On-Call Construction Management, Inspection Services
FIRE STATION 203 DORMITORY & HVAC PROJECT
CITY PROJECT NO. 220204
October 2, 2024
Submitted by
Proposal for
The City of Rialto
Fountainhead Consulting Corporation
Project Time
Needed
Pre-constrcution
Phase
Constrcution
Phase
Post
Constrcution
Phase
Total
Hours Billing Rate Total
Project Assignment Project
Assignment
Construction Inspector / CM 100% 24 360 40 424 160.00$ 67,840.00$ Construction Inspector / CM - OT 10% 36 36 240.00$ 8,640.00$ Labor Compliance 10% 8 36 8 52 118.00$ 6,136.00$ Project Manager - 8 18 8 34 175.00$ 5,950.00$ Subtotal Construction Management: 88,566.00$
Total
-
Subtotal Subconsultants: -$
Total Cost 88,566.00$
Limitations & Conditions:
Construction duration is estimated at 45 working days with 3 day for preconstruction phase and 5 days for closeout phase.
Inspectors will be fully equipped with vehicles, computers, tools, and equipment required to perform their tasks.
Overtime and weekend work is not included. Overtime is to be charged at 1.5 the above rate for inspection work only.
Cost proposal is subject to prevailing wage rates and prevailing wage rate changes for inspection.
October 2, 2024
Construction Management, Inspection and Materials Testing Services City of Rialto
Fire Station 203 Dorms/HVAC Project | City Project No. 220204 Cost Proposal
ServicesSubconsultants