April 16, 2024
Public Works
DATE: April 16, 2024
TO: Mayor Martinez and Members of the City Council
FROM:
Daniel Chavarria, PE, Director of Public Works
Robert Armijo, PE, Deputy Director of Public Works/City Engineer
Ken Cheng, PE, Senior Civil Engineer
Subject:
Award Construction Contract for the Lincoln Elementary
School Safe Route to School Improvement Project
(SRT)- CML -5137(055)
FINANCIAL IMPACT: One Bay Area Grant 2 (OBAG2) grant funding in the amount of $497,000 for construction. Matching local
funds $265,000 from the General Capital Funds (Account
String 20136031-400733-23041).
PREVIOUS COUNCIL
ACTION:
September 12, 2017, City Council adopted resolution for local support authorizing the filing of an application for funding assigned to MTC and committing any necessary
matching funds and stating assurance to complete the
safe routes to school.
October 24, 2023, City Council approved the FY 2022-
23Q4 Financial Report and Administrative Budget
Adjustments that consisted of appropriate additional
funds to numerous projects for completion. Lincoln SRT
was one of many projects approved in the amount of
$265,000.
STATEMENT OF THE
ISSUE:
Award a construction contract for Lincoln Elementary
School Safe Route Improvement Project to Corcus
Construction Inc. in an amount of $599,831 plus a
contingency amount of $67,000.
AGENDA
REPORT
April 16, 2024
RECOMMENDED ACTION:
ADOPT a resolution to ACCEPT and APPROPRIATE the
One Bay Area Grant 2 (OBAG2) in the amount of
$497,000 for Lincoln Elementary School Safe Route to
School Improvement Project CML-5137(055);
AUTHORIZE the city manager or their designee to
execute a contract with Corcus Construction, Inc in an
amount of $599,831; and AUTHORIZE the Director of
Public Works to approve change orders, if necessary, for an additional contingency amount of $67,000 – Public
Works Department (Robert Armijo 510-620-5477/ Ken
Cheng 510-621-1612).
DISCUSSION:
Lincoln Elementary School, situated in the heart of the Iron Triangle neighborhood, stands as one of two primary educational institutions in the area. Its proximity to key community thoroughfares such as the Richmond Greenway, Chanslor Avenue, 4th Street, and 6th Street, positions it centrally within vital safe routes to school. Despite the presence of crosswalks along Chanslor Avenue, frequented by numerous students and their guardians, there remains a substantial need for further pedestrian safety enhancements to safeguard the schoolchildren's journey.
Proposed improvements aim to enhance pedestrian safety by narrowing crossing distances on Chanslor Avenue through the installation of median refuges and curb extensions. Additionally, the introduction of a raised intersection at the junction of Chanslor Avenue and 4th Street is intended to prioritize pedestrian movement and moderate vehicular speed, further reinforcing the safety of this critical school route.
On September 17, 2017, the City Council endorsed a resolution to express local support, authorizing the submission of a funding application to the Metropolitan Transportation Commission (MTC), while committing to provide the requisite matching funds and ensuring the project's completion.
The Lincoln Elementary School Safe Route Improvement Project benefits from dual financial backing: a $497,000 construction grant from the One Bay Area Grant 2 (OBAG2) and a local contribution of $265,000 from the General Capital Funds allocated for both design and construction phases. This local contribution was affirmed by the City Council on October 24, 2023, during the approval of the FY 2022-23 Q4 Financial Report and Administrative Budget Adjustments, which included the allocation of additional resources for the successful execution of this project among others.
The City advertised the project through BidsOnline on October 23, 2023, and bids were opened on December 4, 2023. Unfortunately, there was a Disadvantaged Business Enterprise (DBE) calculation error that required the City of Richmoand to readvertise the construction bid. The plans and specifications were revised and re-advertised on
April 16, 2024
January 22, 2024. Bids were opened on February 20, 2024, and the City received five (5) bids with the following results:
Contractor Base Bid
APENA Construction* $275,933.30
Corcus Construction, Inc. $308,093.00
E.E. Gilbert Construction, Inc. $393,193.90
Mark Lee & Young Kay, Inc. $401,868.60
Krex Engineering, Inc. $448,420.00
*Note: Following a thorough review of the bids, the lowest bidder’s proposal was deemed incomplete due to not meeting the minimum requirements of the bid advertisement.
City staff determined that the apparent low bidder, Corcus Construction, Inc., was both responsive and responsible. The base bid was in the amount of $308,093. City staff recommends that items in the addition to the base bid items be added to the contract for an additional cost of $291,738. This brings the total recommended contract amount to $599,831. The total estimated cost of this project, if awarded to the low bidder, is as follows:
Construction Contract $599,831
Contingency @ 10% $67,000
Total Construction Cost $666,831
Design Support During Construction $10,200
Construction Management Cost (~10%) $59,983.10
Total Project Cost $737,014.10
Construction is scheduled to commence on June 3, 2024, and is anticipated to conclude by September 2, 2024. The project is expected to reach closeout by September 9, 2024.
City staff recommends the acceptance and appropriation of $497,000 from the One Bay Area Grant 2 (OBAG2) for the Lincoln Elementary School Safe Route to School Improvement Project CML-5137(055). Furthermore, it is recommended that the City Council authorize the City Manager or their designee to enter into a contract with Corcus Construction, Inc., for an amount of $599,831. It is also recommended to grant the Director of Public Works the authority to approve change orders as necessary, up to a contingency amount of $67,000.
ENVIRONMENTAL DOCUMENTS:
This project is exempted from CEQA requirements in accordance with Class 1 - Section 15301, Class 2 - Section 15302, and Class 3 - Section 15303.