Cities Index.
Attachment 1 - CIP List.pdf

Rialto City Council
April 26, 2022

Document
Attachment 1 - CIP List.pdf
Meeting
April 26, 2022
Body
Rialto City Council
Original file
237 KB
Text extracted from the city's file for reading and search. Open the original on legistar.granicus.com. That file is the official record.

Capital Improvement Program
Summary of Projects by Status
Fiscal Year 2021/2022
GREEN Text - Milestone was met
ORANGE(BOLD) Text - Future Date
RED Text - Date Passed, Milestone needs
to be re-established
Project
Number
Category/Phase/Project
(Projects listed in Alphabetical Order)
Project
Number
Project
Manager
Consultant /
Contractor
Constructio
n
Managemen
t &
Inspection
Timely Use of
Funds (TUOF) -
36 months after
award of CON
Grant
Reversion Date Project Budget City Council
Adoption Date
Expenditures/
Encumbrance Remaining Budget
Design Construction
Projects in Planning Stage
1 BASELINE: ACACIA TO MERIDIAN

PARKWAY LANDSCAPE IMPROVEMENTS
Planning Stage Planning Stage 190812 Unassigned NA N/A N/A 200,000$ -$ 200,000$ Measure I 200,000$ 10/8/2019 -$ 200,000$ 2 COMMUNITY CENTER ADA REHAB BLDG
400
• Design for building 400 was awarded on the 21-22
CDBG Annual Action Plan
CB2202 Michael T./Dave
H./Rudy
NA NA NA 331,895$ -$ 331,895$ Community Development Block Grant 331,895$ 331,895$ Projects in Design: (60%)
3 HSIP BASELINE IMPROVEMENTS -

WILLOW TO MERIDIAN
• Design consultant awarded on April 09, 2019
• Anticipated completion of design is March/April 2022
• Anticipated release of Request for Bids (RFB) is
April/May 2022
170812 Michael T./Dave
H.

CNS Engineers
PM: Steve
Hosford
N/A N/A 1,174,800$ 288,122$ 886,678$ Major Capital Grant- HSIP Cycle 8 12/31/2022 6/30/2022* 1,057,320$ 9/12/2017 261,032$ 796,288$ Measure I 117,480$ 9/25/2018 27,090$ 90,390$ 4 HSIP CLASS II BIKE LANES ON MERRILL • Anticipated completion of design is June 2021 • Anticipated release of Request for Bids (RFB) is October/November 2021
170813 Jeff NA NA 218,000$ 59,516$ 158,484$ Major Capital Grant 6/30/2022 196,200$ 1/24/2017 37,716$ 158,484$ Measure I 21,800$ 11/14/2017 21,800$ (0)$ 5 1193 W. MERRILL AVE WIDENING • Design consultant awarded on September February 09, 2021
• Anticipated release of Request for Bids (RFB) is
January 2022
210812 Jeff/ Michael T. Huitt Zollars N/A N/A 330,000$ 47,225$ 282,775$ Measure I 330,000$ 7/27/2021 47,225$ 282,775$ 6 RANDALL AVE WIDENING @ FLOOD

CONTROL CHANNEL
• RFP for design was released on December 17, 2020
• Design consultant awarded on February 23, 2021
• Anticipated completion of design is December
2021/January 2022

210811 Michael T./Dave
H.

Ardurra Group
Inc.

PM: Mark
Lewis
N/A N/A 2,500,000$ 135,039$ 2,364,961$ Transportation DIF 2,500,000$ 8/11/2020 135,039$ 2,364,961$ 7 STREET OVERLAY PEPPER AVE JOINT

PROJECT WITH CITY OF SAN

BERNARDINO (LEAD)
• RFP for design will be released in October/November
2020
• City will be part of the selection panel for the
consultant selection
• Anticipated completion of design is January
/February 2022
190804 Jeff/Michael T. N/A N/A 2,900,000$ 9,273$ 2,890,727$ Gas Tax 1,600,000$ 6/25/2019 -$ 1,600,000$ Measure I 1,300,000$ 10/8/2019 9,273$ 1,290,727$ 8 STREET OVERLAY & RECONSTRUCTION: • RFP for Design was released on August 13, 2020 • Award of Design on September 22, 2020
• Anticipated Design completion in April/May 2021

• Anticipated to begin Construction in August
/September 2021
210804 Jeff/Michael T. N/A N/A 10,553,000$ 1,034,120$ 9,518,880$ Gas Tax 400,000$ 8/11/2020 6,329$ 393,671$ Measure I 1,201,000$ 10/8/2019 1,027,791$ 173,209$ SB-1 3,802,000$ 6/25/2019 -$ 3,802,000$ Waste Management Fund 5,150,000$ 6/25/2019 -$ 5,150,000$ Projects in Design: (90%)
9 CITY-WIDE SPEED SURVEY AND TRUCK

ROUTE STUDY
• RFP for Design was released in March 2020
• Awarded study on September 22, 2020
• Anticipated completion of study is February/March
2022
180002 Michael T./Rudy/
Dave H./Daniel
Casey
Advantec
PM: John
Dorado
N/A N/A 139,500$ 127,595$ 11,905$ Measure I 139,500$ 11/14/2017 127,595$ 11,905$ 10 OVERLAY RECONSTRUCTION:

RIVERSIDE SOUTH OF I-10
• RFP for Design was released on August 13, 2020
• Design consultant awarded on September 22, 2020
• Anticipated completion of constructability review
and value engineering is April/May 2021

• Bid(s) rejected in August 2021
• Project is currently in Constructability Review
• Anticipated to begin Construction in June/July 2022
** Requested $3.0M in the FY22 Transportation- HUD
Appropriations Act.
*Any federal award would reduce the contribution of other City funding.
180807 Jeff Advanced Civil
Technologies
PM: Jamal
Samal
South Star N/A N/A 9,103,354$ 816,595$ 8,286,759$ Major Capital Grant(CPNA) N/A 3,907,354$ 6/25/2019 800,453$ 3,106,901$ Measure I 3,596,000$ 10/8/2019 16,142$ 3,579,858$ Project Status
1 LAST UPDATED:11/9/2021
Capital Improvement Program
Summary of Projects by Status
Fiscal Year 2021/2022
GREEN Text - Milestone was met
ORANGE(BOLD) Text - Future Date
RED Text - Date Passed, Milestone needs
to be re-established
Project
Number
Category/Phase/Project
(Projects listed in Alphabetical Order)
Project
Number
Project
Manager
Consultant /
Contractor
Constructio
n
Managemen
t &
Inspection
Timely Use of
Funds (TUOF) -
36 months after
award of CON
Grant
Reversion Date Project Budget City Council
Adoption Date
Expenditures/
Encumbrance Remaining Budget
Design Construction
Project Status
Transportation DIF 1,600,000$ 1,600,000$
11 SR-210 ALDER AVENUE INTERCHANGE • Lewis-Hillwood Rialto (LHR) is the lead on the project
• Anticipated completion of environmental is
January/February 2021, pending funding
• 95% plans submitted to Caltrans
• Anticipated completion of design in March 2022
• Requested $3.0M in the FY22 Transportation- HUD
Appropriations Act.
*Any federal award would reduce the contribution of other City funding.
200808 Michael T. Lewis Hillwood
Rialto
PM: Glen
Crosby
N/A N/A 5,601,436$ 1,192,060$ 4,409,376$ Fair Share 5,601,436$ 11/10/2020 1,192,060$ 4,409,376$ 12 TERRA VISTA NEIGHBORHOOD SAFE

ROUTES TO SCHOOL (SRTS)

IMPROVEMENTS
• RFP for Design will be released in October 2020
• Design consultant awarded on December 08, 2020
• Anticipated completion of design is
November/December 2021
• Anticipated to begin Construction in March/April
2022
200813 Michael T./Dave
H.

TKE
Engineering
PM: Terry R.
663,000$ 69,642$ 593,358$ SB-1 ATP Cycle 4 6/30/2022 663,000$ 7/23/2019 69,642$ 593,358$ 13 NEW TRAFFIC SIGNAL @ AYALA &

FITZGERALD
• RFP for Design will be released in October 2020
• Design consultant awarded on December 08, 2020
• Anticipated completion of design is October 2021
• Anticipated to begin Construction in
January/February 2022
190810 Michael T./Dave
H.

TKE
Engineering
PM: Terry R.

N/A N/A 300,000$ 47,180$ 252,820$ Fair Share 300,000$ 6/25/2019 47,180$ 252,820$ 14 BASELINE STORM DRAIN: TAMARIND/ TO
CACTUS 3 BASIN
• Phase I- Design Complete •Phase I: Anticipated to begin Construction in March 2022
•Phase II: Pending budget programming Using Storm
Drain DIF
170700 Michael T./Dave
H.

Huitt-Zollars
PM: Johny
Murad/ Remi
Candaele
N/A N/A 12,500,000$ 622,677$ 11,877,323$ Storm Drain DIF 12,500,000$ 6/26/2018 622,677$ 11,877,323$ 15 FACILITIES PAVEMENT PROGRAM -

CEMETERY
•Design completed in March 2021

TBD 210209 Michael T./Terry
R.

NA NA 643,449$ -$ 643,449$ General Projects Fund 643,449$ 6/25/2019 -$ 643,449$ 16 CACTUS TRAIL PARKING LOT • Pending City Council direction for the parking lot location and available funding
• Anticipated completion of design is March/April 2022
• Anticipated to begin Construction in June /July 2022 170802 Michael T./Dave H.
500,000$ -$ 500,000$ Open Space DIF 500,000$ 7/11/2017 -$ 500,000$ Projects in Design: (100%) Contract Advertisement and Award 17 CACTUS TRAIL • Authorization to release of Request for Bids (RFB) in November/December 2020
• Anticipated to begin Construction in February 2021
• Caltrans Deadline for the award of Construction
December 2021 (Pending Time Extension)
170801 Michael T./Dave
H.

Construction
Contract has not
been awarded
2,560,000$ 357,625$ 2,202,375$ Open Space DIF 1,300,000$ 6/25/2019 357,625$ 942,375$ SB1 - ATP Cycle 3 Grant 1,260,000$ 4/10/2018 -$ 1,260,000$ 18 PUBLIC RIGHT OF WAY-ADA TRANSITION
PLAN
• RFP for plan/design was released in September 2021
• Anticipated award for plan/design is December 2021
• Anticipated completion of plan/design is
November/December 2022

190808 Michael T./Dave
H.

N/A N/A N/A 350,000$ -$ 350,000$ Measure I 350,000$ 10/8/2019 -$ 350,000$ 19 FACILITIES ADA TRANSITION PLAN • RFP for plan/design was released in September 2021 • Anticipated award for plan/design in December 2021
• Anticipated completion of plan/design is
November/December 2022

190210 Michael T./Dave
H.

NA N/A N/A 500,000$ -$ 499,781$ Major Capital Grant 500,000$ 8/14/2018 219$ 499,781$ 20 CURB, GUTTER, SIDEWALK & ADA- CDBG
2022
• RFB was released in October 2021 Anticipated to begin Construction in CB2201 Jeff/Rudy/ Michael T.

NA NA 121,435$ -$ 121,435$ Community Development Block Grant 121,435$ 121,435$ 2 LAST UPDATED:11/9/2021
Capital Improvement Program
Summary of Projects by Status
Fiscal Year 2021/2022
GREEN Text - Milestone was met
ORANGE(BOLD) Text - Future Date
RED Text - Date Passed, Milestone needs
to be re-established
Project
Number
Category/Phase/Project
(Projects listed in Alphabetical Order)
Project
Number
Project
Manager
Consultant /
Contractor
Constructio
n
Managemen
t &
Inspection
Timely Use of
Funds (TUOF) -
36 months after
award of CON
Grant
Reversion Date Project Budget City Council
Adoption Date
Expenditures/
Encumbrance Remaining Budget
Design Construction
Project Status
21 BIRDSALL PARK IMPROVEMENTS • Anticipated Design completion in October/November 2020

• Anticipated release of Request for Bids (RFB) in
January 2022
210304 Michael T. 1,400,000$ 826$ 1,399,174$ General Projects Fund 1,400,000$ 8/14/2018 826$ 1,399,174$ Non-Infrastructure Plan (Grant Funded/Measure I)
22 MSRC BIKE SHARING PLAN &

IMPLEMENTATION
• Design awarded on August 14, 2018
• RFP was re-issued in September 2020 to secure
consultant for the Installation, maintenance and operations as City pursues $1,000,000 grant for a more effective
program
• Program is scheduled to begin in early March/April
2022
170810 Michael T. Alta Planning 1,411,043$ 193,831$ 2,217,212$ AQMD 411,043$ 3/27/2018 193,831$ 217,212$ CLEAN MOBILITY OPTIONS GRANT 1,000,000$ -$ 2,000,000$ 23 SAFE ROUTES FOR ACTIVE PLAY WORK
& LIVE
• RFP for development of plan will be released in
September/October 2020
• Award on November 10, 2020 to meet Caltrans award
deadline of December 05,2020
• Program began in December 2020/January 2021 200812 Amy C. Safe Moves 549,000$ 319,090$ 229,910$ SB-1 - ATP Cycle 4 6/30/2024 549,000$ 7/23/2019 319,090$ 229,910$ 24 TRAFFIC MGT CENTER PLAN TBD TBD Michael T. 311,578$ 2,300$ 309,278$ Major Capital Grant N/A 311,578$ 8/14/2018 2,300$ 309,278$ Projects Ready to Begin Construction
25 OVERLAY RECONSTRUCTION: FROM I-
210 TO FOOTHILL BLVD.
• RFP for Design was released on August 13, 2020
• Award of Design on September 22, 2020
• Anticipated Design completion in April/May 2021

• Construction Contract Awarded September 14, 2021 210807 Jeff/Michael T. Sequel Contractors
AECOM N/A N/A 7,700,000$ -$ 7,700,000$ Gas Tax 1,400,000$ 1,400,000$
Measure I 600,000$ 600,000$
SB-1 5,700,000$ 5,700,000$
Projects in Construction: Programmed for Completion by December 2021 26 CURB, GUTTER, SIDEWALK
IMPROVEMENTS 2021
• Design In-House • Release of Request for Bids (RFB) in September 2020 • Construction Contract Awarded on November 10, 2020
• Anticipated Construction completion in
October/November 2021
210809 Jeff/Michael T. Onyx Paving
Company, Inc.

TRC
Engineers
N//A N/A 1,832,040$ 1,723,435$ 108,605$ Gas Tax 499,000$ 6/25/2019 499,000$ -$ General Projects Fund 1,315,000$ 8/11/2020 1,224,435$ 90,565$ Measure I 3,608$ -$ 3,608$ TDA Article 3 14,432$ 1/14/2020 -$ 14,432$ 27 HSIP SIGNAL IMPROVEMENTS- FOUR

INTERSECTIONS OF PROTECTED-ONLY

LEFT TURN SIGNAL PHASING
• Construction Contract Awarded on September 22, 2020
• Anticipated Construction completion in November
/December 2021
• Construction of Schedule C, Cedar/Etiwanda Location
Approved by City Council June 08, 2021
170811 Michael T./Rudy Elecnor Belco
Electric
NA 1,290,430$ 1,141,716$ 148,714$ Major Capital Grant - HSIP Cycle 8 6/30/2023 1,290,430$ 3/28/2017 1,141,716$ 148,714$ 28 RANDALL AVE WIDENING - BETWEEN

CACTUS/RIVERSIDE
•Anticipated Construction completion in March 2022.
***Grant TUOF from 03-12-2019 is 03-01-2022**
140809 Michael T./Rudy JM Olvera
PM: Rick
Garabedian
Berg &
Associates
PM: Cass
Hamvas
4,445,500$ 4,364,058$ 81,442$ Measure I 1,113,000$ 2/25/2014 1,147,923$ (34,923)$ SB-1 Local Partnership Program
Grant(LPP)
3/1/2022 6/30/2023 1,145,500$ 5/8/2018 997,662$ 147,838$ Transportation DIF 2,187,000$ 3/12/2019 2,218,473$ (31,473)$ 29 ALDER WIDENING •Anticipated Construction completion in October/November 2021
***Grant TUOF from 03-12-2019 is 03-01-2022**
140801 Michael T./Rudy JM Olvera
PM: Rick
Garabedian
Berg &
Associates
PM: Cass
Hamvas
9,246,282$ 8,348,089$ 898,193$ General Projects Fund 1,070,000$ 2/25/2014 560,611$ 509,389$ 3 LAST UPDATED:11/9/2021
Capital Improvement Program
Summary of Projects by Status
Fiscal Year 2021/2022
GREEN Text - Milestone was met
ORANGE(BOLD) Text - Future Date
RED Text - Date Passed, Milestone needs
to be re-established
Project
Number
Category/Phase/Project
(Projects listed in Alphabetical Order)
Project
Number
Project
Manager
Consultant /
Contractor
Constructio
n
Managemen
t &
Inspection
Timely Use of
Funds (TUOF) -
36 months after
award of CON
Grant
Reversion Date Project Budget City Council
Adoption Date
Expenditures/
Encumbrance Remaining Budget
Design Construction
Project Status
SB-1 Local Partnership Program
Grant(LPP)
3/1/2022 6/30/2023 1,145,500$ 5/8/2018 1,145,500$ -$ Storm Drain DIF 1,152,160$ 3/12/2019 1,152,160$ -$ Transportation DIF 5,878,622$ 3/12/2019 5,489,818$ 388,804$ 30 EASTON SIDEWALK IMPROVEMENT

