WASTEWATER FIP PROJECT STATUS
Status of Completion (CD, SCD, FCWA, FCWA Cost Estimate/Consultant Billed at Project No. Title Construction, Complete, Canceled, CA Cost Estimate Notes/Explanation Rescoping) Completion
51 WWTP Improvements Complete $17,799,000.00 $30,452,424.00 Project completed September 2020.

Sewer Main Replacement CD/Canceled $2,153,000.00 $13,080.00 Flow Studies determined no need for a project.

Sewer Main Replacement Canceled ,506,000. $0.00 Project put on hold due to redesign and Master Plan completion.

Sewer Main Replacement Complete 69,000. $0.00 Project construction is complete - DIF funds used for construction.

Sewer Main Replacement CD/Canceled 3550001
Sewer Main Replacement CD/Canceled
57 WWTP FOG Modifications Canceled S865,000.00
SA Manhole Rehabs Yrs.1&2 Complete $211,000.00
SA Manhole Rehabs Yr. 3 Complete $115,000.00
SA Manhole Rehabs Yr. Complete
SA /anhole Rehabs Yr. Complete 51200001 505310 era comped near 26 2 males repaired.

SB Main Cleaning and Lining Yr.1-2 Canceled $624,000.00 $0.00 Point repair and line replacement recommendations are under review and will be provided to the City for consideration.

SB Main Cleaning and Lining Yrs.3-5 Canceled $1,935,000.00 $0.00 Data for 2016 will be reviewed by March 2017 and next phase of repair recommendations developed by Veolia. sC Studies Canceled $624,000.00 $0.00 If future system developments require the need for studies, source of funding will be determined.

S1.1* Digester 1 Complete N/A $384,020.00 Project completed April 2015.

S8* Emergency Repairs at WWTP Complete $305,661.66) Project consisted of cleaning and repairing airline and diffusers in aeration basin #3 and basin #4.

Total (Wastewater) $28,066,000.00 $31,749,869.66
(Over)/Under CA ($3,683,869.66)
_Completed Projects on Original FIP List
anceled Project on Original FIP Li
completed Projects Not on Original FIP Li
FIP Project Status Summary 20220124 Recap.xIsx 2 1/24/2023