HI NEMA Change Order #1
Construction
DATE January 29, 2022
555 Pierce Street #1005, Albany, CA 94706 City of Richmond Transportation Services [email protected] 440 Civic Center, Richmond, CA 94804
Tel: 510-525-2398 Installation of chargers
In MLK Park
Additional work
# DESCRIPTION Material Labor LINE TOTAL
1 PG&E approved design requies an additional panel called LOAD BREAKER which needs additional 36"x76" prefab concrete pad and 4"-60 feet PVC conduit for LOAD BREAKER to existing power for park outside of the fence. 1,950.00 7,880.00 9,830.00 2 Change 200A power per PG&E proposal to City of Richmond(see attached) to 400A power per final PG&E design which needs to change 200A distibution Panel to 400A 12,890.00 12,890.00 (cost of panel).
Total change order #1 22,720.00
Price good for 6-Months
Authorized by Date
Change Order #2
Construction
DATE January 31, 2022
555 Pierce Street #1005, Albany, CA 94706 City of Richmond Transportation Services [email protected] 440 Civic Center, Richmond, CA 94804
Tel: 510-525-2398 Installation of chargers
In MLK Park
Deduction
# DESCRIPTION Material Labor LINE TOTAL
Installatin of (1)-kiosk -1,200.00
Total change order #2
($1,200.00)
Price good for 6-Months
Authorized by Date