AMENDMENT NO. 1 TO SUPPLEMENT NO. 4
To the MASTER FUNDING AGREEMENT
Between METROPOLITAN TRANSPORTATION COMMISSION
And THE CITY OF RICHMOND
For the CAR SHARING AND MOBILITY HUBS IN AFFORDABLE HOUSING PILOT PROJECT – ELECTRIC VEHICLE CHARGERS AND ELECTRIC VEHICLE CAR SHARE

SERVICES

THIS AMENDMENT, effective as of February 1, 2022, is Amendment No. 1 to the Supplement No. 4, dated April 14, 2021 (“SUPPLEMENT”) to the Master Funding Agreement, dated July 1, 2017, (“MASTER FUNDING AGREEMENT”) by and between the Metropolitan Transportation Commission (“MTC”) and The City of Richmond (“AGENCY”).

NOW, THEREFORE, the parties agree to modify the subject Agreement as follows:

1. Paragraph 2 is revised to increase the amount of the agreement from three hundred forty-seven thousand, eight hundred fifty-one dollars and twelve cents ($347,851.12) by twenty-one thousand, five hundred five hundred twenty dollars ($21,520) for a new total of three hundred sixty-nine, three hundred seventy-one dollars and twelve cents ($369,371.12).

2. Annex II. Project Schedule, Budget, and Payment is revised as shown in the attached Annex II.

Project Schedule, Budget, and Payment.

3. Retention of Contract Provisions. Except as provided herein, all other terms and conditions of the Agreement remain unchanged.

IN WITNESS WHEREOF, this Amendment has been executed by the parties hereto as of the day and year first written above.

METROPOLITAN TRANSPORTATION

COMMISSION

CITY OF RICHMOND

Therese W. McMillan, Executive Director Thomas Butt, Mayor

MTC/City of Richmond
Master Funding Agreement - Car Sharing and Mobility Hubs in Affordable Housing Pilot Project Amendment 1 Supplement 4

Page 2 ends

Annex II
Project Schedule, Budget and Payment
Car Sharing and Mobility Hubs in Affordable Housing Pilot Project Electric Vehicle Chargers and Electric Vehicle Car Share Services

Task Deliverables (#)/ Milestones Due Date: Amount Due 1 PG&E Electrical Upgrades to Martin Luther King Jr. Park

1.1 Deposit for upgrading transformer 2/26/2021
1/12/22
$2,500.00

1.2 Upgraded transformer to accommodate four
electric vehicle chargers (PG&E)
2/26/2021 –
12/31/2021
2/1/2022 –
5-31-2022
$25,000.00
Total Task 1 $27,500.00
2 Electric Vehicle Charger Operations and Maintenance

2.1 Agreement with Service Provider 2/26/2021
4/30/2022

$0.00

2.2 Charger branding and marketing Continuous* $0.00

2.3 Data and analysis on usage and other data
points
Continuous* $0.00
Total Task 2 $0.00
3 Electric Vehicle Charger Installation

3.1 Installation of electric vehicle chargers 2/26/2021 5/1/2022

$0.00
Total Task 3 $0.00
4 Electric Vehicle Charger Implementation

4.1 Engineering Design and Permits 3/30/2021 -
12/31/2021
2/1/2022-
2/15/2022

$11,100.00

4.2 Saw cut, trenching, disposal of dirt,
backfill, asphalt, ADA stripping
3/30/2021 -
12/31/2021
2/16/2022 –
2/28/2022

19,050.00

4.3 Concrete pads for chargers, kiosk, and
panel, sign posts and bollards
3/30/2021 -
12/31/2021
2/28/2022 –
3/4/2022

16,750.00
26,580.00
MTC/City of Richmond
Master Funding Agreement - Car Sharing and Mobility Hubs in Affordable Housing Pilot Project Amendment 1 Supplement 4

Page 3 ends

4.4 Conduits, wires, boxes 3/30/2021 -
12/31/2021
3/7/2022 –
3/14/2022

19,680.00

4.5 New electrical panel and installation 3/30/2021 -
12/31/2021
3/15/2022 –
3/31/2022

9,300.00
22,190.00

4.6 Installation of electric vehicle chargers 3/30/2021 - 12/31/2021
4/1/2022 –
4/4/2022

4,125.00

4.7 Installation of kiosk 3/30/2021 -
12/31/2021
Removed
1,200.00
-1,200.00

4.8 New transformer and installation (PG&E) 3/30/2021 - 12/31/2021
4/5/2022 -
5/30/2022

5,000.00
Total Task 4 $86,205.00
$107,725.00
5 Electric Vehicle Carshare Services

5.1 Installation Activation of electric vehicle
chargers
2/26/2021
5/31/2022

$0.00
Total Task 5 $0.00
6 Carshare Services Provision

6.1 Vehicles
3/30/2021
3/30/2022
$ 91,800.00

6.2 Vehicle Hardware & Construction
3/30/2021
3/30/2022
$ 3,387.84

6.3 Experiential
3/30/2021
3/30/2022
$ 1,489.50

6.4 Third-Party Stipend Continuous* $ 17,000.00

6.5 Marketing, Education, & Outreach Continuous* $ 968.70

6.6 Direct Community Incentives Continuous* $ 80,000.00 MTC/City of Richmond
Master Funding Agreement - Car Sharing and Mobility Hubs in Affordable Housing Pilot Project Amendment 1 Supplement 4

Page 4 ends

6.7 Data & Analysis Continuous* $ 3,600.00

6.8 Operations, Maintenance, Contingency Continuous* $ 15,800.00

6.9 Energy Continuous* $ 5,100.00
Fringe Continuous* $ 10,000.08
Contingency $ 5,000.00
Total Task 6 $ 234,146.12
Total Project Cost $ 347,851.12
$369,371.12
*Continuous Until End of Service Agreement

The estimated and expected budget schedule that AGENCY will be paying for the chargers and carshare service per month is included in Attachment B-1, Estimated Budget Schedule.