Rialto City Park City Inclusive Playground Project
October 28, 2025
Project Background
Community has long requested a modern, inclusive playground Rialto City Park is centrally located and one of the City’s most heavily used parks Families currently travel to surrounding cities for inclusive play opportunities CDBG Ad Hoc Committee strongly supports this project Addresses the need for a facility that welcomes children of all abilities Purchasing coop
PlayCore’s 7 Principles of Inclusive Design
Play Core’s Play On! Framework
COMMUNITY IMPACT
Lots of ShadePour in place- rubber surfacing
Playground Design
-Inclusive Swings-Multigeneration swing-Inclusive Merri Go Round-Inclusive Teter Totter
ClimberMusic Instruments
Project Cost
Inclusive Playground Cost
Design, Removal & Installation
**This includes GameTime/CPRS discount ($144,250.34)
862,792.35
Custom Canopies Freight
$2,595
GameTime equipment Freight
$10,000
Tax
$28,676.93
Total Cost of the Playground
$904,064.28
Project Funding
Inclusive Playground Funding
CDBG
$246,954.08
CDBG-CV
$440,447.40
General Fund (Park Maintenance CIP)
$216,662.80
Total Funding
$904,064.28
Summary
Recommendation
Approve the Proposed Inclusive Playground Design for Installation at Rialto City Park; Ratify the GameTime/CPRS Statewide Funding Initiative Grant Application and Accept the GameTime/CPRS Statewide Funding Initiative Grant Award of $144,250.34 Adopt a Resolution Authorizing a budget adjustment to transfer $216,662.80 from Account No. 33007304-53001 to Account No. 22341857-53001, to complete the necessary funding for the Rialto City Park Inclusive Playground Project; Award a Contract to GameTime, A Playcore Company, through OMNIA Partners for $904,064.28 for Rialto City Park Inclusive Playground, City Project CB260; and Authorize the City Manager or Their Designee to Execute all Related Documents.