CITY OF RIALTO

ON-CALL PROFESSIONAL SERVICES AGREEMENT
SPECS Engineering Group Inc TO-7
FIRE STATION 201 SAFETY IMPROVEMENTS
Scope of Services: Construction Management, Inspection and Materials Testing Services CITY PROJECT No. 25021
October 28, 2025
Total
Hours Billing Rate Total
Task 4
CM &
Inspection
Project Assignment Total
Hours
Rate
Non Prev Wage
Rate
Prevailing Wage
Rate
Prev Wage OT Total Cost
Construction Manager / Project
Manager 40 200 286.80$ 57,360.00$ Assistant RE 240 400 174.47$ 69,788.00$ Office Engineer 294 298 144.06$ 42,929.88$ - -$
- -$
- -$
170,077.88$
Material Testing - - 18,888.00$
- -$
- -$
18,888.00$
-$
188,965.88$
188,965.88$
Notes and Assumptions:

Project Construction Cost is estimated to be $1,200,000 ** Construction duration is estimated at 140 working days, plus preconstruction, post construction / close out Overtime and weekend work is not included. Overtime work to be pre-authorized by City Project Manager.

Note: We're requesting latest addendum, SSPs, Engineers Estimate, Geotechnical Report and General Plans.

Phase
Task 1 - 3
Project Setup, Preconstruction,
Submittal Review
Hours
A: PRIME
160
160
4 A: Subtotal PRIME Construction Management
B: CONSTRUCTION SUPPORT
B: Subtotal Construction Management Support:

D: SPECIALTY SERVICES (OPTIONAL)
A + B + C + D: Total Construction Management Costs
C: OTHER
C: Subtotal OTHER
A + B + C: Total Construction Management Costs: