1& Concrete Paving, Inc.
324 S. Diamond Bar Blvd. PMB 275, Diamond Bar, CA 91765 Phone 909.629.8000 Fax 909.629.8001
Lic. #875627, Class A, C-8, C-12 - DIR # 10000025154
PROPOSAL CCO 1
Submitted To: Rocky Kaw Date: 07/07/26
Agency: City of Rialto Project: City of Rialto, Frisbie SRTS 'ublic Works - Engineerin
Address: Project
335 W. Rialto Avenue, Rialto, Address: City of Rialto
Phone: 909-421-4942
Email: : [email protected]
WE HEREBY SUBMIT SPECIFICATIONS AND ESTIMATE FOR THE FOLLOWING Scope of Work: Site Concrete
Description Unit Qty. Unit Rate Total
Frisbie SRTS Curb Ramp CCO 1 SEE EXHIBIT A
Perform the following On-site work:
1 Mobilization $
Temporary Traffic Control $ 6,000.00 6,000.00
Construction Surveying
Water Pollution Control
Clearing, Grubbing and Removals 4,000.00 4,000.00
Remove Existing AC and/or Native Material 110.00 451.00 Remove Existing Curb and Gutter 15.00 810.00
Remove Existing Concrete Surfaces (Sidewalk, Driveway, Cross Gutter/Spandrel) 3.00 8,379.00 6" Aggregate Base 120.00 1,440.00
4" Asphalt Concrete ..
10 180.00 2,700.00
11 Reconstruct Sidewalk 1,290.00 44,505.00
12 Construct 8" Curb and Gutter 90.00 4,860.00
13 Construct Curb Ramp 5,000.00 175,000.00
14 Construct Cross Gutter/Spandrel 18.00 450.00
:
e propose thereby to furnish material and labor complete in accordance with above specifications. All material is guaranteed to be as specified. All work to be completed in a workman like manner according ndard practices. Any alterations or deviation from above specifications involving extra cost will be executed only upon signed change orders, and will become an extra charge over and above the estimate. agreements upon strikes, accidents or delays beyond our control. Owner to carry fire, tornado and necessary insurance. Our workers are fully covered by workers compensation insurance. Initial Thereby propose to furnish materials and labor to complete in accordance with the specification above for the sum of:
Total Bid $ 248,595.00
Authorized Signature Date Jose Carvajal
909 821 4769
Acceptance of the above prices, spec's and conditions [email protected] are satisfactory and are hereby accepted
This proposal may be withdrawn by us if not
accepted within 15 days
24 S. Diamond Bar Blvd. PMB 275, Diamond Bar, CA 9176
hone 909.629.8000 Fax 909.629.8001 Lic. #875627 www.cttconcretepaving.com Jun 30, 2026 át 2:20:24 PM
302 E Cromwell St
Rialto CA 92376
MUnited States
Ramp J
ADA=11x21
4x10 Sidewalk Transition
31 LF of curb
n 30, 2026 at 2:20:36 PM
/ 302 E Cromwell St
Rialto CA 92376
United States
RAMP K
ADA: 11x21
4x10 Sidewalk Transition
31 LF of Curb
Jun 30,2026 at 2:36:27 PM
272-298 E Chaparral St
Rialto CA 92376
United States!
RAMP S
ADA: 11x20
4x10 Sidewalk Transition
Jun 30, 2026 at 2:36:40 PM
212-298 E Chaparral St
Rialto CA 92376
United States
RAMP R
ADA: 11x20
4x10 Sidewalk Transition
31 LF of curb
n 30, 2026 at 2:47:31 PM
303 E Lomita Or
Rialto GA 92376
United States
HANDY M
RAMP T
ADA: 11x20
4x10 Sidewalk Transition
31 LF of curb
Jun 30, 2026 at 2:47:39 PM
270 E Lomita Dr
Rialto CA 92376
United States
RAMP U:
ADA: 10x21
4x10 Sidewalk Transition
31 LF of curb
Jun 30, 2026 at 2:52:19 PM
270 E Lomita Dr
Rialto CA 92376
United States
RAMP H:
ADA: 12x38
6x10 Sidewalk Transition
43 LF of curb
Jun 30, 2026 at 2:55:03 PM
1776 N Sage Aver
Rialto CA 92376
United States
RAMP I:
ADA: 12x38
6x10 Sidewalk Transition
42 LF of curb
Jun 30: 2026 at 3:06:34 PM
1717 A Sycamore Ave
Rialto CA 92376
United States
RAMP V:
ADA: 11x20
4x10 Sidewalk Transition
31 LF of curb
Jun 30, 2026 at 3:06:46 PM
1717 N Sycamore Ar
Rialto CA 92376
United State:
RAMP W:
ADA: 11x20
4x10 Sidewalk Transition
31 LF of curb
Jun 30, 2026 at 3:13:38 PM
1650-1698 N Sycamore Ave
Rialto CA 92376
United States
CHLA
RAMP AC:
ADA: 11x20
4x10 Sidewalk Transition
31 LF of curb
Jun 30, 2026 at 1:30:46 PM
1829 N Joyce Ave
Pialto CA 92376
United States
RAMP P:
ADA: 6x29
6x10 Sidewalk Transition
31 LF of curb
0. 2026 at 1:30:53 PM
4829 A Joyce Ave
Rialto: 92376
*States
RAMP Q:
ADA: 6x28
6x10 Sidewalk Transition
31 LF of curb
Jun 30, 2026 at 1:54:05 PM
1848 N Marcella Ave
Rialto CA 92376
United States
RAMP N:
ADA: 6x30
6x10 Sidewalk Transition
32 LF of curb
Jun 30, 2026 at 1:54:13 PM
1829 N Marcella Ave
Rialto CA 92376
United States
RAMP O:
ADA: 6x28
6x10 Sidewalk Transition
31 LF of Curb
Jun 30, 2026 at 2:05:31 PM
1820 N Sage Ave
Rialto CA 92376
United States
RAMP M:
ADA: 6x29
6x10 Sidewalk Transition
31 LF of curb
Jun 30, 2026 at 2:05:40 PM
1820 N Sage Ave
Rialto CA 92376
United States
RAMP L:
ADA: 6x34
6x10 Sidewalk Transition
34 LF of curb
Jun 30, 2026 at 3:35:07 PM
359 E Heather St
Rialto CA 92876
United States
Ramp F
ADA 11x21
35' LF C&G & AC
4x10 SW Transition
Jun 30, 2026 at 3:35.14 R
359 E Heather St
Rialto CA 92376
United States
Ramp E
ADA 21x11
35LF of C&G & AC
4x10 SW Transition
Jun 30, 2026 at 3:42:20 PM
1740 N Date Ave
Rialto CA 92376
United States
Ramp AA
11x21 ADA
31 LF of C&G
4x10 SW Transition
Jun 30, 2026 at 3:42.27 PM
1740 N Date Ave
Risto CA 92376
United States
Ramp Z
11x20 ADA
31 LF of C&G
4x10 Sidewalk Transition
Jun 30, 2026 at 3:47:16 PM
250 E Lurelane St
Rialto CA 92376
United States
Ramp Y
11x21 ADA
31LF of C&G
4x10 SW transition
Jun 30, 2026 at 3:47:25 PM
250 E Lurelane St
- Rialto CA 92376
United State
Ramp X
11x21 ADA
31 LF of C&G
4x10 SW Transition
Jun 302026 at 3:49:59PM-
252 E Scott St
Rialto CA 92376
NO
OUTLET United States
Ramp A
21x10 ADA
31 LF of C&G
4x10 SW Trans
Jun 30, 2026 at 3:50:08 PM
252 E Scott St
Rialto CA 92376
United States
Ramp B
20x11 ADA
31LF of C&G
4x10 SW Trans
jun 30. 2026 at 3:58:25 PM
*1187 N Camphor Ave
Rialto CA 92378
United Sia
Ramp AD
6x30 ADA
31 LF of C&G
6x10 SW Trans
Jun 30, 2026 at 3:58:29 PM
1181 N Camphor Ave
Rialto CA 92376
United States
Ramp AE
6x29 ADA
31 LF C&G
6x10 Sidewalk Transition
Jun 30, 2026 at 4:03:08 PM
1192 N Glenwood Ave
Rialto CA 92376
Inited States
35 Ramp AG
6x52 ADA
54 LF of C&G
6x10 Sidewalk Trans
Jun 30, 2026 at A 03: 14 PM
1192 N Glenwood Ave
Rialto CA 92376
United States
Ramp AF
6x52 ADA
54 LF of C&G
6x10 Sidewalk Trans
Jun 30/2026 at 4:05:42 PM
960 W Mesa Dr
Rialto CA 92376
United States
Ramp AH
6x50 ADA
52 LF of C&G
6x10 SW Trans
Jun 30, 2026 at 4:05:46 PM
960 W Mesa Dr
Rialto CA 92376
United States
Ramp Al
6x50 ADA
52 LF of C&G
6x10 SW Trans
Jun 30, 2026 at 3:13:45 PM
280 E Heather St-
Rialto CA 92376
United States
Ramp AB
11x21 ADA
31 LF of C&G
4x10 SW Trans
Jun 30, 2026 at 3:15:39 PM
1669 N Sycamore Ave
Rialto CA 92376
United States
Ramp D
20x11 ADA
31 LF of C&G
4x10 SW Trans
-Jun 30, 2026 at 3:17:36 PM
314 E Heather St
492B76
Tonited States
Ramp C
11x21 ADA
31 LF of Curb
4x10 SW Trans