Public Works
November 2023
Abatement Update
December 19, 2023

NEIGHBORHOOD CLEAN-UPS (1)

1. Belding Woods Neighborhood Council Area

NEIGHBORHOOD CLEAN-UPS (1)
20 Seniors and people with disabilities assisted
8 Debris dumpsters removed

30.76 Tons of debris collected

ILLEGAL DUMPING
261.62 Tons removed

ILLEGAL DUMPING
1,138 Locations
ILLEGAL DUMPING: MATTRESSES, TIRES AND PAINT/OIL
234 Mattresses 210 Tires 112 Gallons of Paint/Oil

ENCAMPMENT ABATEMENT (9)

23.89 Tons removed

JanFebMarAprMayJunJulAugSepOctNovTonnage Collected
249.87169.66210.78224.86185.09242.03213.87238.18207.01317.6261.62Illegal Dumping 011.1172.0751.8460.0962.53489.1783.8353.7930.76Neighborhood Clean-Ups*

21.0826.5413.1853.468.678.5410.664.434.9517.7623.89Encampments 270.95207.31296.03330.16253.85313.07258.53331.7295.79389.15316.27Totals 01333434321*Number of Events

WEED ABATEMENT

GRAFFITI REMOVAL
222 Tags Removed
122 Locations

ABATEMENT STAFF HOURS
Illegal Dumping 2,210
Encampment Removal 84
Graffiti Abatement 160
North Richmond Mitigation 58
Weed/Litter Abatement 64
Private Board Ups & Clean-Ups 0
Transport/Misc.* 144
Total 2,720
October Hours
Illegal Dumping Encampment Removal
Graffiti Abatement North Richmond Mitigation
Weed/Litter Abatement Transport/Misc*
Board Ups/Clean Ups
Transport/Misc. includes staff hours for removal of debris from vehicles, Point Molate trash removal, and hazardous waste facility disposal.

ILLEGAL DUMPING TONNAGE COLLECTED PER MONTH - 2023
0 50
100
150
200
250
300
350
ILLEGAL DUMPING TOTAL COST PER MONTH – 2023*
$0
$20,000
$40,000
$60,000
$80,000
$100,000
$120,000
$140,000
$160,000
January February March April May June Ju ly August September October November *Includes Labor and Equipment

PARTNERSHIPS

← All documents from this meeting