January 4, 2024
Submitted via email:
Mr. Art Cervantes, PMP
Engineering Manager
Engineering Services Department
City of Rialto
150 S. Palm Avenue
Rialto, CA 92376
Subject: Task Order for PFAS Investigation and Reme diation Alternative Recommendation for Fire Station 203
Dear Mr. Cervantes:
GEI Consultants, Inc. (GEI) has prepared this task order for investigation of potential PFAS in soil resulting from the use of aqueous film forming foam (AFFF) at the fire training area behind (west of) Fire Station 203, 1550 N. Ayala Dr., Rialto, CA 92376. In addition to engaging the Santa Ana Regional Water Quality Control board for regulatory oversight of the investigation, GEI will prepare an evaluation of remedial alternatives for cleanup of PFAS-affected soil identified and recommend a preferred alternative.
We appreciate the opportunity to assist the City of Rialto with your upcoming project. We find the goals of the overall project very compelling and would be excited to play a role in investigating and preparing a cleanup plan for the fire training area. Please contact, Rick Ahlers at 760.795.1971 or [email protected],
if you have questions about our proposal.
Sincerely,
GEI Consultants, Inc.
C. Fredrik (Rick) Ahlers, P.E. Thomas Daigle, P. G.
Principal Engineer Senior Geologist
Attached:
• Task Order No. 1
B:\Marketing\Proposals\City of Rialto_Environmental On-Call_GM_EN_VL_2201009_03312022\PFAS Investigati on Task Order\PFAS Task Order Final Revised 010424.doc x
Task Order for PFAS Investigation and Remediation Alter native Recommendation for Fire Station 203 GEI Consultants, Inc. 1 City of Rialto
TASK ORDER NO. 1
CITY OF RIALTO
AND
GEI CONSULTANTS, INC.
1. PURPOSE
The purpose of this Task Order is to authorize and direct GEI Consultants, Inc. (“Consultant”) to perform the Scope of Work specified in Section 2 below, in accordance with the provisions of the On-Call Services Agreement between the City of Rialto (“CITY”) Consultant dated November 15, 2022 (“Agreement”). This Task Order shall be incorporated into Exhibit A of the Agreement.
2. SCOPE OF WORK
The services authorized by this Task Order are presented in Attachment “A” – Scope of Services, which is attached hereto and incorporated by this reference.
3. COMPENSATION AND PAYMENT
Compensation shall be paid as provided in the Agreement. The total compensation for Scope of Services as set forth in Section 2 shall be as set forth in Attachment “B” – Compensation, which is attached hereto and incorporated by this reference. Total compensation for all services provided under this Task Order shall not exceed $315,665 .
4. TIME OF PERFORMANCE
The services described in Section 2 of this Task Order shall be completed in accordance with the schedule set forth in Attachment “C” – Schedule of Completion, which is attached hereto and incorporated by this reference.
5. ITEMS AND CONDITIONS
All terms and conditions contained in the Agreement are incorporated by reference and remain in full force and effect.
Approved this ________ day of ____________________ 202__. [SIGNATURES ON NEXT PAGE]
Task Order for PFAS Investigation and Remediation Alter native Recommendation for Fire Station 203 GEI Consultants, Inc. 2 City of Rialto
CITY OF RIALTO
By:___________________________________________________________________ Date:__________________________ _________ Marcus Fuller
City Manager
GEI CONSULTANTS, INC.
By:_ __________________________________________________________________ Date:____January 4, 2024___________ _ C. Fredrik Ahlers
Principal Engineer
By: ___________________________________________________________________ Date:____January 4, 2024__________ __ Tom Daigle
Senior Geologist
ATTEST
By:___________________________________________________________________ Barbara A McGee
City Clerk
APPROVED AS TO FORM
By:___________________________________________________________________ Eric S. Vail
City Attorney
Task Order for PFAS Investigation and Remediation Alter native Recommendation for Fire Station 203 GEI Consultants, Inc. A-1 City of Rialto
ATTACHMENT A – SCOPE OF SERVICES
The scope of services included in this task order is for GEI Consultants, Inc. (GEI) to investigate the potential presence of PFAS in soil that may have resulted from use of PFAS-containing aqueous film forming foam (AFFF) used at the fire training facility behind (west of) the City of Rialto (City) Fire Station 203 at 1550 N. Ayala Drive in Rialto, California (the Site). GEI will also evaluate the feasibility of remedial alternatives appropriate to the levels of PFAS observed and goals for cleanup and recommend a preferred alternative.
TASK 1 – WORK PLAN
GEI will prepare a work plan to identify the desired investigation sampling locations and depths.
Development of the work plan will require knowledge of current and historical AFFF use and storage practices at the Site, including
■ Types of AFFF used and stored at the Site
■ Quantities of AFFF used and stored at the Site
■ Storage locations
■ Potential accidental discharges of AFFF
■ Locations where AFFF was used during fire training
■ Schedule or frequency of fire training during which AFFF was used GEI will interview City of Rialto Fire Department personnel with knowledge of these details and review documentation provided by the Fire Department. GEI will develop a work plan for a soil investigation based on the information provided. GEI will submit a draft for City review and, as necessary, will revise the work plan to address any City comments.
The City has indicated that a regulatory agency should be engaged to provide oversight and approval of site characterization activities and eventual remediation of PFAS-affected soil. The Santa Ana Regional Water Quality Control Board (Water Board) is the local authority currently engaged in overseeing the investigation of PFAS. In parallel with work plan development, GEI, in close consultation with the City, will submit a request to the Water Board to open a voluntary oversight case. After enrolling in voluntary oversight, GEI will submit the investigation work plan to the Water Board for their review and, as necessary, will respond to the Water Board and/or revise the work plan to address any comments.
TASK 2 – INVESTIGATION
Prior to investigation, GEI will develop a site- and task-specific health and safety plan (HASP) and will clear the investigation area for utilities and other underground obstructions. Underground utility clearance will include Dig-Alert notification, a review of facility and municipal utility records/drawings and oversight of a utility locate survey performed by a subcontractor. No San Bernardino County permit is necessary for the proposed soil borings, which are proposed to be less than 20 feet deep.
Investigation is proposed to occur in up to three phases and include Task Order for PFAS Investigation and Remediation Alter native Recommendation for Fire Station 203 GEI Consultants, Inc. A-2 City of Rialto
■ up to 72 soil samples from the upper one foot of soil in the first one or two phases of investigation followed by
■ up to 96 samples at up to 24 locations to a maximum depth of less than 20 feet in the second and possibly third phases of investigation.
Based on current and historical use and storage, GEI proposes to conduct the investigation as follows:
■ A first phase of investigation will be conducted in surface soil only (upper one foot) to characterize the lateral extent of PFAS-affected soil.
■ GEI will review the results of the first phase of investigation to determine whether lateral step out locations are necessary to complete characterization of the lateral extent of PFAS-affected soil.
■ If necessary, characterization of the lateral extent of PFAS-affected soil will be completed during a second phase of investigation.
■ GEI will review the results of the first and second (if conducted) phases of surface soil characterization to determine locations where subsurface soil samples will be collected between one and 20 feet below ground surface (bgs) for characterization of the vertical extent of PFAS- affected soil.
■ GEI will conduct subsurface sampling during a second and, if necessary, third phase of characterization.
Soil sample collection will be conducted in a manner that minimizes the potential for cross-contamination from PFAS containing materials not associated with the Site. The PFAS Sampling Guidelines for Non- Drinking Water published by the California State Water Quality Control Board in September 2020 provides guidance for sample collection procedures that will, as appropriate, be applied.
Soil samples may be analyzed by United States Environmental Protection Agency (USEPA) Method 537, which has in the past been specified by the Water Board for laboratory analysis of PFAS in soil. However, draft USEPA Method 1633 is currently under review and is anticipated to be finalized and potentially adopted by the Water Board as the preferred analytical method in the near future. Given this uncertainty, Method 1633, which is more expensive, is used to provide a conservative estimate of laboratory costs.
Final determination of the laboratory analytical method will be made in consultation with the Water Board.
Investigation derived waste (IDW) including soil cuttings and water used to decontaminate equipment between sampling locations will be disposed of in compliance with applicable state and federal regulations. Currently, PFAS are not designated as hazardous substances, and disposal costs assume IDW will be classified as non-hazardous.
GEI proposes that soil cores from some of the subsurface soil borings be retained on site to provide samples in the event that geotechnical characterization is relevant to evaluation of potential remedial alternatives.
All sampling locations will be surveyed by a California-licensed surveyor.
TASK 3 – REPORTING
Following completion of each field mobilization and receipt of laboratory data reports, GEI will perform a Level 2 data validation to assess the quality of the data. The data will be incorporated into a Task Order for PFAS Investigation and Remediation Alter native Recommendation for Fire Station 203 GEI Consultants, Inc. A-3 City of Rialto
comprehensive database for the site and visualized after each mobilization to support the planning for subsequent sampling locations and for inclusion in a final report. Iso-concentration maps of the total analyzed PFAS concentrations and selected individual PFAS will be prepared at multiple depth intervals, for example, 1 foot bgs, 2 to 10 feet bgs, and 10 to 20 feet bgs.
A report will be prepared documenting field activities and laboratory analysis and presenting characterization of the distribution of PFAS in soil at the site. A draft report will be prepared for review by the City. Following resolution of comments on the draft report, a final report will be prepared for submittal to the Water Board.
TASK 4 – FEASIBILITY STUDY & REMEDIAL ACTION PLAN
To evaluate the feasibility of alternatives for remediation of PFAS-affected soil, GEI will first develop a conceptual site model (CSM). The CSM will include an evaluation of the potential exposure risks associated with PFAS-affected soil and will be used to develop Site-specific proposed soil cleanup goals.
Based on these cleanup goals, GEI will then assess the feasibility of remedial alternatives for achieving the cleanup goals. GEI will use standard remedial alternative feasibility evaluation criteria established by for CERCLA (National Contingency Plan (40CFR300.430(e)(9))):
■ Threshold criteria of
1. overall protection of human health and the environment
2. compliance with applicable or relevant and appropriate requirements (ARARs) ■ Primary balancing criteria of
3. long-term effectiveness and permanence
4. reduction of toxicity, mobility, or volume through treatment
5. short-term effectiveness
6. implementability
7. cost
■ Modifying criterion 1 of
8. community acceptance
Initial screening of remedial alternatives will focus on the threshold criteria. Balancing criteria, including costs, will be evaluated for remedial alternatives that meet the threshold criteria screening step. For feasibility studies, an AACE Class 4 cost estimate is appropriate 2. This approach uses a project definition (design) of up to 15% and is expected to be accurate to within +50% to -30%. Modifying criteria are evaluated as necessary to discriminate between functionally equivalent alternatives. GEI understands that the Rialto Fire Department will want to pave the fire training area so that water and any other fluids used during fire training will be captured for treatment and/or disposal as appropriate. Remedial alternatives will consider both compatibility with this site use and how paving can enhance effectiveness of remedial alternatives.
1 Note for federal projects there is also a state acceptance criterion, however because regulatory oversight on this project will be state lead, state acceptance is effectively the threshold criteria of compliance with ARARs 2 AACE International. 2020. Recommended Practice No. 18R-97, Cost Estimate Classification System – As Applied in Engineering, Procurement, and Construction for the Process Industries. August 7.
Task Order for PFAS Investigation and Remediation Alter native Recommendation for Fire Station 203 GEI Consultants, Inc. A-4 City of Rialto
One alternative will be recommended following the screening process, and a draft feasibility study and remedial action plan (FS/RAP) will be prepared for City review. Assuming City concurrence with the recommendation, GEI will prepare an AACE Class 3 cost estimate accurate to within +30% to -20% and appropriate for budget authorization at up to a 40% design level. Following satisfactory resolution of City comments, GEI will submit the FS/RAP to the Water Board. Alternatively, and in consultation with the City and the Water Board, this may be submitted as an interim remedial action plan, which may have advantages for streamlining the shorter-term regulatory approval process.
TASK 5 – WATER BOARD OVERSIGHT COST RECOVERY
The Water Board’s Site Cleanup Program (SCP) is set up so that reasonable expenses incurred by the Water Board in overseeing soil and water quality matters can be recovered from the responsible party.
Reasonable expenses will be billed to identified responsible parties. The intent of this process is to ensure that oversight costs are properly documented and collected. This program is designed to cover those facilities in which responsible parties agree to pay oversight costs. As part of enrollment of the Site with the Water Board for voluntary oversight, the City will agree to cost recovery. The Water Board provides annual estimates of oversight costs for all active projects. GEI estimates that the Water Board will seek cost recovery of approximately $40,000 for oversight of the tasks described above. Cost recovery will be billed directly from the Water Board to the City. GEI can review the Water Board’s cost recovery invoices to confirm that the expenses being billed are reasonable.
Task Order for PFAS Investigation and Remediation Alter native Recommendation for Fire Station 203 GEI Consultants, Inc. B-1 City of Rialto
ATTACHMENT B – COMPENSATION
Cost estimate tables provided on following eight pages. Note that subcontractors have provided cost estimates assuming prevailing wages apply. Prevailing wages are assumed not to apply to tasks performed by GEI staff.
TASK Description SUBTOTAL
1 Task 1 - Work Plan 17,531$
2.1 Task 2.1 - Investigation (Direct Labor) 40,443$
2.2 Task 2.2 - Investigation (Driller & Other Direct Costs) 82,822$
2.3 Task 2.3 - Investigation (Analytical) 96,131$
3 Task 3 - Reporting 28,822$
4 Task 4 - Remedial Alternative Feasibility Study and Action Plan 49,916$ 315,665$
5 Task 5 - RWQCB Oversight Cost Recovery 40,000$
40,000$
355,665$
Non-GEI Charges
Non-GEI TOTAL
OVERALL PROJECT TOTAL
GEI PROJECT TOTAL
COST ESTIMATE
Fire Station 203 PFAS Investigation
1550 N. Ayala Dr.
Rialto, CA
Initial Authorization
PFAS_Investigation_Costs_Final_Revised_0104241/4/2024 Page 1 of 8 GEI Consultants, Inc.
Hourly Cost
Rate ($)
R. Ahlers 295 $ 9,440 $
T. Daigle; S. Hawkins 262 $ -$
TBD 220 $ 1,760 $
177$ -$
154$ -$
M. Corrado, A. Caffey, K. Vandervort 127$ 2,540 $ C. Lopez-Flores, J. Reidel, E. Gomez, M. N. Kouassi113$ 3,616 $ 97$ - $
156$ -$
C. Gonzalez 127 $ -$
114$ -$
S. Klingensmith 90 $ - $
89$ - $
17,356$
Units Cost
($)
1 175 $
-$
175$
0 - $
-$
-$
175$
17,531$
Direct Labor Costs
Project Labor Name Estimated
Assignment Classification
COST ESTIMATE
Task 1 - Work Plan
Work Plan Development Project Professional – Grade 3 20 Hours
Project Oversight / Sr Review / Senior Consultant – Grade 8 32 Senior Professional – Grade 7
Project Professional – Grade 4
Senior Professional – Grade 5
Senior Engineering Senior Professional – Grade 6 8
TOTAL DIRECT LABOR 92
Other Direct Costs
Cost Type Purpose of Cost Comments Cost Per
Work Plan Development Staff Professional – Grade 2 32
Office Aide
Staff Professional – Grade 1
Technician, Word Processor, Administrative Staff
Drafter / Designer and Senior Technician
Field Professional
Unit
Travel
Truck Site Visit / FC Interview per day 175$
No Markup
Subtotal
Equipment, Materials, Supplies, Subs
-$
TOTAL OTHER DIRECT
TOTAL ALL DIRECT COSTS
Senior Drafter and Designer
Markup (15%)
Subtotal
PFAS_Investigation_Costs_Final_Revised_0104241/4/2024 Page 2 of 8 GEI Consultants, Inc.
Hourly Cost
Rate ($)
R. Ahlers 295 $ 2,655 $
T. Daigle; S. Hawkins 262 $ 524 $
Project Management TBD 220 $ 11,440 $
177$ -$
154$ -$
M. Corrado, A. Caffey, K. Vandervort127$ 9,398 $ C. Lopez-Flores, J. Reidel, E. Gomez, M. N. Kouassi113$ 7,684 $ 97$ - $
156$ -$
C. Gonzalez 127 $ 8,382 $
114$ -$
S. Klingensmith 90 $ 360 $
89$ - $
40,443$
Units Cost
($)
-$
-$
-$
-$
-$
-$
-$
-$
-$
-$
-$
-$
-$
-$
40,443$
TOTAL OTHER DIRECT
TOTAL ALL DIRECT COSTS
Markup (15%)
Subtotal
Miscelaneous Field Supplies (per unit) 1,000$
GPRS Utility Clearance (per day) 2,400$
Non-Hazardous Waste Waste Decon Water and Drilling Spoils Disposal (per unit) 12,774 $ Enthalpy Analytical Laboratory PFAS Free Water for Equipment Blank (per liter) 25 $ Enthalpy Analytical Laboratory Draft EPA Method 1633 - 40 Analytes (per sample) 471 $ Surveyor Survey 96 locations (daily rate) 3,000$
No Markup
Subtotal
Equipment, Materials, Supplies, Subs
ABC Liovin Drilling Driller Soil Sampling 72 surface & 96 subsurface soil samples 43,498 $ Truck Vehicle Per Day 175$
Hotel Commute Alternative Per Day 250$
Unit
Travel
TOTAL DIRECT LABOR 275
Other Direct Costs
Cost Type Purpose of Cost Comments Cost Per
HASP Technician, Word Processor, Administrative Staff 4 Office Aide
Drafter / Designer and Senior Technician 66
Field Professional
Staff Professional – Grade 1
Senior Drafter and Designer
Project Support, Data Management, Field Implementation Project Professional – Grade 3 74 Field Implementation Staff Professional – Grade 2 68
Senior Professional – Grade 6 52
Senior Professional – Grade 5
Project Professional – Grade 4
Hours
Project Oversight / Senior Review Senior Consultant – Grade 8 9 Senior Engineering / QAQC / Sr. HASP reviewer Senior Professional – Grade 7 2
COST ESTIMATE
Task 2.1 - Investigation (Direct Labor)
Direct Labor Costs
Project Labor Name Estimated
Assignment Classification
PFAS_Investigation_Costs_Final_Revised_0104241/4/2024 Page 3 of 8 GEI Consultants, Inc.
