CITY OF RIALTO

ON-CALL PROFESSIONAL SERVICES AGREEMENT
TASK ORDER NO.12 - "MERRILL AVENUE SAFE ROUTES TO SCHOOL" Construction Management Support Services for City Project No: 220801 Scope of Services: Resident Engineering, Inspection, Specialty, Public Outreach and Material Testing PreScience Corporation
September 16, 2024
Total
Hours Billing Rate Total
Task 4
Post-
Constructi
on
Project Assignment Total
Hours
Rate
Non Prev Wage
Rate
Prevailing Wage
Rate
Prev Wage OT Total Cost
Resident Engineer /
Project Manager 88 286 253.81$ 72,589.66$ Construction Inspector 1 40 128 176.37$ 22,575.36$ Construction Inspector 2 80 156.49$ 12,519.20$ - -$
- -$
- -$
107,684.22$
Material Testing - - 5,000.00$ Public Relations/Office Engineer 40 160 40 240 149.40$ 35,856.00$ Specialty Inspectors/Admin 320 80 400 140.00$ 56,000.00$ - -$
96,856.00$
-$
204,540$
204,540$
Notes and Assumptions:

Project Construction Cost is estimated to be $1,200,000.

Construction duration is estimated at 60 working days, with preconstruction,construction, post construction / close out Overtime and weekend work is not included. Overtime work to be pre-authorized by City Project Manager.

Cost proposal and invoicing is subject to prevailing wage rates.

Project Setup consist of; but not limited to, PR website, office setup, project field measurements & photos, documentation existing conditions, drone footage, etc.

D: SPECIALTY SERVICES (OPTIONAL)
A + B + C + D: Total Construction Management Costs
CM team will support Public Outreach; based on City request, a dedicated public outreach manager is assigned on a part-time as-needed basis.

C: OTHER
C: Subtotal OTHER
A + B + C: Total Construction Management Costs:

A: Subtotal PRIME Construction Management
B: CONSTRUCTION SUPPORT
B: Subtotal Construction Management Support:
88 80
Phase
Task 1 thru 3
Project Setup
Preconstruction
Construction
Hours
A: PRIME
198