CITY OF RICHMOND

PROJECT MANUAL

INCLUDING SPECIFICATIONS
FOR

CONSTRUCTION

PARK IMPROVEMENTS

SHIELDS REID
Richmond, California

PLACEWORKS
2040 Bancroft Way
Suite 400
Berkley, California 94704
MARCH 2024

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SIGNATURE PAGE 00 00 01 - 1
DOCUMENT 00 00 01

CITY OF RICHMOND

SIGNATURE PAGE

1.1 GENERAL INFORMATION
A. The provisions contained herein have been prepared for permitting, bid, and construction by or under the direction of the following:

02.09.2023
Jesse Jones Date
Landscape Architect No. 6371
PlaceWorks
2040 Bancroft Way
Suite 400
Berkeley, CA 94704
B. Issuance of the project for bid and construction approved by:

Robert Armijo, City Engineer Date
Registered Civil Engineer, RCE No. 63173
City of Richmond

END OF DOCUMENT

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
TABLE OF CONTENTS 00 01 00 - 1
DOCUMENT 00 01 00

TABLE OF CONTENTS

PROJECT MANUAL

INTRODUCTORY INFORMATION
Document 00 00 00 Project Title Page
00 00 01 Signature Page
00 01 00 Table of Contents

BIDDING REQUIREMENTS
Document 00 02 00 Invitation to Bid
00 10 00 Instructions to Bidders
00 41 00 Bid Form
Form A-1 Bidders Statement of Subcontractors
Form A-2 Bidders Statement of Major Suppliers
Noncollusion Affidavit
Business Verification Form and Good Faith Effort
Background Check Certification Form
Sanctuary City Compliance Form
Disclosure Statement for Limited Liability Companies

CONTRACTING REQUIREMENTS
Document 00 50 00 Construction Agreement
Construction Agreement
00 51 00 Special Conditions and Provisions
00 60 00 Bond and Insurance Forms
Bid Bond
Performance Bond
Payment Bond
Insurance Requirements
Insurance Coverage Verification
00 70 00 First Source Agreement
First Source Agreement
00 80 00 Community Workforce and Project Stabilization Agreement Community Workforce and Project Stabilization Agreement

SPECIFICATIONS
DIVISION 01 GENERAL REQUIREMENTS
Section 01 11 00 Summary of Work

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
TABLE OF CONTENTS 00 01 00 - 2
01 12 10 Project Management Software
01 20 00 Price and Payment Procedures
01 23 00 Alternates and Unit Pricing
01 25 10 Product Options and Substitutions
01 26 00 Contract Modification Procedures
01 26 10 Requests for Information
01 31 00 Project Meetings
01 32 16 Construction Schedule
01 33 00 Submittals
01 40 00 Quality Requirements
01 42 13 Abbreviations and Acronyms
01 42 16 General Definitions and References
01 45 29 Testing Laboratory Services
01 50 00 Temporary Facilities and Controls
01 52 10 Site Standards
01 56 39 Temporary Tree and Plant Protection
01 57 10 Storm Water Pollution Prevention Plan (SWPPP)
01 60 00 Materials and Equipment
01 66 10 Delivery, Storage and Handling
01 71 23 Construction Staking and Surveying
01 73 00 Execution
01 73 29 Cutting and Patching
01 74 19 Construction Waste Management and Disposal
01 77 00 Contract Closeout and Final Cleaning
01 78 23 Operation and Maintenance Data
01 78 36 Warranties
01 78 39 Record Documents
DIVISION 02 EXISTING CONDITIONS
Section 02 20 00 Utility Potholing
02 41 00 Demolition
DIVISION 03 CONCRETE
Section 03 30 00 CIP Concrete
DIVISION 04 MASONRY
Section 04 41 00 Site Boulders
DIVISION 05 METALS
Section 05 50 00 Metal Fabrications
DIVISION 10 SPECIALTIES
Section 10 14 00 Signage
DIVISION 11 EQUIPMENT
Section 11 68 13 Playground Equipment

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
TABLE OF CONTENTS 00 01 00 - 3
DIVISION 12 FURNISHINGS
Section 12 93 00 Site Furnishings
DIVISION 13 SPECIAL CONSTRUCTION
Section 13 00 00 Pre-Engineered Structures
DIVISION 26 ELECTRICAL
Section 26 05 00 Basic Materials and Methodologies
26 50 00 Lighting
DIVISION 31 EARTHWORK
Section 31 10 13 Site Preparation and Plant Protection
31 20 00 Earthwork
31 23 24 Trench Excavation and Backfill
31 25 13 Erosion Controls
DIVISION 32 EXTERIOR IMPROVEMENTS
32 11 23 Aggregate Base
32 12 16 Asphaltic Paving
32 13 13 Concrete Paving
32 14 19 Stabilized Decomposed Granite
32 18 16 Playground Protective Surfacing
32 31 13 Chain link Fences
32 31 19 Steel Metal Fences and Gates
32 84 00 Planting Irrigation
32 91 13 Soil Preparation
32 91 14 Bioretention Soils
32 93 00 Plants
DIVISION 33 UTILITIES
33 10 00 Water Utilities
33 30 00 Sanitary Sewage System
33 40 00 Storm Drainage System

APPENDICES
A. Geotechnical Report
B. City of Richmond Standard Details
C. Restroom Plans
D. Stage Shade Structure Plans
E. Pump Track Plans and Details

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
TABLE OF CONTENTS 00 01 00 - 4
F. Vertical Sculpture Plans and Structural Calculations G. Pitching and Musician Sculptures Plans and Structural Calculations H. Stage Art Concept Drawings

END OF DOCUMENT
INVITATION TO BID 00 02 00 - 1

CITY OF RICHMOND

PUBLIC WORKS DEPARTMENT

INVITATION TO BID
The Council of the City of Richmond will accept bids for the construction of:

CITY OF RICHMOND

SHIELDS REID

PARK IMPROVEMENTS PROJECT
Notice is hereby given that sealed bids for the City of Richmond Shields Reid Park Improvements Project as further described in the project manual will be received electronically through BidsOnline.

All bid forms must be electronically submitted by the due date and time or the bid will not be considered.

Bids are due via BidsOnline on Friday, March 29, 2024, at 2:00 PM. Bids will be opened publicly via BidsOnline. Please visit the City’s website at www.ci.richmond.ca.us/bids to register as a vendor, to order bid documents, and to submit bid documents.

Bids may be withdrawn prior to bid close.

There shall be one (1) pre-bid conference held at the Project Site (1410 Kelsey Street, Richmond, CA 94801) as follows:

Wednesday, March 13, 2024 at 11:00a.m.

It is not mandatory that bidding contractors attend the pre-bid conference. Bidders are strongly encouraged to visit the sites of the proposed work and fully acquaint themselves with the existing conditions. Bidders should fully inform themselves as to the facilities involved, the difficulties and restrictions attending the performance of the contract. Bidders should thoroughly examine and familiarize themselves with the Specifications and all other Contract Documents. The Contractor, by the execution of this Contract, shall in no way be relieved of any obligation under it, due to Contractor's failure to receive or examine any form or legal instrument, or to visit the site and acquaint themselves with the existing conditions. The owner will reject any claim based on facts regarding which the bidder should have been aware as a result of visiting the site or reading the Contract Documents.

The Engineer’s Estimate of Probable Construction Cost for the Base Bid Work is approximately:
$3,800,000.00
Bid Documents, including plans and specifications, can be ordered online as electronic files at no cost. You must be a registered vendor with the City of Richmond to place an order for bid INVITATION TO BID 00 02 00 - 2
documents. Please visit the City’s website at www.ci.richmond.ca.us/bids to register as a vendor and to order your bid documents.

Bid Documents, including plans and specifications, can also be purchased at the BPXpress ReproGraphics, 4903 Central Avenue, Richmond, CA 94804. Telephone BPXpress ReproGraphics at (510) 559-8299 for reproduction costs and lead-time requirements. Cost of reproduction shall be the responsibility of the bidder.

All questions relative to this bid must be submitted via the electronic BidsOnline system on the Q&A tab by 5:00 pm PST, on Wednesday, March 19, 2024. If the City of Richmond finds it necessary to issue an addendum, prospective bidders will receive e-mail notification of addendum. Otherwise, answers to questions received will be provided on the Q&A tab and notification will be sent accordingly. It is the bidder’s responsibility to periodically check the BidsOnline website, www.ci.richmond.ca.us/bids for any possible Addenda to the bid that may have been posted.

A certified check or bank draft, payable to the order of the City of Richmond, negotiable U.S.

Government Bonds (at par value) or a satisfactory Bid Bond executed by the Bidder and an acceptable surety, in an amount equal to ten percent (10%) of the total bid shall be submitted to the City of Richmond by the three apparent low bidders as identified by the City of Richmond within three working days of the bid submission and notification by the City of Richmond.

Attention is called to the fact that not less than the minimum salaries and wages as set forth in the Contract Documents must be paid on this project, and that the Contractor must ensure that employees and applicants for employment are not discriminated against because of their race, color, religion, sex, or national origin.

The City of Richmond reserves the right to reject any or all Bids or to waive any informality in the bidding.

Bids may be held by the City of Richmond for a period not to exceed sixty (60) days from the date of the opening of bids for the purpose of reviewing the Bids and investigating the qualifications of Bidders, prior to awarding of the Contract by the City Council.

Any protest pertaining to the proposed award or any other matter relating to the bidding procedure must be submitted in writing to the City no later than 4:00 P.M. of the second business day following the date of bid opening. The protestor must have actually submitted a bid directly to the City on the Project or have been specifically excluded from filing a bid due to an action by the City. A subcontractor of a party filing a bid on this project may not submit a bid protest on its own accord.

The City will review the bid protest and will issue its determination within a reasonable amount of time prior to bid award. These procedures and time limits are mandatory and are the bidder’s sole and exclusive remedy in the event of a
bid protest.

City of Richmond, a Municipal Corporation
Pamela Christian
Clerk of the City of Richmond

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
INSTRUCTIONS TO BIDDERS 00 10 00 - 1
DOCUMENT 00 10 00

INSTRUCTIONS TO BIDDERS

1.1 GENERAL INFORMATION
A. Bids are invited for construction for the Richmond Shields Reid Park Improvement Project, 1410 Kelsey Street, Richmond, California 94801.

B. Sealed bids will be received up to the time and date as indicated in the Invitation to Bid or as modified by Addenda. Bids received after that time will not be accepted.

1. Bids will be opened publicly via BidsOnline. Please visit the City’s website at www.ci.richmond.ca.us/bids to register as a vendor, to order bid documents, and to submit bid documents.

C. Copies of Contract Documents including plans and specifications are available as indicated in the Invitation to Bid.

D. Bids shall be clearly written without erasures or deletions.

1. Do not modify Bid Form or qualify bids.

2. Bids shall include valid state contractor's license number.

3. Bids to be signed by a duly authorized officer or agent.

4. Total sum of bid shall be written out and shown in numerals.

5. Where indicated, completion time shall not be altered.

6. Submit bids on total package including alternates if any.

E. Submission of bid signifies careful examination of Contract Documents and complete understanding of nature, extent and location of work to be performed.

F. Addenda shall be acknowledged in Bid Form by number and date and shall be a part of Contract Documents.

G. Bid Form shall include all Bidders Statements and other documentation as called for in the Bid Form, each completed in their entirety.

H. Bid Form and all supporting documents shall be electronically uploaded and submitted through BidsOnline. All bid forms must be electronically submitted by the due date and time or the bid will not be considered.

I. Bid Forms shall not be revised once submitted.

J. Bids may not be withdrawn for sixty calendar days after submittal, or for such extension as may be subsequently agreed in writing.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
INSTRUCTIONS TO BIDDERS 00 10 00 - 2

1. If bid contains inadvertent clerical error make written request for consideration to withdraw bid.

K. Owner reserves right to reject any or all bids and to waive any irregularity.

L. Owner reserves the right to award the project to the lowest responsible bidder as determined by base bid or by base bid plus alternates.

M. Submittal of bid signifies intent to execute a contract for construction, insurance certificates and performance and payment bonds.

N. The bidder will be deemed non-responsive if he/she submits incomplete forms or fails to submit all of the required forms and documentation.

1.2 ADDITIONAL INFORMATION AND INSTRUCTIONS
A. QUESTIONS AND COMMENTS

1. Questions, requests for clarification, or comments regarding the Bid Documents or the Scope of Work must be submitted in writing using the electronic BidsOnline system discussed in the Invitation to Bid. All clarifications and interpretations to this solicitation will be issued by written addenda on the BidsOnline system. No interpretation or clarification given orally or separately will be effective to alter or affect the solicitation documents unless confirmed by written addendum.

B. PRE-BID MEETING

1. Refer to the Invitation to Bid for information pertaining to the Pre-Bid Meeting(s) time and location.

C. BEGINNING OF WORK, TIME OF COMPLETION, AND LIQUIDATED DAMAGES

1. The Contractor shall commence work upon receipt of directions to proceed as stated in the "Notice to Proceed," issued by the City of Richmond after execution of the contract and shall complete the work within the allotted time of:
30 CALENDAR DAYS for preparation of site prior to Bike Pump Track construction
90 CALENDAR DAYS for the construction of the Bike Pump Track by American Ramp Company
335 CALENDAR DAYS for completion of work after Bike Pump Track construction
365 CALENDAR DAYS total for all Contractor required park construction 455 CALENDAR DAYS total for Bike Pump Track and Park Construction counting from and including the day stated as the starting date in the "Notice to Proceed."

