CITY OF RIALTO

ON-CALL PROFESSIONAL SERVICES AGREEMENT
Task Order No. 1
SPECS Engineering Group
Construction Management, Inspection and Material Testing Services (RFP NO. 25-016) PROJECT: BLOOMINGTON, CASA GRANDE AND MAPLE IMPROVEMENTS CITY PROJECT NO: 25082 (25-023)
February 19, 2025
Total
Hours Billing Rate Total
Task 4
Post-
Constructi
on
Project Assignment Total
Hours
Rate
Non Prev Wage
Rate
Prevailing Wage
Rate
Prev Wage OT Total Cost
Resident Engineer / PM 288 286.80$ 82,598.40$ Assistant RE / Utility Coordinator 408 185.00$ 189.66$ 284.49$ 77,381.28$ Public Relations / Office Engineer 40 424 149.90$ 149.90$ 224.85$ 63,557.60$ - -$

- -$

- -$

223,537.28$
Material Testing - - 50,000.00$
CPM Scheduler 30 40 10 80 198.00$ 15,840.00$ Construction Inspector 320 320 220.00$ 70,400.00$ 136,240.00$
-$

359,777$

359,777$

Notes and Assumptions:

Project Construction Cost is estimated to be $1,810,000 Construction duration is estimated at 60 working days, plus preconstruction, post construction / close out Overtime and weekend work is not included. Overtime work to be pre-authorized by City Project Manager.

Cost proposal and invoicing is subject to prevailing wage rates.

Project Setup consist of; but not limited to:

CM team will support Public Outreach effort; however based on City request, a dedicated public outreach manager is assigned on a part-time as-needed basis. 288
Phase
Task 1 thru 3
Project Setup
Preconstruction
Construction
Hours
A: PRIME
B: Subtotal Construction Management Support:
408
384
A: Subtotal PRIME Construction Management
B: CONSTRUCTION SUPPORT
D: SPECIALTY SERVICES (OPTIONAL)
A + B + C + D: Total Construction Management Costs
PR website, project field measurements & photos, documentation existing conditions, scheduling, drone footage, etc.

C: OTHER
C: Subtotal OTHER
A + B + C: Total Construction Management Costs: