Item # Description Quantity Unit Unit Cost Total Cost
1 Additional Mobilization (included in item#5) 1 LS -$ -$ 2 Traffic Control (included in item#5) 1 LS -$ -$ 3 Clearing & Grubbing 1 LS 10,000.00$ 10,000.00$ 4 SWPPP 1 LS 10,000.00$ 10,000.00$
5 Stitch Wall (includes 10% mark up) 1 LS 689,810.00$ 689,810.00$ 6 Guard Rail (included in item#5) 80 LF -$ -$ 7 Chain-Link Fence 100 LF 150.00$ 15,000.00$ 8 Vegetation 1 LS 15,000.00$ 15,000.00$
739,810.00$
147,962.00$
887,772.00$
20% Contingency
Park Central St and CT Grand Total
Subtotal