Item No. Description Costs
PCI 0473 Unforeseen Conditions - Storm Water Culvert 16,784.62 PCI 0296.1County Radio requested Adds/changes
Conduit infrastructure from fire rated shaft to mechanical screen attachments 29,516.74
PCI 0423 Additional FD requested Fire Annunciator Panel 11,121.00 PCI 0375 Front Lobby Entry Paneling 5,662.08
PCI 0506 Dispatch Console AV Changes 35,849.00
PCI 0428 Additional County Radio Requirements
County request to remove and reinstall recepticals (4) in the server room 1,625.00
PCI 0503 Additional caulking and slipsheeting per BI request for roof 10,066.00 PCI 0504 PD Sigange Changes 65,404.45
PCI 0508 Sally Court Changes 51,246.62
PCI 0581 Walkway at the low roof 10,820.00
PCI 0573 Type K - Sliding Door Sidelight Glass Change 17,415.01 PCI 0580 Women's Locker Room Polished Concrete 19,610.00 PCI 0518 Revised Doors 254 and 200 from flush wood to full lite 8,038.67 PCI 0525 Additional blank keys 4,157.25
PCI 0566 Stray Kennel Office Flooring Change to LVT Tile 8,313.00 PCI 0513 RGB equipment temporary solution 22,358.00
PCI 0516 Touch screens schedulers trim piece 19,348.00
PCI 0519 Custom Color Security Caulking 3,225.00
PCI 0543 Chief Suite added power/data 5,697.00
PCI 0548
Conference room 205 vinyl removal and replacement, window films at sidelight, removal of 911 vinyl 5,376.00
PCI 0564 Occupancy sensors in Men's and Women's locker rooms 4,838.00 PCI 0509 Video intercom relocation 4,301.00
PCI 0544 Lactation room quad outlet and quad behind rack (2nd floor IDF)2,256.00 PCI 0550 Executive suite vinyl removal per chief request 2,150.00 PCI 0545 Building 2 camera relocation 1,613.00
PCI 0549 Added corner guards in investigations suite and across first floor 1,600.00 PCI 0541 Added exit signs buildings 1&2 16,125.00
PCI 0568 Interview RR trash receptacle 3,225.00
PCI 0524 Card reader added into level 2 door 250B 5,376.00 PCI 0502 BSCC inspection for juv lounge, RR, and detention areas 40,351.00 PCI 0523 Data run to server room for breathylzer 2,150.00 PCI 0612 Generator enclosure requests per building inspector 26,191.00 PCI 0577 Office 257 changes request for the PD 5,912.00 PCI 0641 Change in gym vinyl 5,376.00
PCI 0329 Perm Revision 9 - Drone dock power and data 27,725.00 Rialto PD - Adds/Changes
PCI 0345 Intercept box for fiber loop cost impacts and investigation 43,159.00 PCI 0635 Range doors mag-lock for card reader functionality 2,239.12 PCI 0639 MPR doors C101B and C101A 6,988.00
PCI 0602 Furnish and install (2) PDUs support building 7,267.00 PCI 0368 Phase 1 High-Lines and new services to existing homes 37,945.52 PCI 0389 North ramp wall adjustment for elevation discrepancies 32,059.79 PCI 0388 Concrete retaining wall RW4 extended height change 31,668.70 PCI 0418 Elevator Pit Sprinkler Head and Smoke Detection 4,122.00 PCI 0494 Non-sworn lockers service amount 13,164.96
PCI 0542 Firing range lane cameras 15,000.00
PCI 0540 Power for Cellular DAS in IDF room level 1 1,295.00 PCI 0643 SCE area re-work 45,148.00
PCI 0557 Memorial design and build 214,557.00
PCI 0692 Firmcrete extension on south retaining wall 17,198.00 PCI 0672 AT&T aded costs for service to the new building 118,237.53 PCI 0699 Motorized Window Roller Shade with Blackout Shade Office 2576,000.00 PCI 0671 Water Spigots/Filters at sinks 3,796.00
PCI 0675 Additional 128 Halo-Lit Building Address Sign 11,372.23 PCI 0701 Site emergency lighting backup power 5,214.00
PCI 0702 Temporary ERRCs solutuion for revised SB frequencies 3,079.00 PCI 0703 Locker end panels for relocated dispatch lockers 2,233.33 PCI 0704 ERRCs permanent solution per revised SB frequencies 165,000.00 PCI 0705 Drinking fountain west canopy 8,500.00
GMBI GM Furniture Adds 14,939.59
Morrow Added costs for SCE field coordination and re-work 7,500.00 LPA Added design and coordination for SCE final plan (PSA 07B) 15,515.00 LPA Added design costs for review of the Memorial design 15,600.00 Total of all changes 1,349,621.21
Total Per Category
Griffin Developer Mark-Ups 94,473.48
City 5% City Contingency 72,204.74
Total All-In for Changes 1,516,299.43
Cost Impact Summary.pdf
Rialto City Council
June 9, 2026
- Document
- Cost Impact Summary.pdf
- Meeting
- June 9, 2026
- Body
- Rialto City Council
- Original file
- 431 KB
Text extracted from the city's file for reading and search. Open the original on legistar.granicus.com. That file is the official record.