeline Plan and Profile Sheets
C09 to C11 – Civil Details and Structures
M01 to M03 – Pump Station Mechanical and Electrical Plans M04 – Pump Station Details
E1 to E6 - Electrical Plans and Details
I1 to I2 – Instrumentation Plans
The discharge Pump Station plans are proposed to be a package type pump station. Because the City is negotiating a full summer diversion pump station with IEUA, the timing of the permanent pump station versus completion of the LRP is yet undetermined. A tentative evaluation appears to indicate the completion of the LRP could coincide to the IEUA pump station. In the event the LRP is completed prior to the IEUA summer diversion pump station, we are proposing a package pump station that would allow the LRP to open sooner. To avoid the potential for duplicative pump station designs, and to save unnecessary design expense, Dopudja & Wells is proposing a 65% design of the package pump station for CEQA evaluation of the project. If the LRP and IEUA schedules coincide, this pump station design effort would be paused to save the City on design fees.
Due to the lower elevations of the LRP, a restroom facility would require a sewage pump to remove waste. The anticipated length and volume of the sewage force main would likely result in significant maintenance and potential failure due to clogging. As part of our design, we will explore alternative restroom facilities such as a portable/trailer mount facility with a sump for routine pumping out via the City’s vactor truck.
Task 1 Deliverables: 90%, 100% and final stamped/signed plans.
No PLC or HMI are anticipated for pump station control. No standby generator is anticipated.
Power will be provided from the WWTP. Major modifications to MCCs are not anticipated, Existing WWTP PLC is anticipated to monitor alarm status.
Is anticipated the City will prepare, submit and obtain the necessary permits. Dopudja & Wells has budgeted some as-need assistance to support the City in this effort.
Task 2 Offsite Surveying and Street Parking Plans
Wilson Mikami will assist Dopudja & Wells in preparing the offsite parking plans. For purposes of this proposal, we are utilizing the Agua Mansa (Alternative #3) concept, attached as Figure 2. Because the original onsite surveying did not cover Agua Mansa, some additional surveying is included to cover this area. We anticipate parking will occur west of the Rialto Channel, on the north side of Agua Mansa Road. Our team will prepare 90%, 100% and final stamped and signed plans for the LRP. We will also prepare a cost estimate that will be provided with each of the submittals. The anticipated drawings for this task are as follows:
P01 to P02 – Street Parking Plans
P03 – Miscellaneous Parking Details
Task 2 Deliverables: 90%, 100% and final stamped/signed plans.
Is anticipated the City will prepare, submit and obtain the necessary permits. Dopudja & Wells has budgeted some as-need assistance to support the City in this effort.
Task 3 Landscaping and Irrigation Plans
Buck and Associates will assist Dopudja & Wells in preparing the Plant Palettes, Planting and Irrigation Plans. Our team will prepare 90%, 100% and final stamped and signed plans for the LRP. As part of our scope of work, we will coordinate with local nurseries so the City can contract grow the required vegetation, prior to planting at the LRP.
We will also prepare a cost estimate that will be provided with each of the submittals. The anticipated drawings for this task are as follows:
L01 to L03 – Landscape Planting Plans
L04 – Plant Palette, Quantities and Notes
L04 – Irrigation Plans
Task 3 Deliverables: 90%, 100% and final stamped/signed plans.
Is anticipated the City will prepare, submit and obtain the necessary permits. Dopudja & Wells has budgeted some as-need assistance to support the City in this effort.
Task 4 Hydrology/Hydraulics Report
Dopudja & Wells team members will prepare a Hydrology/Hydraulics Report in conformance with City standards to support the design of the grading and drainage improvements associated with the project. Our team will prepare hydraulic calculations for the inlet pipeline and lake level control structures. The Hydrology/Hydraulic Study will address the existing and ultimate site condition to assure that proposed drainage improvements are compatible with the existing and ultimate development of the site. The Hydrology/Hydraulic Study will be submitted for review as part of the Grading and Improvement Plan submittal.
Task 4 Deliverables: 90%, 100% and final Hydrology/Hydraulics Report.
Is anticipated the City will prepare, submit and obtain the necessary permits. Dopudja & Wells has budgeted some as-need assistance to support the City in this effort.
Task 5 Storm Water Pollution Prevention Plan (SWPPP)
Dopudja & Wells team members will prepare a SWPPP in conformance with the State Water Resource Control Board and City of Rialto requirements. The SWPPP will be prepared prior to commencement of grading and will include sampling and analysis procedures as well as other recent modifications to the general construction storm water permit.
Task 5 Deliverables: Final SWPPP.
Is anticipated the City will prepare, submit and obtain the necessary permits. Dopudja & Wells has budgeted some as-need assistance to support the City in this effort.
Task 6 Technical Specifications
Dopudja & Wells team members will prepare draft and final specification document for bidding and construction of the LRP. The Technical Specifications will be customized for the LRP. The “front End “contracting documents will be provided by the City and be consistent with City procurement standards. We anticipate the City will advertise and procure bids through the City’s normal procurement process.
Task 6 Deliverables: 90%, 100% and final stamped/signed Technical Specifications.
Is anticipated the City will prepare, submit and obtain the necessary permits. Dopudja & Wells has budgeted some as-need assistance to support the City in this effort.
Task 7. Construction Period Engineering Services
Dopudja & Wells team members will provide construction phase engineering support services. These include:
Review and respond to up to six Request for Information Review and respond to up to six Submittals
Review and respond to up to two Contract Change Orders Attend up to eight construction meetings
Geotechnical Engineering assistance during the construction period (up to 40 hours) Landscaping and irrigation system assistance during the construction period (up to 40 hours) Task 7 Deliverables: Miscellaneous response to Requests for Information, Submittals and Contract Change Orders.
Task 8 Project Management
Dopudja & Wells and our team members will provide overall project management to ensure the project remains on budget and schedule.
Task 8 Assumptions: City will be responsible for preparing, submitting, obtaining and associated cost for the necessary permits. A total of 40 hours of as-needed assistance has been budgeted.
Proposed Fee and Schedule
Table 1 below outlines the proposed fee by tasks. Table 2 provides a more detailed schedule for the Lake Rialto.
Table 1 - Fees for Services
Task Description Amount ($)
1 Civil and Mechanical Plans $203,280
2 Offsite Surveying and Street Parking Plans $35,140
3 Landscaping and Irrigation Plans $80,124
4 Hydrology/Hydraulics Report $17,330
5 Storm Water Pollution Prevention Plan (SWPPP) $10,620 6 Technical Specifications $41,860
7 Construction Period Engineering Services $67,070
8 Project Management $54,940
Reimbursables, mileage, travel, etc. (estimated) 7,500
Total $517,864
Table 2 – Lake Rialto Final Design Schedule
Task/Subtask
Mar-2022 Apr-2022 May-2022 Jun-2022 Jul-2022 Aug-2022 Sep-2022 Oct-2022 Nov-2022 Dec-2022 Civil and Mechanical Plans
Offsite Surveying and Street Parking Plans
Landscaping and Irrigation Plans
Hydrology/Hydraulics Report
Storm Water Pollution Prevention Plan (SWPPP)
Technical Specifications
Construction Period Engineering Services
Project Management
City proceeds to bid construction contract
Notes:
Anticipated Notice to Proceed is March 2022
= Presentation to the Water Subcommittee
Thank you for the opportunity to allow Dopudja & Wells to support the City of Rialto on these Exciting Projects.
Sincerely,
Dopudja & Wells Consulting
Stephen Dopudja, P.E.
President/CEO
RCE #65187