BETWEEN ACACIA TO HIGHLAND
• RFP for Design was released in August 2020
• Design consultant awarded on September 22, 2020
• Anticipated Design completion in January/February
2021
• Construction Contract awarded on September 22, 2020
• Estimated to be completed by December 2021
190811 Monae P.
/Michael T.

EBS General
Engineers
TKE
Engineering
952,875$ 877,852$ 75,023$ Measure I 726,875$ 10/8/2019:
08/10/2021
651,852$ 75,023$
TDA Article 3 12/31/2022 226,000$ 1/14/2020 226,000$ -$ 31 COMMUNITY CENTER ADA REHAB BLDG
200 & 300
•Construction completion for Building 200 in
September/October 2020 - (Project Accepted by City
Council and NOC filed on 11-10-2020)
• Anticipated to begin Construction of Building 300 in October 2020
• Anticipated Construction completion for Building 300 in November/December 2021
CB1804 Michael T./Rudy RS
Construction &
Development,
Inc.

PPM Group,
Inc.

NA NA 1,730,350$ 1,460,919$ 269,431$ Community Development Block Grant 1,555,350$ 12/10/2019 1,431,283$ 124,067$ General Projects Fund 175,000$ 12/10/2019 29,636$ 145,364$ 32 FIRE STATION 205 (PERMANENT) • NOC for City Council Approval September 14, 2021 190211 Michael T. Robert Clapper Construction
Services, Inc.

STK
Engineers,
Inc.

NA NA 4,785,000$ 4,155,008$ 629,992$ Fire DIF 3,230,000$ 8/14/2018 3,431,214$ 786$ General Facilities Development Fund 1,555,000$ 8/14/2018 723,794$ 629,206$ 33 MSRC LPP- ELECTRIC CHARGE

STATION/FLEET
• RFP will be released in November 10, 2020
• Anticipated award in January/February 2021
• Anticipated completion in August/September 2021 190209 Amy/Tony 313,307$ 200,660$ 112,647$ AQMD 5/13/2024 313,307$ 7/24/2018 200,660$ 112,647$ Non-Infrastructure Projects (Grant Funded/Measure I): Programmed for Completion by December 2021 34 PACIFIC ELECTRIC TRAIL FEASIBILITY
STUDY
• RFP for development of plan was released in January
2020
• Design awarded on September 22, 2020
• Feasibility study will be presented to EDC on
November 17, 2021
• Anticipated completion of study in February 2021
200811 Michael T. Alta Planning 299,000$ 270,485$ 28,515$ Measure I 34,295$ 10/8/2019 5,780$ 28,515$ SB-1 Sustainable Communities Grant 2/28/2022 264,705$ 6/11/2019 264,705$ -$ Completed Project
35 ETIWANDA CORRIDOR - TDA/ATP/MSRC Project Accepted by City Council and NOC filed on 01- 12-2021
Michael T./Rudy Vido
Samarzich
INC.

PPM Group,
Inc.
1,300,132$ 1,288,612$ 11,520$ AQMD 85,013$ 3/27/2018 85,013$ -$ Major Capital Grant 6/30/2022 629,098$ 7/11/2017 635,674$ (6,576)$ Measure I 450,000$ 9/25/2018 431,904$ 18,096$ TDA Article 3 12/31/2021 136,021$ 7/11/2017 136,021$ -$ 36 INSTALLATION OF TRAFFIC SIGNAL @

PEPPER & WINCHESTER

DRIVE/TERRACE ROAD
•Anticipated Construction completion in August 2021
(Pending Long Lead Item)
Jeff KDC Inc.,
Dynalectric
TKE
Engineering
350,000$ 346,500$ 3,500$ Measure I N/A N/A 350,000$ 10/8/2019 346,500$ 3,500$ 37 VALLEY/CACTUS/LINDEN WIDENING Project Accepted by City Council and NOC filed on 12- 08-2020
Michael T./Rudy H & H General
Contractors,
INC
Transtech
Engineers,
Inc.

