March 21, 2023

Public Works

DATE: March 21, 2023
TO: Mayor Martinez and Members of the City Council
FROM:

Daniel Chavarria, Director of Public Works
Mary Phelps, Project Manager

Subject:

Contract for the FY 2022-23 Grade 5 Risk Assessment
Analysis (RAA) Sewer Line Replacement of The Sanitary
Sewer Collection System per the Baykeeper Settlement
Agreement
FINANCIAL IMPACT: There is no impact to the General Fund. The funding for this project will be paid from Wastewater Enterprise
Funds – Org/Obj 40322931-400708-22230.

PREVIOUS COUNCIL
ACTION:

On October 3, 2021, City Council adopted Resolution
115-21 approving Veolia to manage a subcontract with
W.R. Forde and Associates for the 2021-22 Grade 5 RAA
Sewer Line Repair/Replacement Project.

STATEMENT OF THE
ISSUE:

City staff is recommending City Council authorize the
issuance of a task authorization to Veolia to award and manage subcontracts with D’Arcy and Harty
Construction, Inc. (San Francisco), V.W. Housen &
Associates, and Questa Engineers to replace and/or
rehabilitate specific sanitary sewer pipelines in the
Richmond Municipal Sewer District collection system.

The City is required to replace and/or rehabilitate a
minimum of two (2) miles annually per the Baykeeper
Settlement Agreement.

AGENDA
REPORT

Page 2 of 3 ends

March 21, 2023
RECOMMENDED ACTION:

ADOPT a resolution authorizing the issuance of a task
authorization to Veolia Water to manage (on behalf of the City) subcontracts with: D’Arcy and Harty Construction, Inc., VW Housen and Questa Engineers to replace and
or rehabilitate specific sanitary sewer pipelines, in an amount not to exceed $2,075,622 [D’Arcy and Harty
Project cost of $1,319,500 plus 16.5 percent mark-up of $217,718, plus 30 percent contingency of $395,980 plus

16.5 percent mark-up of $65,315; VW Housen project
cost of $36,000 plus 16.5 percent mark-up of $5,940,
plus 30 percent contingency of $10,800, plus 16.5
percent mark-up of $1,782; Questa Engineers Project
Cost of $15,000, plus 16.5 percent mark-up of $2,475,
plus 30 percent contingency of $4,500, plus 16.5 percent mark-up of $743)] (Public Works - Daniel Chavarria 510- 620-5478/Mary Phelps 510-621-1269).

DISCUSSION:

Pursuant to Paragraph ¶31.c of the 2018 Settlement Agreement between the City of Richmond and Baykeeper, the City is required to replace or repair at least two (2) miles of Grade 5 gravity sewer per year, based on a five (5) year rolling average.

In order to achieve this goal, the City is required to allocate annual capital funding to cover the cost of these mandated repairs.

On October 17, 2022, the proposal was posted to BidsOnLine, and thirty-four (34) prospective bidders downloaded the bid information. On October 26, 2022, a mandatory walk-through was conducted with Veolia staff and eleven (11) participants. On November 22, 2022, four (4) bids were received from (in alphabetical order): Cratus, Inc., D’Arcy and Harty Construction, Inc., Glosage Engineering Inc., and W.R. Forde and Associates.

The bids received were as follows (in alphabetical order):

Contractor Contractor Bid Amount
Cratus, Inc. $2,245,945
D’Arcy and Harty Construction, Inc. $1,319,500
Glosage Engineering, Inc. $1,689,602
W.R. Forde and Associates $2,543,000

Yader A. Bermudez, City of Richmond Retired Annuitant, Chandrasekar Venkatraman, Veolia Senior Project Manager, and Jayne Lopez, Carollo Engineers, reviewed the bids and determined that D’Arcy and Harty was the lowest responsive bid. Two pre-qualified

Page 3 of 3 ends

March 21, 2023
technical firms (V.W. Housen & Associates and Questa Engineers) also submitted acceptable proposals to provide compaction testing and engineering services during construction for this project for a total amount not to exceed $54,522 (project cost, plus mark-up, plus contingency and mark-up). As such, the task authorization for the project shall not exceed $2,075,622 [Project cost of $1,370,500, plus 16.5 percent mark-up of $226,133, plus 30 percent contingency of $478,990)].

Due to unforeseen conditions that may be experienced in the field, the City is requesting a significant contingency amount of 30 percent. This is so that the project will progress on time in order to meet the demands of the Baykeeper Settlement Agreement.

City staff is requesting City Council adopt the resolution approving the issuance of a task authorization to Veolia in the amount of $1,596,633 with an authorized contingency of 30 percent for a total contract not to exceed $2,075,622.

DOCUMENTS ATTACHED:

Attachment 1 – Resolution – 2022-23 Sewer Line Replacement Project Attachment 2 – Prospective Bids FY 2022-23 Sewer Line Replacement Project Attachment 3 – Canvass of Bids FY 2022-23 Sewer Line Replacement Project Attachment 4 – Task Authorization – 2022-23 Sewer Line Replacement Project Attachment 5 – Memo – Contract Compliance
Attachment 6 – Resolution 82-19
Attachment 7 – Resolution 84-19