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
INSTRUCTIONS TO BIDDERS 00 10 00 - 3

2. The Contractor shall pay to the City of Richmond the sum of $1,000 (One Thousand Dollars) per calendar day for each and every calendar day delay in finishing the work in excess of the number of calendar days prescribed above, except as extended by contract change order.

3. In addition, the City shall have the right to charge the Contractor and to deduct from the payments for the work the actual cost to the City for engineering, inspection and other overhead expenses which are directly chargeable to the Contract and which accrue during the period of such delay. The expenses and damages described above shall be deducted from any money due to the Contractor under this Contract. The Contractor and his sureties shall be liable for any such excess cost.

D. BID SECURITY

1. Submit properly prepared bid bond, certified check or cashier's check acceptable to and payable without condition to the City of Richmond.

2. A certified check or bank draft, payable to the order of the City of Richmond, negotiable U.S. Government Bonds (at par value) or a satisfactory Bid Bond executed by the Bidder and an acceptable surety, in an amount equal to ten percent (10%) of the total bid shall be submitted to the City of Richmond by the three apparent low bidders as identified by the City of Richmond within three working days of the bid submission and notification by the City of Richmond.

3. Bid security is required as guarantee bidder will enter into written contract and furnish insurance certificates, performance and payment bonds within time and in form as set forth in Contract Documents.
a. If after notification of acceptance a contract is not signed or insurance or bonds are not properly submitted due to no fault of Owner, bid security will be retained by Owner.

4. Bid bond shall be executed by bidder and by duly qualified surety company.

Reference Section 00 60 00 for a standard example of the Bid Bond form.

5. Bid security of three lowest and best bidders will be retained by Owner until Contract has been executed and acceptable insurance certificates and performance and payment bond have been furnished.
a. Bid security of other bidders will be returned within ten days after Owner has determined three lowest and best bidders.

6. It is understood that bid security shall not be considered as liquidated damages for failure of bidder to execute and deliver contract, insurance certificates and performance and payment bonds.
a. Bid security shall neither limit nor fix liability to Owner for damages sustained because of failure to execute and deliver required contract, insurance certificates and bonds.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
INSTRUCTIONS TO BIDDERS 00 10 00 - 4
E. INTERPRETATION OF DOCUMENTS

1. If there is doubt about the meaning of any part of Contract Documents, submit written request to the City of Richmond thru the BidsOnline Q&A tab.

2. Request for interpretations shall be delivered to Architect by the date and time indicated in the Invitation to Bid.

3. Bids shall be based only on interpretations as issued in addenda.

F. SUBSTITUTIONS DURING BIDDING

1. Base bids on products and systems specified in Contract Documents or listed by name in addenda.
a. Contractors and materials suppliers may request substitutions to be approved by Architect.
b. Submit substitution requests 14 calendar days prior to the date set for submission of bids. Submit substitution requests thru the BidsOnline Q&A tab.

2. Substitution Procedures:
a. Request for substitutions shall contain sufficient information to assess acceptability of product or system; insufficient information shall be grounds for rejection.
b. Approved substitutions shall be listed in addenda. Non-approved substitutions shall not be listed in addenda.
c. Substitutions may be requested for any product specified unless otherwise noted.
d. Substitutions may be requested after Contract is signed; requests shall be in accordance with requirements specified in Section 01 25 10 - Product Options and Substitutions.

1.3 LAWS AND ORDINANCES
A. The successful Contractor and all subcontractors used in the work will be required to hold or to obtain a City of Richmond business license for which the fee will not be waived. Prior to the start of work, the successful Contractor shall obtain all other required permits from the City of Richmond, for which the fees will not be waived. The successful Contractor shall also obtain any other permits required from other agencies for the completion of the project, for which the fees will be waived.

B. If any Contractor, or any subcontractor used in the work by the Contractor, is currently in violation of any federal, state or local law or ordinance, the Contractor's bid may be deemed to be non-responsible.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
INSTRUCTIONS TO BIDDERS 00 10 00 - 5
C. The Contractor and all subcontractors shall comply with the following City of Richmond Codes and Ordinances, which are incorporated into the Contract Documents by this reference:

1. Nondiscrimination Clause in City Contracts (RMC Chapter 2.28)

2. Business Opportunity Ordinance No. 16-12 N.S. (RMC Chapter 2.50)

3. Local Employment Program Ordinance No. 15-10 N.S. (RMC Chapter 2.56)

4. Living Wage Ordinance No. 15-17 N.S.(RMC Chapter 2.60) a. Except as provided in Section 2.60.080, the Living Wage Ordinance requires that an employer under contract valued at $25,000 or greater and/or an employers with ten or more employees provide to its covered employees the following minimum compensation terms for the duration of the covered period:
 Not less than $15.21/hour if employer pays at $1.50/hour/employee towards an employee medical benefits plan; or
 Not less than $16.71/hour if the employer does not provide the employees with such medical benefits plan.

5. Ordinance Banning the Requirement to Provide information of Prior Criminal Convictions on all Employment Applications No. 14-13 N.S. (“Ban the Box”) (RMC Chapter 2.65)

6. Sanctuary City Contracting and Investment Ordinance No. 12-18 N.S.

7. Disclosure Statement for Limited Liability Companies Resolution No. 86-21 D. City Ordinances may found in their entirety at:
https://www.ci.richmond.ca.us
https://library.municode.com/ca/richmond/codes/code_of_ordinances E. For general information, questions, requests for clarification, or comments regarding compliance with all local, state, and federal ordinances must be submitted in writing using the electronic BidsOnline system discussed in the Invitation to Bid. All clarifications and interpretations affecting the project will be issued by written addenda on the BidsOnline system. No interpretation or clarification given orally or separately will be effective to alter or affect the solicitation documents unless confirmed by written addendum.

1. For specific information or questions regarding compliance with local ordinances, contact:

City of Richmond
Employment and Training Department
330 25th Street, Richmond, CA 94804

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
INSTRUCTIONS TO BIDDERS 00 10 00 - 6
Telephone: (510) 307-8014

1.4 PREVAILING WAGE REQUIREMENT
A. All Contractors and Subcontractors performing services under this Contract shall pay their employees providing such services a minimum hourly prevailing wage rate as further described below.

B. In case of conflict between the Prevailing Wage as specified in this Section and any Federal Minimum Wage that may be specified elsewhere in these Specifications, the higher of the two shall prevail. Any amendments to the Federal Minimum Wage Determination issued up to 10 days prior to the bid opening date will become the part of the contract documents.

C. The Contractor and any subcontractor under the Contractor shall comply with Labor Code Sections 1774 and 1775. Pursuant to Section 1775, the Contractor and any subcontractor under the Contractor shall forfeit to the State or political subdivision on whose behalf the contract is made or awarded a penalty of not more than fifty dollars ($50) for each calendar day, or portion thereof, for each worker paid less than the prevailing rates as determined by the Director of Industrial Relations for the work or craft in which the worker is employed for any public work done under the contract by the Contractor or by any subcontractor under the Contractor in violation of the requirements of the Labor Code and in particular, Labor Code Sections 1770 to 1780, inclusive. The amount of this forfeiture shall be determined by the Labor Commissioner and shall be based on consideration of the mistake, inadvertence, or neglect of the Contractor or subcontractor in failing to pay the correct rate of prevailing wages, or the previous record of the Contractor or subcontractor in meeting their respective prevailing wage obligations, or the willful failure by the Contractor or subcontractor to pay the correct rates of prevailing wages. A mistake, inadvertence, or neglect in failing to pay the correct rate of prevailing wages is not excusable if the Contractor or subcontractor had knowledge of the obligations under the Labor Code.

In addition to the penalty and pursuant to Labor Code Section 1775, the difference between the prevailing wage rates and the amount paid to each worker for each calendar day or portion thereof for which each worker was paid less than the prevailing wage rate shall be paid to each worker by the Contractor or subcontractor. If a worker employed by a subcontractor on a public works project is not paid the general prevailing per diem wages by the subcontractor, the prime contractor of the project is not liable for the penalties described above unless the prime contractor had knowledge of that failure of the subcontractor to pay the specified prevailing rate of wages to those workers or unless the prime contractor fails to comply with all of the following requirements:

1. The contract executed between the contractor and the subcontractor for the performance of work on the public works project shall include a copy of the requirements in Sections 1771, 1775, 1776, 1777.5, 1813 and 1815 of the Labor Code.

2. The contractor shall monitor the payment of the specified general prevailing rate of per diem wages by the subcontractor to the employees, by periodic review of the certified payroll records of the subcontractor.

3. Upon becoming aware of the subcontractor's failure to pay the specified prevailing rate of wages to the subcontractor's workers, the contractor shall diligently take

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
INSTRUCTIONS TO BIDDERS 00 10 00 - 7
corrective action to halt or rectify the failure, including, but not limited to, retaining sufficient funds due the subcontractor for work performed on the public works project.

4. Prior to making final payment to the subcontractor for work performed on the public works project, the contractor shall obtain an affidavit signed under penalty of perjury from the subcontractor that the subcontractor has paid the specified general prevailing rate of per diem wages to the subcontractor's employees on the public works project and any amounts due pursuant to Section 1813 of the Labor Code.

D. Pursuant to Section 1775 of the Labor Code, the Division of Labor Standards Enforcement shall notify the Contractor on a public works project within 15 days of the receipt by the Division of Labor Standards Enforcement of a complaint of the failure of a subcontractor on that public works project to pay workers the general prevailing rate of per diem wages. If the Division of Labor Standards Enforcement determines that employees of a subcontractor were not paid the general prevailing rate of per diem wages and if the Department did not retain sufficient money under the contract to pay those employees the balance of wages owed under the general prevailing rate of per diem wages, the contractor shall withhold an amount of moneys due the subcontractor sufficient to pay those employees the general prevailing rate of per diem wages if requested by the Division of Labor Standards Enforcement. The Contractor shall pay any money retained from and owed to a subcontractor upon receipt of notification by the Division of Labor Standards Enforcement that the wage complaint has been resolved. If notice of the resolution of the wage complaint has not been received by the Contractor within 180 days of the filing of a valid notice of completion or acceptance of the public works project, whichever occurs later, the Contractor shall pay all moneys retained from the subcontractor to the Department. These moneys shall be retained by the Department pending the final decision of an enforcement action.

E. Pursuant to the requirements in Section 1773 of the Labor Code, the City has obtained the general prevailing rate of wages (which rate includes employer payments for health and welfare, pension, vacation, travel time and subsistence pay as provided for in Section 1773.8 of the Labor Code, apprenticeship or other training programs authorized by Section 3093 of the Labor Code, and similar purposes) applicable to the work to be done, for straight time, overtime, Saturday, Sunday and holiday work. The holiday wage rate listed shall be applicable to all holidays recognized in the collective bargaining agreement of the particular craft, classification or type of workmen concerned.

F. The general prevailing wage rates and any applicable changes to these wage rates are available from the California Department of Industrial Relations' Internet Web Site at: http://www.dir.ca.gov.

G. The wage rates determined by the Director of Industrial Relations for the project refer to expiration dates. Prevailing wage determinations with a single asterisk after the expiration date are in effect on the date of advertisement for bids and are good for the life of the contract. Prevailing wage determinations with double asterisks after the expiration date indicate that the wage rate to be paid for work performed after this date has been determined. If work is to extend past this date, the new rate shall be paid and incorporated in the contract. The Contractor shall contact the Department of

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
INSTRUCTIONS TO BIDDERS 00 10 00 - 8
Industrial Relations as indicated in the wage rate determinations to obtain predetermined wage changes.

H. Pursuant to Section 1773.2 of the Labor Code, general prevailing wage rates shall be posted by the Contractor at a prominent place at the site of the work.

I. Changes in general prevailing wage determinations which conform to Labor Code Section 1773.6 and Title 8 California Code of Regulations Section 16204 shall apply to the project when issued by the Director of Industrial Relations at least 10 days prior to the date of the Notice to Contractors for the project.

J. The City of Richmond will not recognize any claim for additional compensation because of the payment by the Contractor of any wage rate in excess of the prevailing wage rate set forth in the contract. The possibility of wage increases is one of the elements to be considered by the Contractor in determining the bid, and will not under any circumstances be considered as the basis of a claim against the City on the contract.

1.5 CONTRACT BONDS
A. General

1. The successful bidder shall furnish to the City of Richmond the two bonds required by the State of California Contract Act. Said bonds shall be furnished in a form satisfactory to the City. Each of said bonds shall be executed in an amount equal to 100% of the contract price.

B. Faithful Performance

1. One of said bonds shall guarantee the faithful performance of the Contract by the Contractor. A sample Performance Bond is enclosed, see Section 00 60 00.

C. Payment

1. One of said bonds shall guarantee payment of all claims for labor, materials, provisions, provender and supplies furnished and any amounts required to be deducted withheld and paid over to the Franchise Tax Board from the wages of employees of the Contractor and his subcontractor pursuant to Section 18806 of the Revenue and Taxation Code. Care shall be taken to assure that the payment bond includes the precise provisions which Section 3248, Subsection (b) of the California Civil Code requires. A sample payment bond is enclosed, see Section 00 60 00.

D. Alterations

1. All alterations, extensions of time, extra and additional work, and other changes authorized by these Specifications or any part of the Contract may be made without securing the consent of the surety or sureties on the Contract bonds.

1.6 INDEMNIFICATION AND INSURANCE

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
INSTRUCTIONS TO BIDDERS 00 10 00 - 9
A. Indemnification

1. Contractor shall indemnify and save the City, its agents, officers and employees harmless from and against any and all liability, claims, suits, actions, damages, penalties and/or cause of action arising during the term of this Contract out of any personal injury, bodily injury, loss of life or damage to property, violation of any Federal, State or municipal law or ordinance or other cause in connection with the activities of Contractor, its subcontractors, agents and employees under this Contract or on account of the performance or Character of the work, unforeseen difficulties, accidents, occurrences or other causes and from and against all costs, counsel fees, expenses incurred in obtaining expert testimony and the attendance of witnesses, expenses and liability incurred in and about any such claim, the investigation thereof or the defense of any action or proceedings brought thereon, and from and against any orders, judgments or decrees which may be entered therein unless arising out of the sole negligence or willful misconduct of the City.

Approval of the insurance coverage does not relieve the Contractor or subcontractors of liability under the Indemnification Clause.

B. Insurance

1. Worker's Compensation
(a) Contractor, at its own cost and expense shall carry and maintain statutory Workers' Compensation Insurance and Employer's Liability with limits not less than One Million Dollars ($1,000,000) with an insurance carrier satisfactory to the City. Policy shall provide that no cancellation, major change in coverage or expiration shall become effective or occur until at least ten (10) days after receipt of such notice by City. In the event Contractor is self-insured, it shall furnish Certificate of Permission to Self-Insure signed by the Department of Industrial Relations Administration of Self-Insurance in Sacramento, California. If any injury occurs to any employee of Contractor for which the employee, or his dependents in the event of his death is entitled to compensation from the City under the provisions of the Worker's Compensation Act, as amended or for which compensation is claimed from the City, the City may retain out of sums due the Contractor under this Contract an amount sufficient to cover such compensation as fixed by said Act, until such compensation is paid or until it is determined that no compensation is due and if City is compelled to pay such compensation, it will deduct and retain from the sums due the Contractor the amount so paid.

2. Liability and Property Damage
(a) Contractor at its own cost and expense shall maintain liability and property damage insurance for the period covered by this Contract in the amount of One Million ($1,000,000) Dollars per occurrence combined single limit coverage. Such coverage shall include but shall not be limited to protection against claims arising from bodily and personal injury, including death resulting therefrom, and damage to property resulting from activities contemplated under this Contract, use of owned and non-owned automobiles, products and completed operations. Such insurance shall be with insurers and under forms of policies satisfactory in all respects to the City and shall

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
INSTRUCTIONS TO BIDDERS 00 10 00 - 10
provide that notice must be given to City at least forty-five (45) days prior to cancellation or material change. The following endorsements shall be attached to the policy:
 Policy shall cover on an "occurrence" basis.
 Policy must cover personal injuries as well as bodily injuries. Exclusion of contractual liability must be eliminated from personal injury endorsement.
 Broad form property damage endorsement must be attached.  Policy must cover contractual liability by amending the definition of "incidental contract" to include any written contract.
(b) City, its officers and employees shall be named as an additional insured, and the policy shall stipulate that this insurance will operate as primary insurance and that no other insurance affected by the City will be called upon to contribute to a loss suffered by Contractors hereunder.

3. Builder’s Risk Insurance
(a) Contractor at its own cost and expense shall maintain builder’s risk insurance for the period covered by this Contract.

4. General Requirements
(a) Coverage Verification form attached hereto shall be completed, signed by Contractor's insurance representative and returned to the City prior to the effective date of this Contract. Coverage Verification form must be approved by the City Attorney's office before any payments will be made under this Contract.
(b) Insurance certificates and endorsements shall be reviewed and approved by the City’s Risk Management before work may begin. The City of Richmond reserves the right to require complete, certified copies of all required insurance policies including endorsements affecting the coverage at any time. (c) Upon notification of receipt by the City of a Notice of Cancellation, major change in coverage or expiration, Contractor shall file with the City a certified copy of the required new renewal policy and certificates for such policies (or in lieu of this a new completed Coverage Verification form). (d) If at any time during the life of the Contract or any extension the Contractor fails to maintain the required insurance in full force and effect, all work under the Contract shall be discontinued immediately and all payments due or that become due to the Contractor will be withheld until notice is received by the City that the required insurance has been restored to full force and effect and that the premiums therefore have been paid for a period satisfactory to the City. Any failure to maintain the required insurance will be sufficient cause for City to terminate the Contract.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
INSTRUCTIONS TO BIDDERS 00 10 00 - 11

1.7 POST-BID INFORMATION
A. Submit following upon notification by Architect:

1. Statement of costs for each major item of work or cost breakdown for each subcontractor and major materials supplier.

2. Designation of work to be performed by Contractor's own forces.

3. Names and addresses of subcontractors to perform work or labor in excess of one percent of total bid, excluding alternates.

4. List of major materials suppliers providing materials in excess of one percent of total bid, excluding alternates.

B. Prior to award of Contract, Architect will provide notification in writing if either Owner or Architect has objection to any listed person or organization.

1. If there is a written objection, the bid may be withdrawn without forfeiture of security.

2. If an acceptable substitute is submitted with an increase in bid price to cover difference in cost of substitution, Owner reserves right to accept increased price or disqualify bid.

3. Subcontractors and suppliers listed and accepted shall be used on work for which they were bid and shall not be changed except with written approval of Owner and Architect.

END OF DOCUMENT
BID FORM 00 41 00 - 1

CITY OF RICHMOND

PUBLIC WORKS DEPARTMENT

BID FORM
Electronically submit this BID FORM thru BidsOnline at or before the time and date and location referenced in the Invitation to Bid for the Project noted below.

1.1 PROJECT
A. In compliance with proposed Contract Documents for construction of:

RICHMOND

SHIELDS REID
Park Improvements Project
1410 Kelsey Street
Richmond, California 94801
B. Including Addenda Numbers ____ ____ ____ ____ ____ ____ ____ ____ C. The undersigned has become thoroughly familiar with the terms and conditions of proposed Contract Documents and with local codes and conditions affecting performance and costs of Work at place where Work is to be completed.

D. The undersigned has fully inspected the site in all particulars.

E. The undersigned hereby proposes and agrees to fully perform Work as follows.

1. The undersigned agrees to perform Work within time agreed upon.

2. The undersigned agrees to perform Work in strict accordance with proposed Contract Documents, including furnishing any and all labor and materials.

3. The undersigned agrees to do all work required to construct and complete said Work in accordance with Contract Documents.

BID FORM 00 41 00 - 2

1.2 BID SCHEDULE
Item
No.

BASE BID IMPROVEMENTS QTY. UNIT TOTAL COST, $
1 Mobilization and SWPPP/Erosion Control 1 LS
2 Site Clearing and Demolition 1 LS
3 Earthwork, Excavation and Grading 1 LS
4 Underground Utilities 1 LS
5 Rigid and Flexible Paving, Safety Surfacing 1 LS
6 5-12 Playground and Fitness Station Equipment 1 LS
7 Stage Shade Structure including foundation and
slab on grade 1 LS
8 Restroom including foundation, slab on grade and
utility connections 1 LS
9 Guardrails, Gates, and Chain Link Fence 1 LS
10 Irrigation System 1 LS
11 Planting Preparation and Planting & Landscaping,
Bioretention 1 LS
12 Electrical, Lighting, Security Cameras 1 LS
13 Site Furnishing, Signage, Water Fountain 1 LS
14 All other scope (not mentioned above) included in
bid plans, specifications and addendums 1 LS
15 General Conditions and General Requirements 1 LS
16 Bonds and Insurance 1 LS
17 Overhead and Profit 1 LS

Total Base Bid in Figures 1 LS

Total Base Bid in Words: _____________________________________________________ __________________________________________________________________________ In case of discrepancy between total of itemized bid amounts and the total base bid amount, total base bid amount will be considered as the bid amount.

Item
No.

BID ADD ALTERNATE 1 QTY. UNIT TOTAL COST, $
BA1
Nature Play Area including zip line, full round
steppers, engineered wood fiber, picnic tables,
concrete mow band in the Nature Play Area 1 LS
BID FORM 00 41 00 - 3

Item
No.

BID ADD ALTERNATE 2 QTY. UNIT TOTAL COST, $
BA2 Perimeter Fence including footings and gates 1 LS

Item
No.

BID ADD ALTERNATE 3 QTY. UNIT TOTAL COST, $
BA3 Basketball Courts - Repaint and restripe two (2)
existing basketball courts to existing dimension
and colors 1 LS

Item
No.

BID ADD ALTERNATE 4 QTY. UNIT TOTAL COST, $
BA4 Basketball Courts - 2” grind and overlay of
blacktop area and repaint and restripe two (2)
existing basketball courts to existing dimension
and colors 1 LS

1.3 BIDDER STATEMENTS
A. The Contractor shall include Bid Form A-1, Bidder Statement of Subcontractors, completed in its entirety with the Bid Form.

B. The Contractor shall include Bid Form A-2, Bidders Statement of Major Suppliers, completed in its entirety with the Bid Form.

C. The Contractor shall complete and include the Noncollusion Affidavit with the Bid Form.

D. The Contractor shall complete and include the Business Verification Form.

E. The Contractor shall complete and include the Proof of Solicitation – Good Faith Effort Requirement Form.

F. The Contractor shall complete and include the Background Check Certification Form.

G. The Contractor shall include a copy of their company’s current employment agreement
H. The Contractor shall complete and include the Sanctuary City Compliance Statement.

BID FORM 00 41 00 - 4
I. The Contractor shall complete and include the Disclosure Statement for Limited Liability Companies

1.4 AWARD OF CONTRACT
A. It is understood that Owner reserves right to reject this bid but that it shall remain open and not be withdrawn for a period of sixty calendar days from date prescribed for its opening.

B. Undersigned agrees to execute and deliver Contract to Owner in accordance with this bid if written acceptance is mailed or delivered before bid is withdrawn by written notification to Owner.

1.5 IDENTIFICATION
A. Notice of acceptance, or request for additional information, may be addressed to the undersigned at address set forth below.

B. The names of all persons interested in the foregoing bid as principals are:
_______________________________________________________________________ _______________________________________________________________________ _______________________________________________________________________

1. Important Notice: If a corporation, give legal name of corporation, state where incorporated, and names of president and secretary; if a partnership, give name of firm and names of all individual co-partners composing the firm; if an individual, give first and last names in full.

C. License: Contractor is licensed in accordance with an act for registration of contractors with license number and DIR registration number:

License #__________________________ DIR # _______________________________ D. Business Address:
_______________________________________________________________________ _______________________________________________________________________ _______________________________________________________________________ E. Telephone Number: _____________________________________________ F. Date of Bid: ____________________________________________________ G. Signature of person(s) with legal authority to sign contracts:
_______________________________________________________________________ _______________________________________________________________________ _______________________________________________________________________ BID FORM 00 41 00 - 5

1.6 BID SECURITY
A. Bid security as described in Document 00 10 00 - Instructions for Bidders for an amount equal to not less than ten percent (10%) of total base bid shall be submitted to the City of Richmond by the three apparent low bidders as identified by the City of Richmond within three working days of the bid submission and notification by the City of Richmond.

END OF BID FORM

RICHMOND SHIELDS REID
Park Improvements Project
Form A-1 Page ______ of ______ (use multiple pages as necessary) FORM A-1

BIDDER STATEMENT OF SUBCONTRACTORS
NAME OF BIDDER: __________________________________ PROJECT NAME OR DESCRIPTION: _____________________________________________

COMPANY NAME,
ADDRESS, PHONE #
LICENSE #
DIR #
SCOPE

DESCRIPTION
CHECK
BOX IF

FIRM IS
RBE

PROPOSED

SUBCONTRACTOR
AMOUNT
% SHARE
OF

PRIME'S

TOTAL BID

BIDDER NAME SIGNATURE

RICHMOND SHIELDS REID
Park Improvements Project
Form A-1 Page ______ of ______ (use multiple pages as necessary) FORM A-1

BIDDER STATEMENT OF SUBCONTRACTORS
NAME OF BIDDER: __________________________________ PROJECT NAME OR DESCRIPTION: _____________________________________________

COMPANY NAME,
ADDRESS, PHONE #
LICENSE #
DIR #
SCOPE

DESCRIPTION
CHECK
BOX IF

FIRM IS
RBE

PROPOSED

SUBCONTRACTOR
AMOUNT
% SHARE
OF

PRIME'S

TOTAL BID

BIDDER NAME SIGNATURE

NONCOLLUSION AFFIDAVIT TO BE EXECUTED AND SUBMITTED WITH BID All bidders shall complete the following form and submit it with their bids:

State of California
County of ________________
[name]____________________________, being first duly sworn, deposes and says that he or she is [title]______________________ of [company]________________________, the party making the foregoing bid that the bid is not made in the interest of, or on behalf of, any undisclosed person, partnership, company, association, organization, or corporation; that the bid is genuine and not collusive or sham; that the bidder has not directly or indirectly induced or solicited any other bidder to put in a false or sham bid, and has not directly or indirectly colluded, conspired, or connived, or agreed with any bidder or anyone else to put in a sham bid, or that anyone shall refrain from bidding; that the bidder has not in any manner, directly or indirectly, sought by agreement, communication, or conference with anyone to fix the bid price of the bidder or any other bidder, or to fix any overhead, profit, or cost element of the bid price, or of that of any other bidder, or to secure any advantage against the public body awarding the contract of anyone interested in the proposed contract; that all statements contained in the bid are true; and, further, that the bidder has not, directly or indirectly, submitted his or her bid price or any breakdown thereof, or the contents thereof, or divulged information or data relative thereto, or paid, and will not pay, any fee to any corporation, partnership, company association, organization, bid depository, or to any member or agent thereof to effectuate a collusive or sham bid.
_________________________________________________ ____________________________ Signature Date

STATE OF CALIFORNIA )
)ss.

