SCOPE OF WORK AMOUNT
RAS pipe replacement 332,033$
Bid Allowance #10, supplement for Primary Sedimentation Basin structural repairs 9,277$ Underground utilities conflicts change conditions 176,073$ Payment for planned work with no identified method of payment 71,725$ Material cost for lead time addition and modification of new (54) 316 steel plates and (10) gates at Aeration Basins and (1) new transformer. Mofication of existing electrical conduits to eliminate underground electrical conflicts 823,370$
Labor cost for Change Order Work #5 1,027,619$
Final underground utilities conflict change conditions work 53,463$ Total 2,493,560$