Cities Index.
Attachment 2 - S1.1 Change Order Memo

Rialto City Council
April 27, 2024

Document
Attachment 2 - S1.1 Change Order Memo
Meeting
April 27, 2024
Body
Rialto City Council
Original file
922 KB
Text extracted from the city's file for reading and search. Open the original on legistar.granicus.com. That file is the official record.

Bob

M e mo r andu m

TO: RWS/RUA
FROM: Soomodh Abraham, Project Manager
CC: Neil Clifton, Jignesh Ladhawala
Subject: S1.1 Digester No.1 Wall Cap and Coating Project – Cost Amendment Memo
Date: April 28, 2015

This memorandum serves as an amendment to the memorandum Veolia submitted to Rialto Water Services (RWS) and Rialto Utility Authority (RUA) dated February 5, 2015 for a change order that resulted from an Unknown Site Condition (Attachment 1).

In accordance with Section 8.9 – Adjustm ents, of the executed Concession Agreement (CA) and Operation and Maintenance Subcontract, compensation for project management services for Veolia is limited to 5% of the additional construction cost. As such, Veolia has reduced its project management fee and the total cost as per the amended cost sheet provided in Attachment 2 .

With this change, the final cost for the requested change order is reduced from $5589 to $4890 .

Sincerely,

Soomodh Abraham

Bob

M e mor andum

TO:  RWS/RUA
FROM:  Soomodh Abraham, Project Manager
CC:   Jignesh Ladhawala, Clarence Mansell
Subject:   S1.1 Digester No.1 Wall Cap and Coating Project Date:    February 5, 2015

Introduction

This memorandum is to obtain approval from City of Rialto (City) and Rialto Water Services (RWS) for a change order that resulted from a change in site condition. Construction contractor, DN Tanks, currently is performing tasks at the Site; however, the contractor will require approval soon to proceed with the minor design changes resulting from the chang e in site condition.

While performing sand blasting of digester walls, the DN Tank’s construction crew noticed that the tendons (rebar) within digester walls were unevenly spaced, contrary to what was known from as‐built drawings obtained from the City. On January 16, 2015, DN Tanks provided a Request For Information (RFI) to Veolia (Appendix A). Based on consultation with West Yost, the team decided that be
cause of this uneven spacing of the tendons, minor design changes need to be made to properly allocate the wall cap anchors (steel  rebar).

Change  Order  Request

Design  changes  require  that  additional  number  of anchors,  from 190 to 224, will  be needed  to provide  adequate  strength  to the wall  cap that  is being  added.  Moreover,  these anchors  need  to be drilled  seven  (7) inches  deeper  into the digester  wall  than  what  was previously  designed.

Based  on the RFI response  requiring  minor  des ign changes,  DN Tanks  provided  a cost estimate  for a change  order  so as to get compensated  for the required  changes.  A breakdown  of the costs  provided  by DN Tanks  is shown  in Appendix  B. The total  cost  of the change  order,  including  Veolia’s costs  as stated  in the contract  for non‐recurring Facilit
y Improvement  Projects,  for these  design  changes  are  also  provided  in the Appendix

B,

Final

Construction

Work

Authorization

(FCWA)

Cost

Sheet

addendum.

This

cost

excludes

design

and

engineering

and

contingency

costs

as

these

are

not

applicable

for

this

project

and

for

this

change

order.

Veolia

requests

that

City

and

RWS

approve

and

process

this

change

order

so

that

the

construction

can

be

continued

without

delays,

thus

avoiding

any

contractor

stand

by

charges.

Conclusion

Veolia

and

its

construction

contractor,

DN

Tanks,

have

encountered

a

situation

that

meets

the

criteria

of

“Unknown

Site

Conditions”

as

specified

in

the

Concession

Agreement

(Appendix

C).

Because

of

this,

a

minor

design

change

will

need

to

be

implemented.

This

design

change

will

require

additional

labor,

and

additional

materials

such

as

anchors

and

equipment.

Therefore,

Veolia

is

requesting

a

change

order

in

the

amount

of

$
4890.00

and

has

provided

an

FCWA

Cost

Sheet

Addendum

in

the

Appendix

B.

Sincerely,

Soomodh

Abraham

Appendix A
Request for Information and Response
Veolia
437 North Riverside Ave.

REQUEST FOR INFORMATION
No. 00001
Phone: 619-270-4548
DN Tanks
351 Cypress Ln.

El Cajon, CA 92020 Fax: 619-440-8653
TITLE: Top of Wall Sandblasted 1/16/2015
1024-50 Digester Rehab, Rialto, CA JOB: 1024-50
Attn: Soomodh Abraham
Rialto, CA 92376
Phone: 909-820-3771 1/28/2015
PROJECT:

TO:

DATE:

REQUIRED:

After completion of the Top of Wall sandblasting our crews were able to investigate the locations of the vertical tendons and original roof anchor system. The vertical tendons are spaced at approximately 22” apart on average, the spacing is very inconsistent and are recessed into the top of the wall approximately 7”. The recesses appear to be filled with a non-shrink grout and may not have the structural support that the design engineer requires.

Further investigation into the original drawings, that were located in our archives,1 show the vertical tendons have a significantly larger anchor plate, this may impact where location of the required drilling for rebar imbeds.

The original roof support anchors are located approximately 13’ but also have a “foot print” of approximately

10.5”.

The conditions referenced above leaves limited area to provide for 190 drilled anchors for the required new wall cap. Spacing of the rebar dowels would have to be spaced in an inconsistent manner and may not provide for a proper structural connection. Please provide direction on how you would like us to proceed.

Note: Please see attached Wall Cap Detail.

QUESTION:

Requested By:DYK Incorporated Date:

Signed:

Ron Kluth
Primavera ®  

01/16/15
Ron Kluth
Response to RFI:

The 51" span shown on the RFI drawing forms a "pattern" with two tendons in 36" long 7" deep recess. The spacing of the dowels can vary to accommodate the tendon locations. Place two dowels between each tendon for a total of 4 dowels per "pattern". Adjust the dowel location based on the field condition not to exceed a maximum spacing of 20". This will result in a total of 224 dowels compared with 190 indicated on the plans.

Due to the presence of the tendon recesses and uncertain condition of the "ridges" all anchors should be extended to provide 15" of dowel depth below the base of the recess. This results in dowels which are 7" longer than submitted.

Momo Savovic PE
For Structural eng: Momo Savovic PE
1 MG DIGESTERRIALTO, CALIFORNIA

Appendix B
Total Cost for the Change Order
FCWA Amended Cost Sheet Addendum for S1.1 Digester No. 1 Wall Cap and Coating Project Prepared Date: April 28, 2015
Description Quantity Unit Unit Cost Total
DN Tanks Costs
Steel/Rebar 1 LS $975.00 $975.00
Hilti RE-500 1 LS $929.73 $929.73
Equipment 1 LS $200.00 $200.00
Labor 1 LS $1,945.00 $1,945.00
Mark Up 15% $607.46
Construction Cost $4,657.19
Veolia Compensation
Project Management Services 5% $232.86
Total Construction Cost* $4,890
* rounded cost
of Construction

Appendix C
Unknown Site Conditions

''Wastewater Master Account", the "Water Master Account", the "Wastewater Operating Account", the ''Water Operating Account", the "Wastewater Facility Authority Expense Account", the "Water Facility Authority Expense Account", the "Wastewater Capital Charges Account", the "Water Capital Charges Account", "Wastewater Interim Retention Account", "Water Interim Retention Account", the "Wastewater Siirplus Account'', the "Water Surplus Account", the "Wastewater Rate Stabilization Account", the "Water Rate Stabilization Account", the "Environmental Compliance Account", the "Excluded Account", the "Wastewater Loss Proceeds Account", th.e "Water Loss Proceeds Account", the "Wastewater Takings Account" and the "Water Takings Account".
"Trustee" has the meaning set forth in the definition of Trust Agreement. "Uncompleted Work" means any unfinished work or work in progress to be performed by any contractor or subcontractor of the City or the Authority with respect to the Utility Facilities as of the Effective Date, or any work ever performed .that has given rise to or will give rise to mechanics liens or any otl:ier claim against the Utilities Facilities. "Uncontrollable Circumstance" means any act, event, condition or circumstance beyond the reasonable control of a party (or the party's subcontractors) which prevents, delays or otherwise adversely affects the ability of that party to perform under this Agreement or adversely · affects the associated cost incurred by that party to perform any obligation under this Agreement (except payment obligations). Such acts, ·events, conditions or circumstances include, but are not limited to, Change of Law, strikes, lockouts, or other labor disturbances, earthquake, flood, hurricanes, or other natural disaster, acts of God, war, terrorism, civil insurrection, catastrophfo equipment failure, electricity or other utility interruption or unavailability, failure or interference with normal sources of supply of equipment and materials necessary to operate the Utllity Facilities in accordance with the terms of this Agreement, accident, any failure or delay in obtaining any Governmental Approval beyond a party's reasonable control, any failure, delay or interference by a party (other than a Party to this Agreement), issuance of a temporary restraining order ·or other form of injunction that prohibits prosecution of a material portion of the party's obligation under this Agreement, acts of third parties or other circumstances beyond a party's reasonable control. With respect to Concessionaire, "Uncontrollable Circumstance" includes, without limitation, receipt of Non-Specification Influent or the interference of use of or access to any portion of the Utility Facilities, the Wastewater Facility Site Easement, the Water Facility Site Easement, the Warehouse Building and Parking Area License, the Collection System License or the Water Delivery System License as a result of any existing title encumbrances that impede or make more difficult the Concessionaire's provision of the Services. "Underground Assets" means underground civil structures and underground assets that are part of the Utility Facilities including, but not limited to, pipes, lines, valves, valve stems, manholes, valve vaults, foundations, tanks and reservoirs. "Unknown Site Condition" means the discovery of historical or archeological or cultural finds, rare, endangered or threatened species, Regulated Substances, underground obstructions, underground utilities, geotechnical or soils issues or defects, faults, anomalies, or unknown features or conditions with respect to the Utility Facilities which were not actually known by Concessionaire as of the Contract Date.
#4827-2499-2007v46 29

← All documents from this meeting