Activity ID Activity Name Original
Duration
Actual
Duration
Remaining
Duration
Activity %
Complete
Start Finish T otal Float
Rialto MortuaryRialto Mortuary 131 0 131 13-Apr-26 15-Oct-26 0 PreconstrucƟonPreconstrucƟon 121 0 121 27-Apr-26 15-Oct-26 0 SCESCE 121 0 121 27-Apr-26 15-Oct-26 0
A1030 SCE Design 80 0 80 0%27-Apr-26*18-Aug-26 0
A1040 Schedule SCE for On-Site Work 20 0 20 0%18-Sep-26 15-Oct-26 0 SubmiƩalsSubmiƩals 90 0 90 13-Apr-26 18-Aug-26 36
A1000 Generator/A TS - Procurement 90 0 90 0%13-Apr-26*18-Aug-26 36 ConstrucƟonConstrucƟon 97 0 97 18-May-2602-Oct-26 9
DemoDemo 10 0 10 18-May-2601-Jun-26 9
Demo1000 Clear Site 5 0 5 0%18-May-26*22-May-26 9
Demo1010 Excavate 5 0 5 0%26-May-2601-Jun-26 9
GradingGrading 20 0 20 02-Jun-26 29-Jun-26 14
Grade1000 Rough Grade 5 0 5 0%02-Jun-26*08-Jun-26 9
Grade1020 Install Infiltration Basins 15 0 15 0%09-Jun-26 29-Jun-26 14 UndergroundUnderground 20 0 20 09-Jun-26 07-Jul-26 9
UG1000 Install SD Piping 10 0 10 0%09-Jun-26 22-Jun-26 9 UG1010 Install UG Electrical 10 0 10 0%23-Jun-26 07-Jul-26 9 StructuralStructural 25 0 25 08-Jul-26 1 1-Aug-26 9
Struc1000 Excavate/FRP Wall Footings 5 0 5 0%08-Jul-26 14-Jul-26 9 Struc1010 Auger / FRP Light Pole Footings 5 0 5 0%15-Jul-26 21-Jul-26 9 Struc1020 Install Masonry Wa lls 15 0 15 0%22-Jul-26 1 1-Aug-26 9 Curb & GuƩer / PavingCurb & GuƩer / Paving 37 0 37 12-Aug-2602-Oct-26 9 Grade1010 Grade for Curbs 3 0 3 0%12-Aug-2614-Aug-26 9
Grade1030 Fine Grade 2 0 2 0%17-Aug-2618-Aug-26 9
CG 1000 Form & Pour Curb & Gutter 8 0 8 0%19-Aug-2628-Aug-26 9 CG 1010 Base & Pave 3 0 3 0%17-Sep-26 21-Sep-26 9
CG 1020 Clean & Stripe Parking 2 0 2 0%01-Oct-26 02-Oct-26 9 City Curb & GuƩer / SidewalkCity Curb & GuƩer / Sidewalk 12 0 12 31-Aug-2616-Sep-26 9 City1000 Demo City Sidwalk & Curb/Gutter 2 0 2 0%31-Aug-2601-Sep-26 9 City1010 Form & Pour Curb & Gutter 5 0 5 0%02-Sep-26 09-Sep-26 9 City1020 Pour City Sidewalk 5 0 5 0%10-Sep-26 16-Sep-26 9 LandscapingLandscaping 7 0 7 22-Sep-26 30-Sep-26 9
Land 1000 Install Landscaping & Irrigation 7 0 7 0%22-Sep-26 30-Sep-26 9 Site FinishesSite Finishes 3 0 3 22-Sep-26 24-Sep-26 15 Site 10010 Install Light Poles 3 0 3 0%22-Sep-26 24-Sep-26 15 Site 10020 Install Security Gates 2 0 2 0%22-Sep-26 23-Sep-26 16 ElectricalElectrical 21 0 21 19-Aug-2617-Sep-26 20
A1010 Installation of Generator 5 0 5 0%19-Aug-2625-Aug-26 36 Q4 Q1 Q2 Q3 Q4 Q1
2026 2027
SCE Design, 27-Apr-26*, 18-Aug-26
Schedule SCE for On-Site Work, 18-Sep-26, 15-Oct-26
Generator/A TS - Procurement, 13-Apr-26*, 18-Aug-26
Clear Site, 18-May-26*, 22-May-26
Excavate, 26-May-26, 01-Jun-26
Rough Grade, 02-Jun-26*, 08-Jun-26
Install Infiltration Basins, 09-Jun-26, 29-Jun-26
Install SD Piping, 09-Jun-26, 22-Jun-26
Install UG Electrical, 23-Jun-26, 07-Jul-26
Excavate/FRP Wall Footings, 08-Jul-26, 14-Jul-26
Auger / FRP Light Pole Footings, 15-Jul-26, 21-Jul-26
Install Masonry Wa lls, 22-J ul-26 , 1 1-Aug-26
Grade for Curbs, 12-Aug-26, 14-Aug-26
Fine Grade, 17-Aug-26, 18-Aug-26
Form & Pour Curb & Gutter , 19-Aug-26, 28-Aug-26
Base & Pave, 17-Sep-26, 21-Sep-26
Clean & Stripe Parking, 01-Oct-26, 02-Oct-26
Demo City Sidwalk & Curb/Gutter , 31-Aug-26, 01-Sep-26
Form & Pour Curb & Gutter , 02-Sep-26, 09-Sep-26
Pour City Sidewalk, 10-Sep-26, 16-Sep-26
Install Landscaping & Irrigation, 22-Sep-26, 30-Sep-26
Install Light Poles, 22-Sep-26, 24-Sep-26
Install Security Gates, 22-Sep-26, 23-Sep-26
Installation of Generator , 19-Aug-26, 25-Aug-26
NEWPROJ-1352-Rialto Mortuary Page 1 of 2 DD: 16-Dec-25 RD:03-Apr-26 11:38 Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work

IMPACTS
Milestone
Rialto Mortuary
Schedule Update

Page 1 of 2 ends

Layout: Client Review - All Activities W/
Float
TASK filter: All Activities

Activity ID Activity Name Original
Duration
Actual
Duration
Remaining
Duration
Activity %
Complete
Start Finish T otal Float
A1020 Underground Infrastructure for SCE 20 0 20 0%19-Aug-2616-Sep-26 0 A1050 SCE Inspection 1 0 1 0%17-Sep-26 17-Sep-26 0
Q4 Q1 Q2 Q3 Q4 Q1
2026 2027
Underground Infrastructure for SCE, 19-Aug-26, 16-Sep-26 SCE Inspection, 17-Sep-26, 17-Sep-26
NEWPROJ-1352-Rialto Mortuary Page 2 of 2 DD: 16-Dec-25 RD:03-Apr-26 11:38 Remaining Level of Effort
Actual Level of Effort
Actual Work
Remaining Work
Critical Remaining Work

IMPACTS
Milestone
Rialto Mortuary
Schedule Update

Page 2 of 2 ends

Layout: Client Review - All Activities W/
Float
TASK filter: All Activities