N/A N/A 2,254,760$ 2,227,060$ 27,700$ Measure I 1,400,000$ 7/23/2019 1,372,300$ 27,700$ Transportation DIF 854,760$ 2/25/2014 854,760$ -$ 38 SAFETY LIGHTS CONVERSION TO LED • Conversion completed March 2021 Amy/Tony Siemens N/A N/A 134,125$ 116,125$ 18,000$ Street Lighting District 134,125$ 6/25/2019 116,125$ 18,000$ 39 BUD BENDER PARK BALL FIELD FENCE •Construction will be completed in September 2020 - (Project Accepted by City Council and NOC filed on 11-10- 2020)
Michael T. RS
Construction &
Development,
Inc.

PPM Group,
Inc.
178,765$ 182,244$ (3,479)$ Community Development Block Grant 178,765$ 12/10/2019 182,244$ (3,479)$ 4 LAST UPDATED:11/9/2021
Capital Improvement Program
Summary of Projects by Status
Fiscal Year 2021/2022
GREEN Text - Milestone was met
ORANGE(BOLD) Text - Future Date
RED Text - Date Passed, Milestone needs
to be re-established
Project
Number
Category/Phase/Project
(Projects listed in Alphabetical Order)
Project
Number
Project
Manager
Consultant /
Contractor
Constructio
n
Managemen
t &
Inspection
Timely Use of
Funds (TUOF) -
36 months after
award of CON
Grant
Reversion Date Project Budget City Council
Adoption Date
Expenditures/
Encumbrance Remaining Budget
Design Construction
Project Status
40 COMMUNITY CENTER BASKETBALL

RESURFACE
•Construction will be completed in September 2020 -
(Project Accepted by City Council and NOC filed on 11-10- 2020)
Michael T. RS
Construction &
Development,
Inc.

PPM Group,
Inc.
264,690$ 260,540$ 4,150$ Community Development Block Grant 264,690$ 12/10/2019 260,540$ 4,150$ 41 FRISBIE PARK EXPANSION •Anticipated Construction completion in October/November 2020 (Project Accepted by City
Council and NOC filed on 02-09-2021)
Michael T. RC Graves
Construction,
Inc.

Griffin
Structures
20,113,981$ 18,954,440$ 1,159,541$ General Projects Fund 2,599,786$ 2/12/2019 1,235,260$ 1,364,526$ Park DIF 17,514,195$ 2/12/2019 17,719,180$ (204,985)$ Design 4,710,000$ 465,331$ 4,244,669$ 42 COMMUNITY GARDEN ACROSS FROM

CITY HALL
• Anticipated Construction completion in October 2020 Amy/Tony 250,000$ 106,880$ 143,120$ Waste Management Fund 250,000$ 6/25/2019 106,880$ 143,120$ 43 HVAC REPLACEMENT PROGRAM • Anticipated Construction completion in June 2021 Tony NA NA 100,000$ 36,830$ 63,170$ General Projects Fund 100,000$ 6/25/2019 36,830$ 63,170$ 44 TRAFFIC SIGNAL COORDINATION

UPGRADE
• San Bernardino County Transportation Authority
(SBCTA) and the City of Rialto are working in partnership to maintain the system corridors
• San Bernardino County Transportation Authority
(SBCTA) is the lead on the project
• Anticipated Completion January 2021 Savat 200,000$ 159,120$ 40,136$ Measure I 200,000$ 9/26/2017 159,120$ 40,136$ 45 CLIMATE ADAPTATION PLAN • RFP for development of plan was released in 2018 • Awarded on May 14, 2019
• Plan accepted by City Council September 2021 Michael T. Dudek 395,500$ 323,933$ 71,567$ Measure I 45,500$ 9/25/2018 22,773$ 22,727$ SB-1 9/30/2021 350,000$ 5/14/2019 301,160$ 48,840$ 5 LAST UPDATED:11/9/2021

← All documents from this meeting