COUNTY OF _____________)
On __________________________, 2009, before me, the ________________, a Notary Public, personally appeared ____________________________, personally known to me (or proved to me on the basis of satisfactory evidence) to be the person(s) whose name(s) is/are subscribed to the within instrument, and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.

WITNESS my hand and official seal.
__________________________________

City of Richmond

CERTIFICATION FORM
************************************************************************************************** Deliver the completed form and all necessary attachments to, enter address an suite number If there are any question please contact, name, job title at phone/e-mail address

1. Do you have ten (10) or more Full-Time-Equivalent Employees?  YES  NO If YES move on…

2. Are you required by Federal or State Law to perform criminal background checks?  YES  NO

3. Please identify the positions and regulations that require you to preform criminal background checks? _______________________________________________________________________________________________ _______________________________________________________________________________________________ _______________________________________________________________________________________________ _______________________________________________________________________________________________

4. Do you contend that some or all of your position(s) meet the definition of ‘sensitive positions’, as defined in the Richmond Municipal Code, Section 2.65.030 (h)?
_______________________________________________________________________________________________ _______________________________________________________________________________________________ _______________________________________________________________________________________________ _______________________________________________________________________________________________

5. Please identify position(s) and specify why you contend they are ‘sensitive’, within the meaning of the ordinance. _______________________________________________________________________________________________ _______________________________________________________________________________________________ _______________________________________________________________________________________________ _______________________________________________________________________________________________

6. Please provide job descriptions for all your ‘sensitive positions’. _______________________________________________________________________________________________ _______________________________________________________________________________________________ _______________________________________________________________________________________________ _____________________________________________________________________________________________

7. Please provide a copy of your employment application.  See attached applications
************************************************************************************************** Vendor Name: ___________________________________ Owner Name: ______________________________________ Mailing Address: ____________________________________________________________________________________ Street City State Zip
Address to which notices from the City are to be directed (if different than above):

Name: ____________________________________________________________________________________________ Address: __________________________________________________________________________________________ Owner Signature Date
I declare under penalty of perjury that the foregoing is true and correct.

CITY OF RICHMOND
Sanctuary City Compliance Statement
The undersigned, an authorized agent of (hereafter
"Contractor"), has had an opportunity to review the requirements of City of Richmond Ordinance 12-18 (hereafter "Sanctuary City Contracting Ordinance" or “SCCO”). Contractor understands and agrees that the City may choose with whom it will maintain business relations and may refrain from contracting with any person or entity that provides Data Broker or Extreme Vetting services to the U.S. Immigration and Customs Enforcement Division of the United States Department of Homeland Security (“ICE”). Contractor understands the meaning of the following terms used in the SCCO:
a. "Data Broker” means either of the following:
i. The collection of information, including personal information about consumers, from a wide variety of sources for the purposes of reselling such information to their customers, which include both private-sector business and government agencies; ii. The aggregation of data that was collected for another purpose from that for which it is ultimately used.
b. “Extreme Vetting” means data mining, threat modeling, predictive risk analysis, or other similar services."
Contractor understands that it is not eligible to receive or retain a City contract if at the time the Contract is executed, or at any time during the term of the Contract, it provides Data Broker or Extreme Vetting services to ICE.

Contractor further understands and agrees that Contractor's failure to comply with the SCCO shall constitute a material default of the Contract and the City Manager may terminate the Contract and bar Contractor from bidding on future contracts with the City for five (5) years from the effective date of the contract termination.

By executing this Statement, Contractor certifies that it complies with the requirements of the SCCO and that if at any time during the term of the Contract it ceases to comply, Contractor will promptly notify the City Manager in writing. Any person or entity who knowingly or willingly supplies false information in violation of the SCCO shall be guilty of a misdemeanor and subject to a $1,000 fine.

Based on the foregoing, the undersigned declares under penalty of perjury under the laws of the State of California that the foregoing is true and correct. Executed this day of , 20 , at , California.

Printed Name: Title:

Signed: Date:

Business Entity:

Vendor SCCO Compliance Statement (Augt2020)
Disclosure Statement for Limited Liability Companies
This Statement Shall be included with all Bid and Proposal Submissions Is your Business a Limited Liability Company (LLC)? YES NO If you answered YES, please provide the City with the names and business addresses of any and all shareholders, directors, officers, members, managers, other authorized persons, partners, and “Beneficial Owners” of the applying LLC. A Beneficial Owner is any person or entity who: (1) exercises substantial control over the applying LLC; (2) owns 25% or more of the interest in the applying LLC; or (3) receives substantial economic benefits from the assets of the applying LLC.

If any LLC shareholder, director, officer, member, manager, other authorized person, partner, or Beneficial Owner is itself an LLC or other business entity, the names and business addresses must also be provided for any and all shareholders, directors, officers, members, managers, other authorized persons, partners, and Beneficial Owners of that LLC or other business entity all the way up through each entity in the organizational chart until ultimate ownership by individual person(s) is/are disclosed.

Name: _____________________
Title: _____________________
Address:__________________________________________
Name: _____________________
Title: _____________________
Address:__________________________________________
Name: _____________________
Title: _____________________
Address:__________________________________________
☐ Check this box if additional ownership information is attached to this Disclosure Statement.

In signing this Disclosure Statement, I represent that the information submitted in this Disclosure Statement, and any attachments, is true and correct.

Signature: _____________________
Printed Name: _____________________
Title: _____________________
Date: _____________________

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CONSTRUCTION AGREEMENT 00 01 00 - 1
DOCUMENT 00 50 00

CONSTRUCTION AGREEMENT

GENERAL INFORMATION
A. The City of Richmond Construction Agreement and all referenced Exhibits in the Contract Documents shall be the agreement between the City and the Contractor.

B. A sample copy of this agreement is bound herein for reference.

END OF DOCUMENT
1 2018_Final Form

CONSTRUCTION AGREEMENT
This Construction Agreement (“Agreement”) is made and entered into this ____ day of ____, 2018, by and between the City of Richmond, a municipal corporation and charter city (“City”) and __________________, [IDENTIFY CORPORATE FORM] (“Contractor”), with reference to the following facts. The parties may be referred to in this Agreement individually as “Party” and collectively as the “Parties.”

RECITALS
A. On ______________, the City circulated an Invitation for Bids seeking contractors willing to undertake the construction of _________________, located at ____________ (the “Project”).

B. Contractor submitted the lowest responsive bid and has been determined to be responsible.

C. City now desires to contract with Contractor to furnish construction and related services for the Project.

NOW THEREFORE, in consideration of the promises and agreements hereinafter set forth, and intending to be bound hereby, the Parties agree as follows:

ARTICLE I

CONSTRUCTION OF PROJECT
Section 1.1 Contract Documents.

Project Specifications – including the Notice to Prospective Bidders, Invitation for Bids, Instructions to Bidders, Special Provisions, Description of Work, Construction Details (including all plans and specifications), and Proposal Package, along with any Requests for Information (RFI), responses to RFI, and addenda issued prior to the deadline for submitting bids [THIS

LIST MAY BE MODIFIED TO PROVIDE A MORE DETAILED DESCRIPTION OF THE DOCUMENTS FOR YOUR PROJECT – FOR EXAMPLE, YOU MAY SPECIFY THE NUMBER OF RFI/RESPONSES TO RFI THAT RE INCLUDED] – Contractor’s Proposal attached as Exhibit A, and this Agreement, constitute the “Contract Documents.” Section 1.2 Construction.

Contractor shall furnish all labor, materials, methods, processes, implements, tools and machinery, within the time frames set, and do all the things necessary for the proper completion of the work shown and described in Contract Documents.
2 2018_Final Form
Section 1.3 Payments.

Contractor agrees to receive and accept the sums set forth in the Bid Schedule attached as part of the Proposal, as full compensation for furnishing all materials and doing all the work contemplated and required by this Agreement, and for all loss or damage arising out of the nature of the undertaking of the construction of the Project, or from the acts of the elements, or from any unforeseen difficulties or obstructions which may arise or be encountered in the prosecution of the construction of the Project until its completion and acceptance by the City, and for all expenses incurred by or in consequence of the suspension or discontinuance of the construction of the Project, and for well and faithfully performing the construction of the Project and the whole thereof, in the manner and according to the Contract Documents.

Section 1.4 Discovery of Hazardous Waste or Unusual Conditions. (a) Promptly and before the following conditions are disturbed, the Contractor shall notify the City in writing of any:
(1) Material that the Contractor believes may be hazardous waste, as defined in Section 25117 of the Health and Safety Code, that is required to be removed to a Class I, Class II, or Class III disposal site in accordance with provisions of existing law.
(2) Subsurface or latent physical conditions at the site differing from those indicated by information about the site made available to bidders prior to the deadline for submitting bids.
(3) Unknown physical conditions at the site of any unusual nature, different materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in this Agreement. (b) The City shall promptly investigate the conditions, and if it finds that the conditions do materially so differ, or do involve hazardous waste, and cause a decrease or increase in the Contractor’s cost of, or the time required for, performance of any part of the work shall issue a Change Order under the procedures described in this Agreement. (c) In the event that a dispute arises between the City and the Contractor whether the conditions materially differ, or involve hazardous waste, or cause a decrease or increase in the Contractor’s cost of, or time required for, performance of any part of the work, the Contractor shall not be excused from any scheduled completion date provided for by this Agreement, but shall proceed with all work to be performed under this Agreement. The Contractor shall retain any and all rights provided either by contract or by law which pertain to the resolution of disputes and protests between the Parties.

Section 1.5 Laws and Regulations.
(a) The Project work shall proceed only after procurement of each permit, license, or other authorization that may be required by any governmental agency having jurisdiction, and Contractor shall be responsible to the City for the procurement and maintenance thereof. 3 2018_Final Form
(b) Contractor shall cause all work performed in connection with construction of the Project to be performed in compliance with (i) all applicable laws, ordinances, rules and regulations now in force or that may be enacted hereafter; (ii) all conditions of Project approval and mitigation measures included in any adopted or certified environmental document prepared for the Project; and (iii) all directions, rules and regulations of any fire marshal, health officer, building inspector, or other officer of every governmental agency now having or hereafter acquiring jurisdiction, provided that such direction given during construction does not conflict with conditions of Project approval or mitigation measures. (c) Contractor shall and shall cause its subcontractors to pay prevailing wages in the construction of the Project as those wages are determined pursuant to Labor Code Sections 1720 et seq., and implementing regulations of the Department of Industrial Relations, and to comply with all other applicable federal, State and local laws, regulations and ordinances pertaining to labor standards insofar as those laws, regulations and ordinances apply to the performance of this Agreement, including any applicable City of Richmond employment requirements, including but not limited to the City’s Living Wage Ordinance (Richmond Municipal Code Chapter 2.60), the City’s Business Opportunity Ordinance (Richmond Municipal Code Chapter 2.50), and the City’s Local Employment Program Ordinance (Richmond Municipal Code Chapter 2.56).

During the construction of the Project, Contractor shall post at the construction site the applicable prevailing rates of per diem wages. Contractor shall indemnify, hold harmless and defend, (with counsel reasonably acceptable to the City) the City against any claims for damages, compensation, fines, penalties or other amounts arising out of failure or alleged failure of any person or entity (including Contractor and its subcontractors) to pay prevailing wages in connection with construction of the Project. This Section 1.5(c) shall survive the termination of this Agreement.
(d) Contractor and all subcontractors shall maintain accurate payroll records showing the name, address, social security number, work classification, straight time and overtime hours worked each day and week, and the actual per diem wages paid to each journeyman, apprentice, worker and others employed on the Project. Each payroll record shall contain or be verified by a written declaration made under penalty of perjury, stating both of the following: (1) the information contained in the payroll record is true and correct, and (2) the employer has complied with the requirements of Labor Code Section 1771 (prevailing wage provisions), Section 1811 (eight-hour day, forty-hour week provisions), and Section 1815 (overtime compensation) for any work performed by his or her employees on the Project. The Contractor shall provide certified payroll records to the City each week, no later than ten (10) days after the end of a weekly pay period. Pay records shall be maintained and made available in accordance with Labor Code Section 1776. In addition, Contractor shall and shall cause its subcontractors promptly to deliver to the City, upon request, documents verifying compliance with the Living Wage Ordinance, which include documents which evidence that each affected employee has been notified regarding the wages required to be paid pursuant to the Living Wage Ordinance.

Such wages shall also be posted at the construction site. This Section 1.5(d) shall survive the termination of this Agreement.
4 2018_Final Form
Section 1.6 Inspections.

Contractor shall permit and facilitate, and shall require its subcontractors to permit and facilitate, observation and inspection of the Project by the City and by public authorities at all times for the purposes of determining compliance with this Agreement and permits issued to perform the Project work. In so doing, Contractor shall provide access for testing and inspections. Contractor shall coordinate and schedule all testing and inspections required on the Project with the required advance notice as defined in the Project Specifications.

Section 1.7 Equal Opportunity.
(a) During the construction of the Project there shall be no discrimination on the basis of race, color, creed, religion, age, sex, sexual orientation, marital status, national origin, ancestry, or disability in the hiring, firing, promoting, or demoting of any person engaged in the construction work.
(b) In addition, Contractor agrees to observe the provisions of Section 2.28.030 of the Richmond Municipal Code, obligating Contractor and its subcontractors to refrain from discriminatory employment or subcontracting practices on the basis of race, color, sex, sexual orientation, religion, creed, national origin or ancestry of any employee, any applicant for employment or any potential subcontractor.

Section 1.8 Working Hours.

Eight hours of labor is a legal day’s work. Any worker’s time of service is restricted to eight hours during any calendar day, and 40 hours during a calendar week, unless overtime compensation is paid at not less than one and one-half times the basic rate of pay. The Contractor shall be assessed a penalty of twenty-five dollars ($25) for each day a worker is employed in violation of these requirements.

