CITY OF RIALTO

ON-CALL PROFESSIONAL SERVICES AGREEMENT
Task Order No. 3 - Construction Management Support Sevices for City Project No: 210804 "STREET OVERLAY AND RECONSTRUCTION - Various Streets" Scope of Services: Resident Engineering, Inspection, Public Outreach and Material Testing PreScience Corporation
October 18, 2022
Task 1 Task 2 Task 3 Task 4
Project Setup Pre-
Construction Construction Post-
Construction
Project Assignment Total
Hours Billing Rate Total Cost
Project Manager As-Needed 40 136 20 196 256.16$ 50,208.19$ Resident Engineer 176 352 1,584 352 2,464 228.04$ 561,888.98$ Construction Inspector 1 (ARE) 176 352 1,584 352 2,464 174.38$ 429,679.81$ Construction Inspector 2 176 176 1,584 176 2,112 167.68$ 354,131.71$ Construction Inspector 3 176 1,584 176 1,936 152.03$ 294,322.80$ Construction Inspector 4 1,440 1,440 152.03$ 218,917.79$ Office Engineer 176 352 1,584 352 2,464 96.13$ 236,874.77$ Public Relations (Manager) 80 80 792 952 152.03$ 144,728.98$ Public Relations (Officer) As-Needed 80 792 872 111.78$ 97,475.65$ A: Subtotal PRIME Construction Management 2,388,228.67$ Materials Testing @ 1.6% of Cost - - 520,000.00$ -
B: Subtotal Construction Management Support: 520,000.00$ 31,200.00$
1,000.00$
C: Subtotal OTHER 32,200.00$
A + B + C: Total Construction Management Costs: 2,940,429$ Surveying Services 50,000.00$
- -
A + B + C + D: Total Construction Management Costs 2,990,429$ Notes and Assumptions:
1 Project Construction Cost is estimated to be $32,000,000 2 Construction duration is estimated at 9 months.
3 Overtime and weekend work is not included. Overtime work to be pre-authorized by City Project Manager. 4 Cost proposal and invoicing is subject to prevailing wage rates. 5 Project Setup consist of; but not limited to, PR website, office setup, project field measurements & photos, documentation existing conditions, scheduling, etc. 6 Project team will support Public Outreach effort, however dedicated public outreach staff on a part-time as-needed basis will be provided upon City's request. 7 Field Surveying support may be required for verification purposes within improvements.

Surveying Crew cost averages $2000 (4 hour minimum), however survey crew will be provided on a part-time (as-needed basis), upon City's request. 8 Office Space rentals for the duration of 1 year
ODCs
D: SPECIALTY SERVICES (OPTIONAL - IF NEEDED)
Phase
Hours
A: PRIME
B: CONSTRUCTION SUPPORT
C: OTHER
ODCs - Office Space @ $2,600/mo