Hourly Cost
Rate ($)
R. Ahlers 295 $ - $
T. Daigle; S. Hawkins 262 $ -$
Project Management TBD 220 $ -$
177$ -$
154$ -$
M. Corrado, A. Caffey, K. Vandervort127$ -$
C. Lopez-Flores, J. Reidel, E. Gomez, M. N. Kouassi113$ -$ 97$ - $
156$ -$
C. Gonzalez 127 $ -$
114$ -$
S. Klingensmith 90 $ - $
89$ - $
-$
Units Cost
($)
12 2,100 $
7 1,750 $
-$
3,850$
1 43,498 $
-$
3 9,000 $
1 12,774 $
-$
1 1,000 $
1 2,400 $
10,301$
78,972$
82,822$
82,822$
TOTAL OTHER DIRECT
TOTAL ALL DIRECT COSTS
Markup (15%)
Subtotal
Miscelaneous Field Supplies (per unit) 1,000$
GPRS Utility Clearance (per day) 2,400$
Non-Hazardous Waste Waste Decon Water and Drilling Spoils Disposal (per unit) 12,774 $ Enthalpy Analytical Laboratory PFAS Free Water for Equipment Blank (per liter) 25 $ Enthalpy Analytical Laboratory Draft EPA Method 1633 - 40 Analytes (per sample) 471 $ Surveyor Survey 96 locations (daily rate) 3,000$
No Markup
Subtotal
Equipment, Materials, Supplies, Subs
ABC Liovin Drilling Driller Soil Sampling 72 surface & 96 subsurface soil samples 43,498 $ Truck Vehicle Per Day 175$
Hotel Commute Alternative Per Day 250$
Unit
Travel
TOTAL DIRECT LABOR 0
Other Direct Costs
Cost Type Purpose of Cost Comments Cost Per
HASP Technician, Word Processor, Administrative Staff
Office Aide
Drafter / Designer and Senior Technician
Field Professional
Staff Professional – Grade 1
Senior Drafter and Designer
Project Support, Data Management, Field Implementation Project Professional – Grade 3 Field Implementation Staff Professional – Grade 2
Senior Professional – Grade 6
Senior Professional – Grade 5
Project Professional – Grade 4
Hours
Project Oversight / Senior Review Senior Consultant – Grade 8 Senior Engineering / QAQC / Sr. HASP reviewer Senior Professional – Grade 7
COST ESTIMATE
Task 2.2 - Investigation (Driller & Other Direct Costs) Direct Labor Costs
Project Labor Name Estimated
Assignment Classification
PFAS_Investigation_Costs_Final_Revised_0104241/4/2024 Page 4 of 8 GEI Consultants, Inc.
Hourly Cost
Rate ($)
R. Ahlers 295 $ - $
T. Daigle; S. Hawkins 262 $ -$
Project Management TBD 220 $ -$
177$ -$
154$ -$
M. Corrado, A. Caffey, K. Vandervort127$ -$
C. Lopez-Flores, J. Reidel, E. Gomez, M. N. Kouassi113$ -$ 97$ - $
156$ -$
C. Gonzalez 127 $ -$
114$ -$
S. Klingensmith 90 $ - $
89$ - $
-$
Units Cost
($)
-$
-$
-$
-$
-$
177 83,367 $
-$
-$
9 225 $
-$
-$
12,539$
96,131$
96,131$
96,131$
TOTAL OTHER DIRECT
TOTAL ALL DIRECT COSTS
Markup (15%)
Subtotal
Miscelaneous Field Supplies (per unit) 1,000$
GPRS Utility Clearance (per day) 2,400$
Non-Hazardous Waste Waste Decon Water and Drilling Spoils Disposal (per unit) 12,774 $ Enthalpy Analytical Laboratory PFAS Free Water for Equipment Blank (per liter) 25 $ Enthalpy Analytical Laboratory Draft EPA Method 1633 - 40 Analytes (per sample) 471 $ Surveyor Survey 96 locations (daily rate) 3,000$
No Markup
Subtotal
Equipment, Materials, Supplies, Subs
ABC Liovin Drilling Driller Soil Sampling 72 surface & 96 subsurface soil samples 43,498 $ Truck Vehicle Per Day 175$
Hotel Commute Alternative Per Day 250$
Unit
Travel
TOTAL DIRECT LABOR 0
Other Direct Costs
Cost Type Purpose of Cost Comments Cost Per
HASP Technician, Word Processor, Administrative Staff
Office Aide
Drafter / Designer and Senior Technician
Field Professional
Staff Professional – Grade 1
Senior Drafter and Designer
Project Support, Data Management, Field Implementation Project Professional – Grade 3 Field Implementation Staff Professional – Grade 2
Senior Professional – Grade 6
Senior Professional – Grade 5
Project Professional – Grade 4
Hours
Project Oversight / Senior Review Senior Consultant – Grade 8 Senior Engineering / QAQC / Sr. HASP reviewer Senior Professional – Grade 7
COST ESTIMATE
Task 2.3 - Investigation (Analytical)
Direct Labor Costs
Project Labor Name Estimated
Assignment Classification
PFAS_Investigation_Costs_Final_Revised_0104241/4/2024 Page 5 of 8 GEI Consultants, Inc.
Hourly Cost
Rate ($)
R. Ahlers 295 $ 2,360 $
T. Daigle; S. Hawkins 262 $ -$
TBD 220 $ 2,640 $
177$ -$
L. McKinnon 154 $ 4,928 $
M. Corrado, A. Caffey, K. Vandervort127$ 5,334 $ C. Lopez-Flores, J. Reidel, E. Gomez, M. N. Kouassi113$ 13,560 $ 97$ - $
156$ -$
C. Gonzalez 127 $ -$
114$ -$
S. Klingensmith 90 $ - $
89$ - $
28,822$
Units Cost
($)
0 - $
-$
-$
0 - $
-$
-$
-$
28,822$
Markup (15%)
Subtotal
TOTAL OTHER DIRECT
TOTAL ALL DIRECT COSTS
No Markup
Subtotal
Equipment, Materials, Supplies, Subs
-$
Unit
Travel
-$
TOTAL DIRECT LABOR 214
Other Direct Costs
Cost Type Purpose of Cost Comments Cost Per
Memo Project Professional – Grade 3 42
Office Aide
Staff Professional – Grade 2
Staff Professional – Grade 1
Senior Drafter and Designer
Drafter / Designer and Senior Technician
Field Professional
Technician, Word Processor, Administrative Staff
120
Direct Labor Costs
Project Labor Name Estimated
Assignment Classification
Senior Professional – Grade 6 12
Hours
Project Oversight / Senior Review Senior Consultant – Grade 8 8 Senior Engineering / Field Testing / QAQC Senior Professional – Grade 7
COST ESTIMATE
Task 3 - Reporting
Project Support / Data Analysis / Memo
Senior Professional – Grade 5
Project Professional – Grade 4 32
PFAS_Investigation_Costs_Final_Revised_0104241/4/2024 Page 6 of 8 GEI Consultants, Inc.
