Presentation to City CouncilTuesday, March 8, 2022
City of Rialto
Street Overlay & Reconstruction Project
Riverside Avenue from Galway Street to Foothill Boulevard City Project No. 210807 &210807A
Project Location
PROJECT LIMITS: Riverside Avenue between Galway Street and Foothill Boulevard WORK HOURS:Weekdays, Mondays through Fridays, from 7 a.m. to 4 p.m.
At least one lane in each direction will be open at all times, during project construction
Construction Start: Monday, Feb. 7, 2022
Look Ahead Schedule:
Pre-Construction/ Submittals/: Up to Feb. 7, 2022
Survey/Pothole
Concrete Improvement: Feb. 7 to May 18, 2022
Full Street Reconstruction
Outside Lanes: May 18 to July 26, 2022
Inside Lanes: July 26 to Sept. 14, 2022
Close Out: Sept. 14 to Oct. 18, 2022
Tentative Schedule
Project Information Signage
Maintaining Access on Riverside Avenue
Full street reconstruction of outside lanes on Riverside Avenue anticipated to begin in May 2022 and continue through July 2022 Stakeholders (residential and business) will be provided advanced notice via a construction notice flyer (distributed door-to-door) Access to all driveways will be maintained during non-working hours with base material or ramps to respective driveways If access to residences will be impeded during working hours, the team will provide at least one week advanced notice to make contact, provide information and help identify alternate parking locations for impacted stakeholders
Website
Active: bilingual project fact sheet, interactive Google Map, project hotline/email, sign-up form for project database Bi-weekly construction alerts are posted for reference and information is on the City homepage under Latest News Residents/businesses
Attend Famer’s Markets in March/April prior to the start of lane closures and pavement reconstruction in May 2022 Canvassed 9,500 bilingual flyers to all residents and businesses within ½ mile radius of the project corridor Door-to-door business visits to 50 businesses along Riverside Ave., with bilingual flyer and business card Phone calls to nearly 450 businesses, apartments, churches and civic groups within 1 mile of the project area; emailed 66 fact sheets per business request Agencies/schools/key stakeholders
Coordinating with: Rialto Unified School District, Omnitrans, Trucking Association, Fire/Police, first responders (EMR, hospitals); Shared outreach collaterals including fact sheet, website, Google Map link, hotline In contact with these groups and setting meetings to provide additional project information First briefing with Police/Fire held in October 2021; follow-up briefing to be held prior to the start of construction Phone calls to public information office to notify of start of construction and project contact information Request stakeholder emails to add to project database, to receive project information/construction alerts Social media
Bi-weekly construction alerts are posted on City social media accounts Project Hotline, Database and Stakeholder Log
To date, we have 223 subscribers to the project database To date, we have not received any complaints to the Project Hotline Collaterals finalized
Bilingual flyer
Business card
QR code activated
Public Outreach Activities
As of February 28, 2022