CO # Item Cost City Contingency
City Share of Developer
Contingency
1,000,000.00$ -$
1 Removal of copper lines and install of fiberoptic 49,628.73$ 950,371.27$ -$ 2 Temp parking lot design and paving 215,862.54$ 734,508.73$ -$ 3 Temp lot additional percolation and design 14,260.39$ 720,248.34$ -$ 4 Security Adds/AV, E power changes, armory lockers, purchase dispatch consoles, purchase furniture 390,009.96$ 330,238.38$ -$ 5 Mortuary Lot soil testing and survey, culvert relocation, SCE & ATT permit fees, added cable TV drops, city requested water kills, CMU wall height change, dispatch furniture changes, furniture adds, culvert redesign 613,331.49$ -$ (283,093.11)$ 6 Mortuary Lot adds 182,206.78$ -$ (182,206.78)$ 7 Cellular DAS Addition and Install, county radio added grounding, dispatch console adds, added design scope for county radio revisions, mortuary lot, Axon cameras, fitness vendor, dispatch communications, and drone landing 375,267.27$ -$ (375,267.27)$ Total Amount from all Change Orders 1,840,567.16$
Amount Remaining in City Contingency -$
Amount Remaining in Unallocated Developer Contingency 906,394.34$