Hourly Cost
Rate ($)
R. Ahlers 295 $ 10,620 $
T. Daigle; A. Campbell 262 $ 2,096 $
TBD; D. Murray 220 $ 13,200 $
177$ -$
154$ -$
M. Corrado, A. Caffey, K. Vandervort127$ 12,700 $ C. Lopez-Flores, J. Reidel, E. Gomez, M. N. Kouassi113$ 11,300 $ 97$ - $
156$ -$
C. Gonzalez 127 $ -$
114$ -$
S. Klingensmith 90 $ - $
89$ - $
49,916$
Units Cost
($)
0 - $
-$
-$
0 - $
-$
-$
-$
49,916$
TOTAL OTHER DIRECT
TOTAL ALL DIRECT COSTS
Markup (15%)
Subtotal
Equipment, Materials, Supplies, Subs
-$
No Markup
Subtotal
Travel
-$
Cost Type Purpose of Cost Comments Cost Per
Unit
Office Aide
TOTAL DIRECT LABOR 304
Other Direct Costs
Field Professional
Technician, Word Processor, Administrative Staff
Senior Drafter and Designer
Drafter / Designer and Senior Technician
Data Analysis / Risk Assessment / Report Staff Professional – Grade 2 100 Staff Professional – Grade 1
Project Professional – Grade 4
Project Engineering / Report Project Professional – Grade 3 100 Senior Professional – Grade 5
Hours
Project Oversight / Senior Review Senior Consultant – Grade 8 36 Senior Engineering / Field Testing / QAQC Senior Professional – Grade 7 8 Direct Labor Costs
Project Labor Name Estimated
Assignment Classification
PM / Sr Engineering / Risk Assessment Senior Professional – Grade 6 60
COST ESTIMATE
Task 4 - Remedial Alternative Feasibility Study and Action Plan PFAS_Investigation_Costs_Final_Revised_0104241/4/2024 Page 7 of 8 GEI Consultants, Inc.
Hourly Cost
Rate ($)
N/A 200 $ 40,000 $
40,000$
Units Cost
($)
0 - $
-$
-$
0 - $
-$
-$
-$
40,000$
TOTAL OTHER DIRECT
TOTAL ALL DIRECT COSTS
Markup (15%)
Subtotal
Equipment, Materials, Supplies, Subs
-$
No Markup
Subtotal
Travel
-$
Cost Type Purpose of Cost Comments Cost Per
Unit
TOTAL DIRECT LABOR 200
Other Direct Costs
Hours
RWQCB Staff RWQCB Average Rate 200
Direct Labor Costs
Project Labor Name Estimated
Assignment Classification
COST ESTIMATE
Task 5 - RWQCB Oversight Cost Recovery
PFAS_Investigation_Costs_Final_Revised_0104241/4/2024 Page 8 of 8 GEI Consultants, Inc.
Task Order for PFAS Investigation and Remediation Alter native Recommendation for Fire Station 203 GEI Consultants, Inc. C-1 City of Rialto
ATTACHMENT C – SCHEDULE OF COMPLETION
Task Sub Task Start Date Duration
1 Voluntary Oversight Enrolment January 15, 2024 4 Weeks City Fire Department Staff Interview January 15, 20 24 2 Weeks Prepare Draft Work Plan January 15, 2024 6 Weeks
City Review of Draft Work Plan February 26, 2024 (b egins after Draft Work Plan Preparation)
2 Weeks
Work Plan Finalization March 11, 2024 1 Week
Work Plan Submittal to Water Board March 18, 2024 0 Weeks Water Board Approval March 18, 2024 6 Weeks
2 HASP March 18, 2024 (begins after
Final Work Plan Submittal)
2 Weeks
Utility Clearance April 29, 2024 (begins after
Water Board Approval)
2 Weeks
Surface Soil Investigation Phase I May 13, 2024 8 W eeks Surface/Subsurface Soil Investigation Phase II July 8, 2024 8 Weeks Surface/Subsurface Soil Investigation Phase III
(as needed)
September 3, 2024 8 Weeks
3 Prepare Draft Investigation Report September 3, 2 024 (assuming investigation phase III is not
necessary)
4 Weeks
City Review of Draft Investigation Report September 30, 2024 2 Weeks Investigation Report Finalization October 14, 2024 1 Week Investigation Report Submittal to Water Board Octob er 21, 2024 0 Weeks Water Board Approval October 21, 2024 6 Weeks
4 Prepare Draft FS/(I)RAP December 2, 2024 8 Weeks
City Review of Draft FS/(I)RAP January 27, 2025 2 W eeks FS/(I)RAP Finalization February 10, 2025 1 Week
FS/(I)RAP Submittal to Water Board February 17, 202 5 0 Weeks Water Board Approval February 17, 2025 8 – 24
Weeks