CITY OF RIALTO

ON-CALL PROFESSIONAL SERVICES AGREEMENT
Task Order No. 9 - Construction Management Support Services for City Project No: 240802 "VARIOUS STREETS - PHASE II" Scope of Services: Resident Engineering, Inspection, Electrical, Public Outreach and Material Testing PreScience Corporation
January 11, 2024
Total
Hours Billing Rate Total
Task 4
Post-
Constructi
on
Project Assignment Total
Hours
Rate
Non Prev Wage
Rate
Prevailing Wage
Rate
Prev Wage OT Total Cost
Resident Engineer / Project
Manager 176 1,408 241.91$ 340,609.28$ Construction Inspector 1 176 1,584 165.57$ 165.57$ 223.06$ 262,262.88$ Construction Inspector 2 176 1,408 134.24$ 144.87$ 200.98$ 203,976.96$ Construction Inspector 3 400 170.00$ 68,000.00$ - -$

- -$

874,849.12$
Material Testing - - 100,000.00$
CPM Scheduler 30 160 20 210 195.00$ 40,950.00$ Public Relations/Office Engineer 96 672 768 149.00$ 114,432.00$ Specialty Elec Inspectors
(Range B: 160-179) 120 1,920 176 2,216 179.00$ 396,664.00$ 652,046.00$
21,960.00$
4,000.00$
25,960.00$
1,552,855$
1,552,855$
Notes and Assumptions:

Project Construction Cost is estimated to be $8,000,000 with an additional 25% increase for Traffic Signal intersections Construction duration is estimated at 7 months, with preconstruction, post construction / close out Overtime and weekend work is not included. Overtime work to be pre-authorized by City Project Manager.

Cost proposal and invoicing is subject to prevailing wage rates.

Project Setup consist of; but not limited to, PR website, office setup, project field measurements & photos, documentation existing conditions, scheduling, drone footage, etc.

Office Space rental is for duration of 7 months, plus close out 2 months 1,232
Phase
Task 1 thru 3
Project Setup
Preconstruction
Construction
Hours
A: PRIME
B: Subtotal Construction Management Support:
1,408
1,232
400
A: Subtotal PRIME Construction Management
B: CONSTRUCTION SUPPORT
D: SPECIALTY SERVICES (OPTIONAL)
A + B + C + D: Total Construction Management Costs
CM team will support Public Outreach effort; however based on City request, a dedicated public outreach manager is assigned on a part-time as-needed basis.

C: OTHER
ODCs - Office Space @ $2440/mo
ODCs - printer lease @ $500/mo
C: Subtotal OTHER
A + B + C: Total Construction Management Costs: