FIXED LUMP SUM FEE
Rialto Community Development Dept. Office Renovation
and Façade Improvement Address at 131 & 141 Riverside Ave. date: Dec. 19, 2023 Construction Cost Estimate: TBD
prepared by: BOA Architecture, Edward Lok Ng prepared for: City of Rialto, Art Cervantes
HOURS UNIT HR RATE COST TOTAL
ARCHITECTURAL DESIGN DEVELOPMENT
CADD-3D modeling of construction document drawings 80 hrs 110 8,800 project management, mtgs,refine schematic design,coord. w engineers50 hrs 150 7,500 specifications in CSI format 14 hrs 150 2,100
construction cost estimate 10 hrs 150 1,500
19,900
ENGINEERING and EXPENSES
structural engineering 12,000
mechanical, new HVAC equipment, provide new ducts 14,000 plumbing 7,000
electrical 18,000
civil engineering 5,000
expenses for blueprints, photocopies, mailing, misc. 400 56,400
ARCHITECTURAL CONSTRUCTION DOCUMENTS
CADD-3D modeling of construction document drawings 190 hrs 110 20,900 project management,refine design development,coord. w engineers 130 hrs 150 19,500 meeting or coordination with Client 40 hrs 150 6,000
specifications in CSI format 30 hrs 150 4,500
construction cost estimate 20 hrs 150 3,000
quality control 30 hrs 150 4,500
City bldg-safety dept. and client submittal&corrections 60 hrs 110 6,600 65,000
CONSTRUCTION SUPPORT
pre-bid meeting 6 hrs 150 900
project management, RFI & submittal response 20 hrs 150 3,000 pre-construction meeting 6 hrs 150 900
project management, RFI & submittal response 60 hrs 150 9,000 CADD-3D modeling, record drawings 20 hrs 110 2,200
construction site meetings, punchlist meeting 16 hrs 150 2,400 18,400
PHASE 2, SUBTOTAL $159,700
CONTINGENCIES
Design Contingency 10% $15,970.0
PHASE 2, FEE TOTAL $175,670