Section 1.9 Insurance and Bond Requirements.
(a) In accordance with California Labor Code Section 3700, Contractor must secure Workers’ Compensation coverage for its employees. Prior to performing any work, Contractor must execute a certification in the form set out at California Labor Code Section 1861. (b) Contractor shall submit to the City evidence of the insurance and payment and performance bond coverage meeting the requirements set forth in the Project Specifications. Proof of insurance and bonding related to the construction of the Project shall be provided to the City not more than (10) days after award of the contract. The City shall review and approve or disapprove of the evidence of insurance within twenty (20) days after submittal of complete information in the form required by the City. If the City disapproves the evidence of insurance, it shall specify in writing the reasons for such disapproval. Contractor shall resubmit the information required within ten (10) days. The review and submittal periods for resubmittals shall be reduced to a ten (10) day review period for the City and a five (5) day period for resubmittal by Contractor and shall continue to apply until the City approves the evidence of insurance coverage, but in no event shall the 5 2018_Final Form
submittal and review period continue for more than forty-five (45) days. If, after forty-five (45) days the Contractor has not provided evidence of insurance and bond coverage meeting the requirements of the City, the City shall terminate the contract and may either award the work to the next lowest responsive responsible bidder or issue a new request for bids. (If the City issues a new request for bids, the Contractor shall be disqualified from re-bidding the work because of the failure to provide timely proof of insurance and/or bond coverage.) No work shall be initiated on the Project prior to Contractor’s receipt of the City’s approval of evidence of insurance coverage related to the construction of the Project.
(c) Contractor shall require and verify that all subcontractors or other parties hired for the Project purchase and maintain coverage for indemnity and insurance at least as broad as specified in the Project Specifications to the extent they apply to the scope of the subcontractor’s work with the same certificate of insurance requirements and naming as additional insureds all parties to this Agreement. Contractor shall include the following language in their agreement with subcontractors: “Subcontractors hired by Contractor agree to be bound to Contractor and City in the same manner and to the same extent as Contractor is bound to City under the Contract Documents and provide a valid certificate of insurance and the required endorsements included in the agreement as proof of compliance prior to commencement of any work and to include this same requirement for any subcontractors they hire for this work. A copy of the insurance and indemnity requirements of the Contract Documents will be furnished to the subcontractor upon request.” Contractor shall have furnished the City with evidence of the insurance coverage meeting the insurance requirements set forth in Project Specifications for each subcontractor prior to initiating any work on the Project, including Builder’s Risk insurance with appropriate coverage for the cost of construction. The periods for submittal, review and approval shall apply as stated in subparagraph (b) above.

(d) The Parties agree that notwithstanding the time requirements set forth in this subsection for submittal and resubmittal to the City by the Contractor of the evidence of insurance and review and approval of the evidence of insurance by the City, Contractor is responsible for ensuring that the evidence of insurance in approvable form is submitted to the City in a timely manner.
(e) Any available insurance proceeds broader than or in excess of the specified minimum insurance coverage requirements and/or limits set forth in the Project Specifications shall be available to the City as an additional insured. Furthermore, the requirements for coverage and limits shall be (1) the minimum coverage and limits specified in the Project Specifications; or (2) the broader coverage and maximum limits of coverage of any insurance policy or proceeds available to the named insured, whichever is greater. No representation is made that the minimum insurance requirements set forth in the Project Specifications are sufficient to cover the obligations of the Contractor under this Agreement. (f) Contractor shall maintain the insurance requirements set forth in the Project Specifications for a minimum of five (5) years following the completion of the Project. In the event Contractor fails to obtain or maintain completed operations coverage as required by the Project Specifications, the City at its sole discretion may purchase the coverage required and the cost for the same shall be paid by Contractor upon demand by the City. 6 2018_Final Form
Section 1.10 Security In Lieu of Retention.
(a) The City shall retain five percent (5%) of the sum requested in each progress payment unless the Contractor elects to invoke the procedures set forth at California Public Contract Code 22300 to substitute securities to ensure performance under the contract.

1. At the request and the expense of the Contractor, securities equivalent to the amount withheld shall be deposited with the City, or with a state or federally chartered bank in the state as escrow agent, who shall then pay the retained funds to the Contractor. Upon satisfactory completion of the contract, the securities shall be returned to the Contractor.

2. Alternatively, the Contractor may request and the City shall make payment of retentions earned directly to the escrow agent at the expense of the Contractor. At the expense of the Contractor, the Contractor may direct the investment of the payments into securities and the Contractor shall receive the interest earned on the investments upon the same terms provided for in Public Contract Code 22300 for securities deposited by the Contractor. Upon satisfactory completion of this Agreement, the Contractor shall receive from the escrow agent all securities, interest, and payments received by the escrow agent from the owner, pursuant to the terms of this section.
(b) If the Contractor chooses to place securities in escrow, the escrow agreement to be used shall be substantially similar to the following form:

ESCROW AGREEMENT FOR SECURITY DEPOSITS IN LIEU OF RETENTION This Escrow Agreement is made and entered into by and between _________________________________________________ whose address is ________________________________ hereinafter called "Owner," ___________ whose address is ________________________________ hereinafter called "Contractor" and ___________ whose address is ________________________________ hereinafter called "Escrow Agent."
For the consideration hereinafter set forth, the Owner, Contractor, and Escrow Agent agree as follows:
(1) Pursuant to Section 22300 of the Public Contract Code of the State of California, Contractor has the option to deposit securities with Escrow Agent as a substitute for retention earnings required to be withheld by Owner pursuant to the Construction Contract entered into between the Owner and Contractor for ____ in the amount of ____ dated ____ (hereinafter referred to as the "Contract"). Alternatively, on written request of the Contractor, the Owner shall make payments of the retention earnings directly to the Escrow Agent. When the Contractor deposits the securities as a substitute for Contract earnings, the Escrow Agent shall notify the Owner within 10 days of the deposit. The market value of the securities at the time of the substitution shall be at least equal to the cash amount then required to be withheld as retention under the terms of the Contract between the Owner and Contractor. Securities shall be held in the name of ____, and shall designate the Contractor as the beneficial owner. 7 2018_Final Form
(2) The Owner shall make progress payments to the Contractor for those funds which otherwise would be withheld from progress payments pursuant to the Contract provisions, provided that the Escrow Agent holds securities in the form and amount specified above. (3) When the Owner makes payment of retentions earned directly to the Escrow Agent, the Escrow Agent shall hold them for the benefit of the Contractor until the time that the escrow created under this contract is terminated. The Contractor may direct the investment of the payments into securities. All terms and conditions of this agreement and the rights and responsibilities of the parties shall be equally applicable and binding when the Owner pays the Escrow Agent directly.
(4) Contractor shall be responsible for paying all fees for the expenses incurred by Escrow Agent in administering the Escrow Account and all expenses of the Owner. These expenses and payment terms shall be determined by the Owner, Contractor, and Escrow Agent. (5) The interest earned on the securities or the money market accounts held in escrow and all interest earned on that interest shall be for the sole account of Contractor and shall be subject to withdrawal by Contractor at any time and from time to time without notice to the Owner. (6) Contractor shall have the right to withdraw all or any part of the principal in the Escrow Account only by written notice to Escrow Agent accompanied by written authorization from the Owner to the Escrow Agent that Owner consents to the withdrawal of the amount sought to be withdrawn by Contractor.
(7) The Owner shall have a right to draw upon the securities in the event of default by the Contractor. Upon seven days' written notice to the Escrow Agent from the Owner of the default, the Escrow Agent shall immediately convert the securities to cash and shall distribute the cash as instructed by the Owner.
(8) Upon receipt of written notification from the Owner certifying that the Contract is final and complete, and that the Contractor has complied with all requirements and procedures applicable to the Contract, Escrow Agent shall release to Contractor all securities and interest on deposit less escrow fees and charges of the Escrow Account. The escrow shall be closed immediately upon disbursement of all moneys and securities on deposit and payments of fees and charges. (9) Escrow Agent shall rely on the written notifications from the Owner and the Contractor pursuant to Sections (5) to (8), inclusive, of this Agreement and the Owner and Contractor shall hold Escrow Agent harmless from Escrow Agent's release and disbursement of the securities and interest as set forth above.
(10) The names of the persons who are authorized to give written notice or to receive written notice on behalf of the Owner and on behalf of Contractor in connection with the foregoing, and exemplars of their respective signatures are as follows:

On behalf of Owner: On behalf of Contractor:
_______________________ _________________________
Title Title
_______________________ _________________________
Name Name
_____________________ _________________________
Signature Signature
_______________________ _________________________
Address Address
On behalf of Escrow Agent:
8 2018_Final Form
_______________________
Title
_______________________
Name
_______________________
Signature
_______________________
Address
At the time the Escrow Account is opened, the Owner and Contractor shall deliver to the Escrow Agent a fully executed counterpart of this Agreement.

IN WITNESS WHEREOF, the parties have executed this Agreement by their proper officers on the date first set forth above.

Owner Contractor
________________________ _________________________
Title Title
________________________ _________________________
Name Name
________________________ _________________________
Signature Signature
Section 1.11 Senate Bill 854 Notice Requirements.

As provided in SB 854 (Stats. 2014, ch. 28): (a) no contractor or subcontractor may be qualified to bid on, be listed in a bid proposal, subject to the requirements of Section 4104 of the California Public Contracts Code, or engage in the performance of any contract for public work, unless currently registered with DIR and qualified to perform public work pursuant to California Labor Code Section 1725.5 (Lab. Code §1771.1(a)); (b) no contractor or subcontractor may be awarded a public works contract unless registered with the DIR to perform public work pursuant to Labor Code Section 1725.5 (Lab. Code §1771.1(b)); and (c) work performed on the project is subject to compliance monitoring and enforcement by DIR (Lab. Code §1771.4).

Section 1.12 Job Site Notices.

Contractor shall post at the job site notices in compliance with Title I California Code of Regulations Section 16451.

Section 1.13 Municipal Code Chapter 2.65 Requirements.

Contractor shall comply with Chapter 2.65 of the Richmond Municipal Code banning the requirement to provide information of prior criminal convictions on employment applications. 9 2018_Final Form

ARTICLE II

DEFAULT AND REMEDIES
Section 2.1 Events of Default.

In addition the remedies set forth in Section 2.2, below, in the event of default the Department Head reserves the right to stop work immediately if any action or inaction by the Contractor or any subcontractor creates a risk of imminent harm to the public or property.

Each of the following shall constitute a “Default” by Contractor under this Agreement:
(a) Breach of Covenants. Failure by Contractor or any subcontractor to duly perform, comply with, or observe any of the conditions, terms, or covenants of any of the Contract Documents. The City shall give Contractor written notice of the breach and specify a time in which to cure the breach. If the Contractor cures the breach within the time specified in the notice or, if the breach cannot be cured in the time specified but the Contractor has diligently pursued measures to cure the breach and to keep the City informed of its progress, then the breach shall not constitute a default provided that the breach is cured within thirty (30) days from the date of the City’s last notice and demand to cure.
(b) Disregard of Laws. Disregard of laws, rules, regulations, directions or instructions of City by Contractor or any subcontractor with respect to the performance of work. (c) Insolvency. A court having jurisdiction shall have made or entered any decree or order (i) adjudging Contractor to be bankrupt or insolvent, (ii) approving as properly filed a petition seeking reorganization of Contractor or seeking any arrangement for Contractor under the bankruptcy law or any other applicable debtor’s relief law or statute of the United States or any state or other jurisdiction, (iii) appointing a receiver, trustee, liquidator, or assignee of Contractor in bankruptcy or insolvency or for any of their properties, (iv) directing the winding up or liquidation of Contractor if any such decree or order described in clauses (i) to (iv), inclusive, shall have continued unstayed or undischarged for a period of ninety (90) days; or (v) Contractor shall have admitted in writing its inability to pay its debts as they fall due or shall have voluntarily submitted to or filed a petition seeking any decree or order of the nature described in clauses (i) to (iv), inclusive.
(d) Suspension; Termination. Contractor shall have voluntarily suspended its business, or shall have voluntarily or involuntarily lost or terminated one or more of the licenses required to perform the work.
(e) Liens on Property and the Development. There shall be filed any claim of lien (other than liens approved in writing by the City) against the Project or the construction site or any part thereof, or any interest or right made appurtenant thereto and the continued maintenance of said claim of lien for a period of twenty (20) days without discharge or satisfaction thereof or provision therefore (including, without limitation, the posting of bonds) satisfactory to the City. 10 2018_Final Form
Section 2.2 Remedies.

The occurrence of any Default hereunder following the expiration of all applicable notice and cure periods will, either at the option of the City or automatically where so specified, relieve the City of any obligation to make or continue payments and shall give the City the right to proceed with any and all remedies set forth in the Contract Documents, including but not limited to the following:
(a) Specific Performance. The City shall have the right to mandamus or other suit, action or proceeding at law or in equity to require Contractor to perform its obligations and covenants under this Agreement or to enjoin acts on things which may be unlawful or in violation of the provisions of this Agreement.
(b) Right of Contest. Contractor shall have the right to contest in good faith any claim, demand, levy, or assessment the assertion of which would constitute a Default hereunder.

Any such contest shall be prosecuted diligently and in a manner unprejudicial to the City or the rights of the City hereunder.
(c) Remedies Cumulative. No right, power, or remedy given to the City by the terms of the Contract Documents is intended to be exclusive of any other right, power, or remedy; and each and every such right, power, or remedy shall be cumulative and in addition to every other right, power, or remedy given to the City by the terms of any such instrument, or by any statute or otherwise against Contractor and any other person. Neither the failure nor any delay on the part of the City to exercise any such rights and remedies shall operate as a waiver thereof, nor shall any single or partial exercise by the City of any such right or remedy preclude any other or further exercise of such right or remedy, or any other right or remedy.

