ATTACHMENT 1
BID SUMMARY
City of Rialto
Bid Results for Project J&K Auto Body Demolition Project, 230205 (23‐028) Issued on 03/08/2023
Bid Due on April 11, 2023 3:00 PM (PDT)
Exported on 04/11/2023
Line Totals (Unit Price * Quantity)
Unit Price Total Unit Price Total Unit Price Total Unit Price Total Unit Price Total Unit Price Total 1 Mobilization LS 1 $18,300.00 $18,300.00 $5,500.00 $5,500.00 $7,500.00 $7,500.00 $20,000.00 $20,000.00 $17,112.00 $17,112.00 $22,000.00 $22,0 00.00 2 SWPPP / Erosion Control LS 1 $2,500.00 $2,500.00 $28,820.00 $28,820.00 $4,760.00 $4,760.00 $7,500.00 $7,500.00 $24,950.00 $24,950.00 $5,000.00 $5,000.00 3 Traffic Control LS 1 $2,500.00 $2,500.00 $2,750.00 $2,750.00 $3,500.00 $3,500.00 $6,000.00 $6,000.00 $6,398.00 $6,398.00 $2,000.00 $2,000.00 4 Clearing and Grubbing LS 1 $1,000.00 $1,000.00 $1,100.00 $1,100.00 $12,500.00 $12,500.00 $5,000.00 $5,000.00 $1,624.00 $1,624.00 $2,000.00 $2,000.00 5 Temporary Construction Fencing LS 1 $6,600.00 $6,600.00 $10,120.00 $10,120.00 $12,500.00 $12,500.00 $9,000.00 $9,000.00 $17,658.00 $17,658.00 $7,500.00 $7,500.00 6 Hazardous Building Materials Abatement LS 1 $14,000.00 $14,000.00 $6,506.00 $6,506.00 $33,355.25 $33,355.25 $38,000.00 $38,000.00 $32,852.00 $32,852.00 $48,000.00 $48,000 .00 7 Unclassified Fill and Final Grading LS 1 $1,500.00 $1,500.00 $13,227.00 $13,227.00 $12,000.00 $12,000.00 $15,000.00 $15,000.00 $44,200.00 $44,200.00 $2,000.00 $2,000.00 8 Remove Existing CMU Masonry "J&K Auto
Body" Building, Garage Overhang
Structures, and Foundations LS 1 $1,500.00 $1,500.00 $23,050.00 $23,050.00 $43,828.56 $43,828.56 $30,000.00 $30,000.00 $45,150.00 $45,150.00 $145,155.00 $145 ,155.00 9 Remove Existing Steel Framed Portable
Structure(s) LS 1 $1,500.00 $1,500.00 $550.00 $550.00 $2,506.75 $2,506.75 $28,000.00 $28,000.00 $4,224.00 $4,224.00 $2,500.00 $2,500.00 10 Remove Existing Corrugated Metal Framed
Shed / Garage LS 1 $9,000.00 $9,000.00 $2,013.00 $2,013.00 $9,481.25 $9,481.25 $17,000.00 $17,000.00 $23,408.00 $23,408.00 $2,500.00 $2,500.00 11 Remove Existing Wood Framed / Stucco
Structure LS 1 $14,000.00 $14,000.00 $4,713.00 $4,713.00 $6,290.00 $6,290.00 $10,000.00 $10,000.00 $16,845.00 $16,845.00 $16,768.00 $16,768.0 0 12 Remove Existing Asphalt Concrete
Pavement SY 584 $4.90 $2,861.60 $9.50 $5,548.00 $40.35 $23,564.40 $20.00 $11,680.00 $9.31 $5,437.04 $22.00 $12,848.00 13 Remove Existing Portland Cement Concrete SY 602 $6.89 $4,147.78 $12.60 $7,585.20 $40.35 $24,290.70 $13.00 $7,826.00 $8.60 $5,177.20 $22.00 $13,244.00 14 Remove Existing Wrought Iron Fence, Gate,
Chain Link Fence and Footing LF 1250 $5.07 $6,337.50 $11.00 $13,750.00 $9.50 $11,875.00 $10.00 $12,500.00 $4.53 $5,662.50 $10.00 $12,500.00 15 Remove Existing 6' High Concrete Masonry
Unit (CMU) Wall and Footing LF 389 $10.87 $4,228.43 $11.00 $4,279.00 $9.50 $3,695.50 $10.00 $3,890.00 $23.00 $8,947.00 $5.00 $1,945.00 16 Remove Existing Concrete Panel Fence and
Footing LF 115 $21.75 $2,501.25 $11.00 $1,265.00 $9.50 $1,092.50 $50.00 $5,750.00 $18.75 $2,156.25 $10.00 $1,150.00 17 Remove Existing Vinyl Panel Fence and
Footing LF 112 $22.00 $2,464.00 $11.00 $1,232.00 $9.50 $1,064.00 $17.00 $1,904.00 $1.00 $112.00 $5.00 $560.00 18 Remove Existing Steel Structure LF 64 $54.53 $3,489.92 $11.00 $704.00 $9.50 $608.00 $80.00 $5,120.00 $2.50 $160.00 $10.00 $640.00 19 Remove Existing Overhead Light and Pole EA 2 $750.00 $1,500.00 $550.00 $1,100.00 $2,300.00 $4,600.00 $1,000.00 $2,000.00 $174.00 $348.00 $500.00 $1,000.00 20 Remove Existing Sign and Posts EA 1 $1,500.00 $1,500.00 $110.00 $110.00 $3,700.00 $3,700.00 $1,000.00 $1,000.00 $765.00 $765.00 $500.00 $500.00 21 Furnish and Install "No Dumping / No
Trespassing" Signs EA 11 $230.00 $2,530.00 $110.00 $1,210.00 $500.00 $5,500.00 $1,000.00 $11,000.00 $280.00 $3,080.00 $50.00 $550.00 22 Furnish and Install 3" Thick Wood Mulch CY 417 $15.00 $6,255.00 $53.00 $22,101.00 $6.20 $2,585.40 $15.00 $6,255.00 $102.50 $42,742.50 $100.00 $41,700.00 23 Furnish and Install Fiber Rolls LF 1485 $1.68 $2,494.80 $3.60 $5,346.00 $3.10 $4,603.50 $4.00 $5,940.00 $5.35 $7,944.75 $4.00 $5,940.00 24 Field Orders LS 1 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $30,000.00 $30,000. 00 Subtotal $142,710.28 $192,579.20 $265,400.81 $290,365.00 $346,953.24 $378,000.00 Total $142,710.28 $192,579.20 $265,400.81 $290,365.00 $346,953.24 $378,000.00 Interior Demolition, Inc. AD Improvements, Inc. California Building Evaluation & Construction Inc. Resource Environmental, Inc.Ampco North, Inc.Item Num Description Unit of
Measure Quantity Unlimited Environmental, Inc.
Attachment 1 - Bid Summary.pdf
Rialto City Council
April 25, 2023
- Document
- Attachment 1 - Bid Summary.pdf