Cities Index.
Resolution - Cutting-Harbour Bikeways Project - Contract Amendment.pdf

Richmond City Council
December 20, 2022

Document
Resolution - Cutting-Harbour Bikeways Project - Contract Amendment.pdf
Meeting
December 20, 2022
Body
Richmond City Council
Pages
2
Original file
108 KB
Text extracted from the city's file for reading and search. Open the original on pub-richmond.escribemeetings.com. That file is the official record.
Page 1 of 2 ends

December 20, 2022

Public Works

DATE: December 20, 2022
TO: Mayor Butt and Members of the City Council
FROM:

Daniel Chavarria, Director of Public Works Director
Patrick Phelan, Infrastructure Administrator

Subject:

Resolution Amending the Construction Agreement with
W.R. Forde Associates, Inc.

FINANCIAL IMPACT: No impact to the General Fund. An additional $88,738.99 is needed to complete the project with funds coming from the ATP Quick Build Grant account #15436431-400708-
23G06.

PREVIOUS COUNCIL
ACTION:

City Council awarded the construction contract to W.R.

Forde Associates, Inc., in an amount not to exceed
$1,783,969 at the July 6, 2021 meeting.

STATEMENT OF THE
ISSUE:

The Cutting Boulevard and Harbour Way South Bikeways
Project is building a protected bikeway along Cutting
Boulevard, Hoffman Boulevard, and Harbour Way South.

Due to unforeseen conditions encountered during the
progress of construction, extra work is needed to
complete the project.

RECOMMENDED ACTION:

ADOPT a resolution authorizing a first amendment to the construction agreement with W.R. Forde Associates, Inc. to increase the amount by $88,738.99, for a new total
contract limit not to exceed $1,872,707.99, to complete the Cutting Boulevard and Harbour Way South Bikeways
Project and additional required work – Public Works
(Daniel Chavarria/Patrick Phelan 510-307-8111).

AGENDA
REPORT

Page 2 of 2 ends

December 20, 2022
DISCUSSION:

The Cutting Boulevard and Harbour Way South Bikeways Project was awarded to W.R.

Forde Associates, Inc. at the July 6, 2021 City Council meeting. The original construction contract is in an amount not to exceed $1,783,969, including a 10 percent contingency ($162,179).

Though there have been many delays, mainly due to railroad and Caltrans permits, most of the work on Cutting Boulevard and Harbour Way South is complete except the connecting section on Hoffman Boulevard remains.

The project implements concept designs outlined in the Ferry to Bridge to Greenway Plan, most of which consists of a two-way cycle track, where both directions of bicycle traffic are on one side of the street, separated from vehicles by a striped buffer with flexible bollards and curb stops (“armadillos”). The railroad operator (BNSF) and the Public Utilities Commission (PUC) would not allow the construction of a two-way cycle track across a railroad without significant, costly modifications to the crossing infrastructure. The design was modified to create single-direction cycle tracks on Cutting Boulevard, which avoided most problems with rail crossings, but added additional striping, bollards, and curb stops.

Other changes to the project include:
 pavement repair along West Cutting Boulevard, where considerable uplift of the asphalt adjacent to the concrete gutter created dangerous conditions  modifications to the striping at the railroad crossing on South Garrard Boulevard  modifications to the striping at the railroad crossing on Harbour Way South  unit price increases due to the delay in securing approval from BNSF, the PUC, and Caltrans

Approximately, $250,000 of changes are necessary to complete the project and comply with railroad crossing regulations. The original contract of $1,783,969 includes a contingency in the amount of $162,179. Public Works staff is requesting an additional $88,738.99, for a new total contract amount not to exceed $1,872,707.99.

DOCUMENTS ATTACHED:

Attachment 1 – Original Contract
Attachment 2 – Amendment to the Contract
Attachment 3 – Resolution

← All documents from this meeting