Section 2.3 Waiver of Damages.

Contractor, in having tendered the Proposal, shall be deemed to have waived any and all claims for damages because of termination of this Agreement for any reason. Contractor shall not be entitled to any lost profit in the event of termination.

ARTICLE III

GENERAL PROVISIONS
Section 3.1 Relationship of Parties.

Nothing contained in this Agreement shall be interpreted or understood by any of the Parties, or by any third persons, as creating the relationship of employer and employee, principal and agent, limited or general partnership, or joint venture between the City and Contractor or its agents, employees or subcontractors, and Contractor shall at all times be deemed an independent contractor and shall be wholly responsible for the manner in which it or its agents, or both, perform the services required of it by the terms of this Agreement. Contractor has and retains the right to exercise full control of employment, direction, compensation, and discharge of all persons assisting in the performance of services under the Agreement. In regards to the 11 2018_Final Form
construction of the Project, Contractor shall be solely responsible for all matters relating to payment of its employees, including compliance with Social Security, withholding, and all other laws and regulations governing such matters, and shall include requirements in each contract that subcontractors shall be solely responsible for similar matters relating to their employees.

Contractor shall be solely responsible for its own acts and those of its agents and employees.

Section 3.2 Change Orders.
(a) Changes affecting the time of performance, unit pricing, or total contract price shall be set forth in a written Change Order that shall specify:

1. The work performed in connection with the change to be made;

2. The amount of the adjustment to the Payment Limit, if any, and the basis for compensation for the work ordered; which adjustment may be a negotiated lump sum amount, agreed unit price, or paid under Section 9-1.04 “Force Account” of the 2015 State of California Department of Transportation Standard Specifications; and

3. The amount of time to be adjusted in the schedule for performance, if any. (b) A Change Order will become effective when signed by the Department Head, or his or her representative, notwithstanding that Contractor has not signed it. A Change Order will become effective without Contractor’s signature, provided the Department Head or his or her representative so indicates by noting thereon “unilateral change order.” (c) All changes in any plans and specification approved by any authority with jurisdiction over the Project may also require addenda or change orders approved by that authority.
(d) Where the City requests, a performance bond rider covering the changed work must be executed and delivered to the City before proceeding with the changed work, or shortly in time thereafter.
(e) The Department Head or his or her representative has the authority to approve Change Orders with a cumulative dollar value of up to ten percent (10%) of the contract price.

Section 3.3 Claims By Contractor.
(a) No Third-Party Claims. Nothing contained in this Agreement shall create or justify any claim against the City by any person that Contractor may have employed or with whom Contractor may have contracted relative to the purchase of materials, supplies or equipment, or the furnishing or the performance of any work or services with respect to the construction of the Project, and Contractor shall include similar requirements in any contracts entered into for the construction of the Project. Pursuant to Section 9204 (d)(5) of the Public Contract Code, however, Contractor may present a claim on behalf of a subcontractor for work which was performed by that subcontractor or lower tier subcontractor. Such claim shall have been reviewed and evaluated by Contractor prior to submission to the City. 12 2018_Final Form
(b) Obligation to File Claims for Disputed Work. Should it appear to the Contractor that the work to be performed or any of the matters relative to the Contract Documents are not satisfactorily detailed or explained therein, or should any questions arise as to the meaning or intent of the Contract Documents, or should Contractor have a claim against the City, as the term “claim” is defined in Section 9204 of the Public Contract Code, or should any dispute arise regarding the true value of any work performed, work omitted, extra work that the Contractor may be required to perform, time extensions, payment to the Contractor during performance of the work, construction of the Project, and/or compliance with procedures or standards set forth in the Contract Documents, or should Contractor otherwise seek extra time or compensation FOR ANY REASON WHATSOEVER (each, a “Claim”), then Contractor shall first follow the procedures set forth in this Agreement, including but not limited to Section 3.2, “Change Orders.” If a dispute remains, then Contractor shall give written notice by registered or certified mail with return receipt requested, and such Claim shall be resolved as set forth below. (c) Form and Contents of Claim. The Claim shall be submitted to the City within thirty (30) days of receiving the City’s written decision regarding the dispute, or the date the Contractor contends such decision was due, and in no event later than the date of final payment.

Contractor’s written claim must identify itself as a “Claim” under this Section 3.3 and must include the following: (1) a narrative of pertinent events; (2) citation to contract provisions; (3) theory of entitlement; (4) complete pricing of all cost impacts; (5) a time impact analysis of all time delays that shows actual time impact on the critical path; (6) documentation supporting items 1 – 5; and (7) verification under penalty of perjury of the claim’s accuracy. The Claim shall be priced like a Change Order, and must be updated every thirty (30) days as to cost and entitlement if it remains a continuing Claim. Routine contract materials, for example, correspondence, RFI, Change Order requests, or payment requests shall not constitute a Claim.

Contractor shall bear all costs incurred in preparation, submittal, and administration of a Claim. (d) Administration After Claim Submittal.

1. City may render a final decision based solely on the materials submitted in support of the Claim or may in its sole discretion conduct an administrative hearing on the Claim, in which case Contractor shall appear, participate, answer inquiries, and present any further evidence or analysis requested by City. Should City take no action on the Claim within forty-five (45) days (or any extension thereof mutually agreed upon by City and Contractor, or any such greater time to respond afforded City under Section 9204(d)(1)(C) of the Public Contract Code) of submittal, it shall be deemed denied.

2. If Contractor disputes City’s written response, or if City fails to respond to a Claim within the time prescribed, Contractor may demand in writing an informal conference to meet and confer for settlement of the issues in dispute. Upon receipt of a demand in writing sent by registered mail or certified mail, return receipt requested, City will schedule a meet and confer conference within thirty (30) days for settlement of the dispute.

3. Within ten (10) business days following the conclusion of the meet and confer conference, if the Claim or any portion of the Claim remains in dispute, City will 13 2018_Final Form
provide Contractor a written statement identifying the portion of the Claim that remains in dispute and the portion that is undisputed. Any payment due on an undisputed portion of the Claim will be processed and made within sixty (60) days after City issues its written statement. Any disputed portion of the Claim, as identified by Contractor in writing, shall be submitted to nonbinding mediation, with City and Contractor sharing the associated costs equally. City and Contractor shall mutually agree to a mediator within ten (10) business days after the disputed portion of the Claim has been identified in writing. If City and Contractor cannot agree upon a mediator, each party shall select a mediator and those mediators shall select a qualified neutral third party to mediate with regard to the disputed portion of the Claim. Each party shall bear the fees and costs charged by its respective mediator in connection with the selection of the neutral mediator. If mediation is unsuccessful, the parts of the Claim remaining in dispute shall be subject to Section 3.3(f) of this Agreement.

4. Failure by City to respond to a Claim within the time periods described in Section 9204 of the Public Contract Code or to otherwise comply with the time requirements of that section shall result in the Claim being deemed rejected in its entirety. A Claim that is denied by reason of City’s failure to have responded to a claim, or its failure to otherwise comply with the time requirements of Section 9204 of the Public Contract Code, shall not constitute an adverse finding with regard to the merits of the Claim or the responsibility or qualifications of the claimant filing the Claim.

5. Notwithstanding and pending the resolution of any Claim or dispute, Contractor shall diligently perform the disputed work to final completion in accordance with the City’s direction.
(f) Compliance

1. The provisions of this Section 3.3 constitute a non-judicial claim settlement procedure that, pursuant to California Government Code Section 930.2, shall constitute a condition precedent to the submittal of a valid claim under the California Government Code. Any Government Code claims alleging disputed work must affirmatively indicate prior compliance with this Section 3.3. In accordance with Richmond Municipal Code Section 1.10.010(b), all Government Code claims must be presented no later than the 100th day after the earlier of (i) the date the City actively or passively denied the Claim, or (ii) substantial completion or termination of the contract.

2. Failure to submit and administer Claims as required in Section 3.3 shall waive Contractor’s right to compensation for any disputed work not included in a timely Claim. Disputes not raised in a timely protest and timely Claim submitted under this Section 3.3 may not be asserted in any subsequent Government Code claim, administrative hearing, or civil action. 14 2018_Final Form

3. City shall not be deemed to waive any provision under this Section 3.3 if, at City’s sole discretion, a Claim is administered in a manner not in accord with this Section 3.3. Waivers or modifications of this Section 3.3 may only be made by signed Change Order approved as to form by legal counsel for both City and Contractor. Oral or implied modifications shall be of no force or effect.

Section 3.4 Indemnification.
(a) To the fullest extent permissible by law, Contractor shall indemnify, defend, and hold harmless, and require its subcontractors to defend, indemnify and hold harmless, the City, its elected and appointed officials, and all of its employees, volunteers and agents (the “Indemnified Parties”), from all liability, penalties, costs, losses, damages, expenses, causes of action, claims or judgments, including attorney’s fees and other defense costs (collectively, “Actions”), resulting from injury to or death sustained by any person (including Contractor’s or any subcontractors’ employees), or damage to property of any kind, or any other injury or damage whatsoever, which Actions arise out of or are in any way connected with the construction of the Project, regardless of Contractor’s fault or negligence; provided, however, that Contractor’s, and Contractor’s subcontractors’ indemnity obligations hereunder shall not apply to the extent any Actions are caused by the active negligence or willful act or omission of an Indemnified Party. The indemnification obligations of Contractor and its subcontractors shall extend to Actions asserted after termination of this Agreement for whatever reason for the full period of time allowed by law.
(b) In Actions against any person or entity indemnified under Section 3.4(a) above by an employee of Contractor or its subcontractors, anyone directly or indirectly employed by any one of them or anyone for whose acts one of them may be liable, the indemnification obligation under Section 3.4(a) above shall not be limited by a limitation on amount or type of damages, compensation of benefits payable under workers’ compensation acts, disability benefit acts or other employee benefit acts.
(c) The defense and indemnification obligations set forth in Section 3.4(a) above are undertaken in addition to, and shall not in any way be limited by, the insurance obligations set forth in the Project Specifications.

Section 3.5 Non-Liability of City Officials, Employees and Agents.

No member, official, employee or agent of the City shall be personally liable to Contractor in the event of any default or breach by the City or for any amount which may become due to Contractor or its successor or on any obligation under the terms of this Agreement.

Section 3.6 No Third Party Beneficiaries.

There shall be no third party beneficiaries to this Agreement. 15 2018_Final Form
Section 3.7 Conflict of Interest.
(a) Except for approved eligible administrative or personnel costs, no person described in Section 3.7(b) below who exercises or has exercised any functions or responsibilities with respect to the activities funded pursuant to this Agreement or who is in a position to participate in a decision-making process or gain inside information with regard to such activities, may obtain a personal or financial interest or benefit from the activity, or have an interest in any contract, subcontract or agreement with respect thereto, or the proceeds thereunder, either for themselves or those with whom they have family or business ties, during, or at any time after, such person’s tenure. Contractor shall exercise due diligence to ensure that the prohibition in this Section 3.7(a) is followed.
(b) The conflict of interest provisions of Section 3.7(a) above apply to any person who is an employee, agent, consultant, officer, or elected or appointed official of the City of Richmond, and any immediate family member or dependent of such person.

Section 3.8 Notices, Demands and Communications.

If at any time after the execution of this Agreement it shall become necessary or convenient for one of the Parties hereto to serve any notice, demand or communication upon the other Party, such notice, demand or communication shall be in writing and shall be served personally or by depositing the same in the registered United States mail, return receipt requested, postage prepaid or delivered by express delivery service, return receipt requested and (1) if intended for the City shall be addressed to:

City of Richmond
450 Civic Center Plaza
Richmond, California 94804
Attention: XXXX
With copy to:

City of Richmond
450 Civic Center Plaza
Richmond, CA 94804
Attention: City Attorney

(2) if intended for Contractor shall be addressed to:

XXXX
XXXX
XXXX
Attn: XXXX
16 2018_Final Form
Any notice, demand or communication shall be deemed given, received, made or communicated on the date personal delivery is affected or, if mailed in the manner herein specified, on the delivery date or date delivery is refused by the addressee, as shown on the return receipt. Any Party may change its address at any time by giving written notice of such change at least ten (10) days prior to the date such change is desired to be effective.

Section 3.9 Applicable Law.

This Agreement shall be governed by California law. This Agreement is made in Contra Costa County, California, and any action relating to this Agreement shall be instituted and prosecuted in the courts of Contra Costa County, California.

Section 3.10 Parties Bound.

Except as otherwise limited herein, the provisions of this Agreement shall be binding upon and inure to the benefit of the Parties and their heirs, executors, administrators, legal representatives, successors, and assigns. Any reference in this Agreement to a specifically named Party shall be deemed to apply to any successor, heir, administrator, executor, successor, or assign of such Party who has acquired an interest in compliance with the terms of this Agreement or under law. This Agreement shall be binding upon and inure to the benefit of the heirs, administrators, executors, successors in interest, and assigns of each of the Parties.

Section 3.11 Severability.

If any term of this Agreement is held by a court of competent jurisdiction to be invalid, void or unenforceable, the remainder of the provisions shall continue in full force and effect unless the rights and obligations of the Parties have been materially altered or abridged by such invalidation, voiding or unenforceability.

Section 3.12 Force Majeure.

Performance by either Party shall not be deemed to be in default when delays in performance are due to war, insurrection, strikes, lock-outs, riots, floods, earthquakes, fires, quarantine restrictions, freight embargoes, or court order, or any other similar causes (other than lack of funds of Contractor) beyond the control or without the fault of the Party claiming an extension of time to perform (“Force-Majeure Delays”). In no event shall any extension of any period of time be deemed to have occurred unless the Party claiming the Force-Majeure Delay gives written notice to the other Party within ten (10) days following the commencement of any such delay, setting forth the facts giving rise to the Force-Majeure Delay request, the expected duration of the delay, and the steps the Party intends to take to minimize the Delay. During the Force-Majeure Delay, the Party whose performance is delayed shall keep the other Party reasonably informed of the situation and the steps taken by such Party to continue performance and minimize delay. After the Force-Majeure Delay is over, the Parties shall in good faith jointly prepare an accurate written record of the circumstances giving rise to delay, specifying the commencement date and duration of the Force-Majeure Delay and the cause thereof, which record shall be signed by each Party to confirm agreement with respect to its content. In no event shall the City be required to agree to cumulative Force-Majeure Delays in excess of sixty 17 2018_Final Form
(60) days unless the City is the cause of such delay. In the event that the parties cannot agree upon a record of the circumstances giving rise to the Force-Majeure Delay, the procedures set forth in Section 3.3 of this Agreement shall apply.

Section 3.13 Waivers.

Any waiver by the City of any obligation or condition in this Agreement must be in writing. No waiver will be implied from any delay or failure by the City to take action on any breach or default of Contractor or to pursue any remedy allowed under this Agreement or applicable law. Any extension of time granted to Contractor to perform any obligation under this Agreement shall not operate as a waiver or release from any of its obligations under this Agreement. Consent by the City to any act or omission by Contractor shall not be construed to be consent to any other or subsequent act or omission or to waive the requirement for the City’s written consent to future waivers.

Section 3.14 Title of Parts and Sections.

Any titles of the sections or subsections of this Agreement are inserted for convenience of reference only and shall be disregarded in interpreting any part of the Agreement’s provisions.

Section 3.15 Entire Understanding of the Parties.

The Contract Documents – along with any written change orders and dispute determinations that may be issued by the City in the course of performance – shall constitute the entire understanding and agreement of the Parties with respect to construction of the Project.

The Contract Documents, written change orders (if any), and dispute determinations (if any) are deemed complementary and should be interpreted together.

Section 3.16 Multiple Originals; Counterpart.

This Agreement may be executed in multiple originals, each of which is deemed to be an original, and may be signed in counterparts. A facsimile or electronic signature to this Agreement shall be as valid as an ink signed original.
[Signatures on following page]
18 2018_Final Form
WHEREAS, this Agreement has been entered into by the undersigned as of the date first above written.

Reviewed By:
_______________________
City Attorney
ATTEST:
_______________________________
City Clerk
CITY:

CITY OF RICHMOND, a municipal corporation and
charter city
By: _________________________________
Name: _________________________________
Its: __________________________________
CONTRACTOR:

XXXX
By: _________________________________
Name: _________________________________
Its: _________________________________
19 2018_Final Form
Exhibit A
Proposal

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SPECIAL CONDITIONS AND PROVISIONS 00 51 00 - 1
DOCUMENT 00 51 00

SPECIAL CONDITIONS AND PROVISIONS

1.1 GENERAL INFORMATION
A. The City of Richmond Standard Contract shall include the following Special Conditions and Provisions.

1.2 SUPPLEMENTARY GENERAL CONDITIONS
A. AIA Document A201 - GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION, 2017 Edition, shall supplement and be complimentary to the City of Richmond Standard Contract General Conditions (Exhibit D) and Special Conditions and Provisions (Exhibit E).

B. The City of Richmond Standard Contract General Conditions, Special Conditions and Provisions, and AIA Document A201 shall collectively establish how the project shall be administered.

C. A copy of AIA Document A201 – GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION for this Project is available upon request.

1.3 DOCUMENT HIERARCHY
A. In the event of a written discrepancy or conflict between the City of Richmond Contract General Conditions, these Special Conditions and Provisions, or the Supplementary General Conditions referenced as the AIA Document A201- General Conditions of the Contract for Construction, the following document hierarchy shall be followed:

1. City of Richmond Contract General Conditions (Exhibit D of the Agreement)

2. Special Conditions and Provisions (Exhibit E of the Agreement)

3. Supplementary General Conditions AIA Document A201 – General Conditions of the Contract for Construction
B. In the absence of a written discrepancy or conflict, these above referenced documents shall be collectively considered complimentary and additive to each other in describing how the project shall be administered.

C. No Section or Paragraph of the Supplementary General Conditions AIA Document A201 shall supersede the City of Richmond Standard Contract General Conditions.

1.4 COMMENCEMENT AND PROCEEDING WITH THE WORK

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SPECIAL CONDITIONS AND PROVISIONS 00 51 00 - 2
A. The Contractor shall commence with the Work upon receipt of directions to proceed as stated in the "Notice to Proceed" issued by the Public Works Director.

B. The Contractor shall diligently prosecute the Work on each working day, weather permitting. Work shall continue without delays until completed.

C. Failure to provide an adequate working force shall be considered as grounds for the termination of the contract.

D. The Contractor shall not work on Saturdays, Sundays, City of Richmond holidays, nor between the hours of 6:00 p.m. and 7:00 a.m. without the written permission of the Public Works Director.

1.5 PROJECT COORDINATION SPECIAL REQUIREMENTS
A. The plan set includes bike track improvements to be constructed by American Ramp Company (ARC) after the commencement of this project and is currently anticipated to be built between July 1, 2024 until September 30, 2024. This work is shown in these plans designated as NIC. See pump track plans in Appendix F of Project Manual for more information. The Contractor shall install construction fence, implement and maintain SWPPP, erosion control plan, construction access, procure water and power, complete demolition, clear and grub, install storm utility infrastructure in the bike track area and any other work in the contractor’s scope for ARC to be able to mobilize and start their work. On July 1, 2024. The contractor shall pause all work on site while ARC is performing their work. Once ARC finishes the bike track, Contractor shall install a safety fence around the bike track and continue with the construction of the park scope.

Contractor shall schedule a coordination meeting with ARC and other project team members to develop a schedule and work plan for ARC’s work on site. Contractor’s master schedule will incorporate the anticipated 3 months for bike pump track construction. Contractor is fully responsible for coordinating ARC’s work with it’s own work, and maintain site security, construction fence, construction access, SWPPP and any other required items during the bike track construction.

B. This project includes public art, and coordination with the Artists is required during construction. Contractor is responsible for coordinating installation of art work with it’s own work. Contractor’s schedule shall incorporate art installation tasks. The contractor shall install footings and attachment brackets as shown in the plans in Appendix G and H and notify the Artists when complete for placement of the final pieces.

1.6 PRE-CONSTRUCTION MEETING
A. Within five (5) working days of the issuance of the Notice to Proceed, a preconstruction meeting shall be held in the City of Richmond (typically project location) for the purpose of discussing with the Contractor and the Contractor’s Major Subcontractors the following topics:

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SPECIAL CONDITIONS AND PROVISIONS 00 51 00 - 3

1. Lines of Communication and Personnel Contacts

2. Notice to Proceed and Completion Dates

3. Administrative Procedures

4. Scope of Work

5. Contract Documents

6. Coordination with Owner Work or Owner Furnished Equipment

1.7 CERTIFIED PAYROLL RECORDS
A. The Contractor shall maintain ‘Certified Payroll Records’ for all employees employed in the performance of the Work illustrating compliance with the California Department of Industrial Relations and the California Labor Code.

B. Such payroll records shall be prepared and maintained on a weekly basis and shall be available for review by the City or the City’s Inspector at anytime.

C. Certified Payroll Records shall be submitted monthly with the Contractor’s Application for Payment. Failure to submit payroll records is cause for delay in payment.

1.8 PAYMENTS TO CONTRACTOR
A. Within forty-five (45) days after approval of the Contractor’s Application for Payment, the Contractor shall be paid a sum equal to ninety five percent (95%) of the value of the Work performed (as verified by Architect and Inspector and certified by the Contractor) up to the last day of the previous month, less the aggregate of previous payments and amounts to be withheld.

B. The value of the Work completed shall be Contractor's best estimate. No inaccuracy or error in said estimate shall operate to release the Contractor, or any Surety upon any bond, from damages arising from such Work, or from the City's right to enforce each and every provision of this Contract, and the City shall have the right subsequently to correct any error made in any estimate for payment.

1.9 WARRANTY OF TITLE
A. If a lien or a claim based on a stop notice of any nature should at any time be filed against the Work or any City property, by any entity which has supplied material or services at the request of the Contractor, Contractor and Contractor's Surety shall promptly, on demand by the City and at Contractor's and Surety's own expense, take any and all action necessary to cause any such lien or a claim based on a stop notice to be released or discharged immediately therefrom.

B. If the Contractor fails to furnish to the City within ten (10) calendar days after demand by the City, satisfactory evidence that a lien or a claim based on a stop notice has

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SPECIAL CONDITIONS AND PROVISIONS 00 51 00 - 4
been so released, discharged, or secured, the City may discharge such indebtedness and deduct the amount required therefore, together with any and all losses, costs, damages, and attorney's fees and expense incurred or suffered by City from any sum payable to Contractor under the Contract.

1.10 COMPLETION OF THE WORK
A. Completion

1. The City will accept completion of Contract and have the Notice of Completion recorded when the entire Work shall have been completed to the satisfaction of the City.

2. The Work may only be accepted as complete by action of the governing board of the City.

B. The City, at its sole option, may accept completion of Contract and have the Notice of Completion recorded when the entire Work shall have been completed to the satisfaction of the City, except for minor corrective items, as distinguished from incomplete items. If Contractor fails to complete all minor corrective items within thirty (30) days after the date of the City's acceptance of completion, the City shall withhold from the final payment one hundred fifty percent (150%) of an estimate of the amount sufficient to complete the corrective items, as determined by City, until the item(s) are completed.

1.11 WATER RESOURCES, DUST CONTROL AND NOISE CONTROL
A. Comply with federal, state and local regulations pertaining to water, air, solid waste, recycling, chemical waste, sanitary waste, sediment and noise pollution.

B. Protection of Natural Resources: Preserve the natural resources within the project boundaries or restore to an equivalent condition.

1. Confine construction activities to areas defined by public roads, easements, and work area limits indicated on the drawings.
a. Temporary Construction: Remove indications of temporary construction facilities, such as haul roads, work areas, structures, stockpiles or waste areas.

2. Water Resources: Comply with applicable regulations concerning the direct or indirect discharge of pollutants to underground and natural surface waters. a. Oily Substances: Prevent oily or other hazardous substances from entering the ground, drainage areas, or local bodies of water in such quantities as to affect normal use, aesthetics, or produce a measurable ecological impact on the area.
1) Store and service construction equipment at areas designated for collection of oil wastes.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SPECIAL CONDITIONS AND PROVISIONS 00 51 00 - 5
b. Exercise every reasonable precaution to prevent any debris, chemical or other harmful material in the construction water resulted from his operations from discharging into the storm drain system.

3. Dust Control, Air Pollution, and Odor Control: Prevent creation of dust, air pollution and odors.
a. Use temporary enclosures and other appropriate methods to limit dust and dirt rising and scattering in air to lowest practical level. b. Exercise diligence in preventing dust nuisances. When necessary or when directed by the Public Works Director, the Contractor shall apply water for laying dust. Water shall be applied by means of pressure-type distributors equipped with a spray system that will insure a uniform application. b. Store volatile liquids, including fuels and solvents, in closed containers. c. Properly maintain equipment to reduce gaseous pollutant emissions.

4. Noise Control: Perform construction operations to minimize noise. a. Repetitive, high level impact noise will be permitted only between the hours of 7:00 a.m. and 6:00 p.m.

Repetitive impact noise at or within occupied buildings shall not exceed the following dB limitations:

Sound Level in dB Time Duration of Impact Noise
70 More than 12 minutes in any hour
80 More than 3 minutes in any hour
b. Provide equipment, sound-deadening devices, and take noise abatement measures that are necessary to comply with the requirements of this Contract. c. Comply with applicable City Ordinances and State Regulatory Requirements pertaining to noise and sound level dB limitations while performing construction operations.
d. There is no noise limitation on unoccupied buildings.

1.12 UNDERGROUND UTILITIES AND OBSTRUCTIONS
A. The Contractor shall notify the appropriate regional Underground Service Alert (USA) notification center for operations of subsurface installations at least 2 working days prior to performing any excavation in the proximity of any underground facilities.

B. It is the responsibility of the Contractor to exercise due caution in performing his work so as not to damage both on-site and off-site utilities whether shown on the plans or not. The work specified shall be so conducted as to permit the utility companies to maintain their services without interruption.

C. Utilities and underground pipelines which are to remain in place shall be worked around and protected from damage or interruption of service.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SPECIAL CONDITIONS AND PROVISIONS 00 51 00 - 6
D. Existing facilities are to remain unless otherwise indicated to be removed or except as may be required to be removed, modified and/or restored to permit construction.

1.13 PRESERVATION OF PROPERTY
A. The Contractor shall take care to protect all existing improvements and facilities within and adjacent to the work area. Any damage to the existing improvements and facilities caused by the Contractor’s operations shall be repaired or replaced as directed by the City of Richmond at the Contractor’s expense.

1.14 PUBLIC CONVENIENCE
A. The Contractor shall maintain a neat appearance to the work.

B. In any area visible to the public, the following shall apply:

1. Debris shall be disposed of concurrently with its removal. If stockpiling is necessary, the material shall be removed and disposed of daily. The Contractor shall furnish trash bins for all debris. All debris shall be placed in trash bins concurrently with its removal.

END OF DOCUMENT

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
BONDS AND INSURANCE FORMS 00 60 00 - 1
DOCUMENT 00 60 00

BOND AND INSURANCE FORMS

1.1 GENERAL INFORMATION
A. The Bid Documents and Contract Documents reference Bid Bond requirements, Performance Bond requirements, and Payment Bond requirements.

1. Sample copies of these three bond documents are bound herein for reference.

B. The City of Richmond requires an Insurance Verification Form to be submitted at a time as requested by the City.

1. A sample copy of this form is bound herein for reference.

END OF DOCUMENT
Bond No.

BID BOND
KNOW ALL MEN BY THESE PRESENTS:

That We, , as Principal,
and , as Surety,
are hereby held and firmly bound unto the City of Richmond, in the penal sum of TEN PERCENT (10%) of the total bid submitted by said Principal to the City of Richmond for the work described below, for the payment of which sum in lawful money of the United States, well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.

THE CONDITION OF THE ABOVE OBLIGATION IS SUCH THAT, whereas the Principal has submitted to the City of Richmond a certain bid, attached hereto and hereby made a part hereof, to enter into a contract in writing for the .

NOW, THEREFORE, if said bid submitted by the Principal be accepted and the contract be awarded to the Principal and the Principal shall, within ten (10) days after having received notice that the contract has been awarded to the Principal, enter into the Contract so awarded, shall furnish the required corporate surety bonds and insurance coverage verification and shall in all other respects perform the agreement created by the acceptance of the bid, then this obligation shall be void, otherwise the same shall remain in full force and effect.

The Surety, for value received, hereby stipulates and agrees that the obligations of said Surety and its bond shall be in no way impaired or affected by any extension of the time within which the City of Richmond may accept such Bid; and said Surety does hereby waive notice of such extension.

As a part of the obligation secured hereby and in addition to the face amount specified therefore, there shall be included costs and reasonable expenses and fees, including reasonable attorney's fees, incurred by the City of Richmond in successfully enforcing such obligation, all to be taxed as costs and included in any judgment rendered.

IN WITNESS WHEREOF, the Principal and the Surety have hereunto set their hands and seals on this day of , 20 .

By:

Title
By:

Title:

Bid Bond (11/4/03)
§ 66499.1. Faithful performance bond; form, CA GOVT § 66499.1

PERFORMANCE BOND
Whereas, The City Council of the City of Richmond, State of California, and __________ (hereinafter designated as “principal”) have entered into an agreement whereby principal agrees to install and complete certain designated public improvements, which said agreement, dated __________, 201_, and identified as project __________, is hereby referred to and made a part hereof; and

Whereas, Said principal is required under the terms of said agreement to furnish a bond for the faithful performance of said agreement.

Now, therefore, we, the principal and __________, as surety, are held and firmly bound unto the City of Richmond (hereinafter called “City”), in the penal sum of __________ dollars ($__________) lawful money of the United States, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, successors, executors and administrators, jointly and severally, firmly by these presents.

The condition of this obligation is such that if the above bounded principal, his or its heirs, executors, administrators, successors or assigns, shall in all things stand to and abide by, and well and truly keep and perform the covenants, conditions and provisions in the said agreement and any alteration thereof made as therein provided, on his or their part, to be kept and performed at the time and in the manner therein specified, and in all respects according to their true intent and meaning, and shall indemnify and save harmless City, its officers, agents and employees, as therein stipulated, then this obligation shall become null and void; otherwise it shall be and remain in full force and effect.

As a part of the obligation secured hereby and in addition to the face amount specified therefor, there shall be included costs and reasonable expenses and fees, including reasonable attorney’s fees, incurred by City in successfully enforcing such obligation, all to be taxed as costs and included in any judgment rendered.

The surety hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the agreement or to the work to be performed thereunder or the specifications accompanying the same shall in anywise affect its obligations on this bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the agreement or to the work or to the specifications.

In witness whereof, this instrument has been duly executed by the principal and surety above named, on __________, 201__.

By: _________________________
Title: _________________________

By: _________________________
Title: _________________________
§ 66499.2. Bond for security of laborers and material suppliers; form, CA GOVT § 66499.2 1 PAYMENT BOND
Whereas, The City Council of the City of Richmond, State of California, and __________ (hereinafter designated as “the principal”) have entered into an agreement whereby the principal agrees to install and complete certain designated public improvements, which agreement, dated __________, 201__, and identified as project __________, is hereby referred to and made a part hereof; and

Whereas, Under the terms of the agreement, the principal is required before entering upon the performance of the work, to file a good and sufficient payment bond with the City of Richmond to secure the claims to which reference is made in Title 3 (commencing with Section 9000) of Part 6 of Division 4 of the Civil Code.

Now, therefore, the principal and ____________, as corporate surety, are held firmly bound unto the City of Richmond (hereinafter called “City”) and all contractors, subcontractors, laborers, material suppliers, and other persons employed in the performance of the agreement and referred to in Title 3 (commencing with Section 9000) of Part 6 of Division 4 of the Civil Code in the sum of __________ dollars ($ __________), for materials furnished or labor thereon of any kind, or for amounts due under the Unemployment Insurance Act with respect to this work or labor, that the surety will pay the same in an amount not exceeding the amount hereinabove set forth, and also in case suit is brought upon this bond, will pay, in addition to the face amount thereof, costs and reasonable expenses and fees, including reasonable attorney’s fees, incurred by City in successfully enforcing this obligation, to be awarded and fixed by the court, and to be taxed as costs and to be included in the judgment therein rendered.

It is hereby expressly stipulated and agreed that this bond shall inure to the benefit of any and all persons, companies, and corporations entitled to file claims under Title 3 (commencing with Section 9000) of Part 6 of Division 4 of the Civil Code, so as to give a right of action to them or their assigns in any suit brought upon this bond.

Should the condition of this bond be fully performed, then this obligation shall become null and void, otherwise it shall be and remain in full force and effect.

The surety hereby stipulates and agrees that no change, extension of time, alteration, or addition to the terms of the agreement or the specifications accompanying the same shall in any manner affect its obligations on this bond, and it does hereby waive notice of any such change, extension, alteration, or addition.

In witness whereof, this instrument has been duly executed by the principal and surety above named, on __________, 201__.

By: _________________________
Title: _________________________

By: _________________________
Title: _________________________
City of Richmond
Department of Public Works

WARRANTY BOND
City of Richmond (“City”) and ____________________________ (“Contractor”) have entered into a contract, dated _________________, 20___ (“Contract”) for work on the Flood Risk Reduction in the Rheem Creek Watershed Project (“Project”). The Contract is incorporated by reference into this Warranty Bond (“Bond”).

1. General. Under this Bond, Contractor as principal and _______________ __________, its surety (“Surety”), are bound to City as obligee in the maximum amount of 15% of the final Contract Price, unless otherwise specified in the Contract Documents.

2. Warranty Period. The Contract requires Contractor to guarantee its work and that of its Subcontractors on the Project, against defects in materials or workmanship which are discovered during the one-year period commencing with City’s acceptance of the Project (“Warranty Period”).

3. Surety’s Obligations. If Contractor faithfully carries out and performs its guarantee under the Contract, and, on due notice from City, repairs and remedies, at its sole expense, any and all defects in materials and workmanship in the Project which are discovered during the Warranty Period, or if Contractor promptly reimburses City for all loss and damage that City sustains because of Contractor’s failure to makes such repairs in accordance with the Contract requirements, then Surety’s obligations under this Bond will be null and void.

Otherwise, Surety’s obligations will remain in full force and effect.

4. Waiver. Surety waives the provisions of Civil Code §§ 2819 and 2845.

5. Notice. Any notice to Surety may be given in the manner specified in the Contract and delivered or transmitted to Surety as follows:

Attn: _________________________________________________ Address: ______________________________________________ City/State/Zip: _________________________________________ Phone: _______________________________________________
Fax: _________________________________________________
Email: ________________________________________________

6. Law and Venue. This Bond will be governed by California law, and venue for any dispute pursuant to this Bond will be in the Contra Costa County Superior Court, and no other place. Surety will be responsible for City’s attorneys’ fees and costs in any action to enforce the provisions of this Bond.

7. Effective Date; Execution. This Bond is entered into and is effective on __________, 20_________.
[Signatures are on the following page.]
SURETY:
___________________________________
Business Name
s/__________________________________ Date ______________________________ ___________________________________
Name, Title
(Attach Acknowledgment with Notary Seal and Power of Attorney) CONTRACTOR:
___________________________________
Business Name
s/__________________________________ Date ______________________________ ___________________________________
Name, Title
APPROVED BY CITY:
s/ __________________________________ Date ______________________________ ____________________________________
Name, Title

END OF WARRANTY BOND
___ Exhibit F
___ Section 8
City of Richmond - Insurance Requirements – Type 1:

Consultants and Contractors
Type 1 – Page 1 of 4
Revised: September 2011
In all instances where a CONTRACTOR or its representatives will be conducting business and/or providing services, the City requires the following MINIMUM insurance requirements and limits.

CONTRACTOR shall procure and maintain for the duration of the contract, agreement, or other order for work, services or supplies, insurance against claims for injuries to persons or damages to property which may arise from or in connection with the performance of the work hereunder and the results of that work by the CONTRACTOR, its agents, representatives, employees or subcontractors. Maintenance of proper insurance coverage is a material element of the contract. Failure to maintain or renew coverage or to provide evidence of renewal may be treated by the City as a material breach of contract.

CONTRACTOR agrees that in the event of loss due to any of the perils for which it has agreed to provide Commercial General Liability insurance, CONTRACTOR shall look solely to its insurance for recovery. CONTRACTOR hereby grants to CITY, on behalf of any insurer providing Commercial General Liability insurance to either CONTRACTOR or CITY with respect to the services of CONSULTANT herein, a waiver of any right to subrogation which any such insurer of said CONTRACTOR may acquire against the CITY by virtue of the payment of any loss under such insurance.

Original, signed certificates and original, separate policy endorsements, naming the City as an additional insured for general liability, as well as a waiver of subrogation for Workers’ Compensation insurance, shall be received and approved by the City before any work may begin. However, failure to do so shall not operate as a waiver of these insurance requirements.

City reserves the right to modify or require additional coverages for specific risk exposures depending on scope of CONTRACTORS work.

Minimum coverage is detailed below. The policy limits of coverage shall be made available to the full limits of the policy.

The minimum limits stated herein shall not serve to reduce the policy limits of coverage of CONTRACTOR.

Minimum Scope of Insurance – the following forms shall be provided and coverage shall be at least as broad as the following:

1. Insurance Services Office Commercial General Liability coverage (ISO Occurrence Form CG 0001) including coverage for bodily and personal injury, property damage, and products and completed operations.

2. Insurance Services Office Automobile Liability coverage (ISO Form CA 0001, Code 1, Any Auto)

3. Original and Separate Additional Insured Endorsements for General Liability (ISO Form CG 20 10 11/85 or its equivalent) with primary and non-contributory language.

4. Workers’ Compensation Insurance as required by the State of California including Employer’s Liability coverage.

5. Original and Separate Waiver of Subrogation for Workers’ Compensation and Builder’s Risk/ Course of Construction Insurance.

6. Builder’s Risk/Course of Construction insurance covering all risks of loss less policy exclusions when the City of Richmond has a financial interest in the property. – (Only required for Construction Contracts involving property)

7. Contractor’s Pollution Liability (if applicable for Construction Contractors) Required Coverage Minimum Limits
Workers’ Compensation and
Employers’ Liability
Statutory limits as required by the State of California including $1 million Employers’ Liability per accident, per employee for bodily injury or disease.

If CONTRACTOR is self-insured, provide a certificate of Permission to SelfInsure, signed by the California Department of Industrial Relations and SelfInsurance. If contractor is a sole proprietor (has no employees) than contractor must sign “Contractor Release of Liability” found at:
http://www.ci.richmond.ca.us/index.aspx?nid=61.
___ Exhibit F
___ Section 8
City of Richmond - Insurance Requirements – Type 1:

Consultants and Contractors
Type 1 – Page 2 of 4
Revised: September 2011

PROJECT COST REQUIRED LIMIT
$0 - $5 million $2 million p/o
$5 million - $10 million $5 million p/o
Over $10 million $10 million p/o
Fireworks $5 million p/o
General Liability
(primary and excess limits
combined)

Includes coverage for bodily injury, personal injury, property damage and products and completed operations. The policy shall not exclude coverage for XCU perils (explosion, collapse, or damage to underground property).

If the policy includes a general aggregate, either the general aggregate shall apply separately to this project, service or location or the minimum required aggregate limit shall be twice the per occurrence limit ($4 million aggregate limit).

Policy shall be endorsed to name the City of Richmond as an additional insured per the conditions detailed below.

Automobile Liability $1,000,000 per occurrence for bodily injury and property damage.

Builders’ Risk/Course of
Construction – Covers property
under construction, repair or
renovation as well as equipment
and materials to be installed.
(Only required for Construction
Projects involving property and
equipment installation.)
Coverage shall include all risks of direct physical loss, excluding earthquake, for an amount equal to the full completed value of the covered structure or replacement value of alterations or additions, including soft costs and business interruption.

If the project does not involve new or major reconstruction, an Installation Floater may be acceptable. For such projects, a property installation floater shall be obtained that provides for the improvement, remodel, modification, alteration, conversion or adjustment to existing buildings, structures, processes, machinery and equipment. The Property Installation Floater shall provide property damage coverage for any building, structure, machinery or equipment damaged, impaired, broken or destroyed during the performance of the Work, including during transit, installation and testing at the City of Richmond’s site.

The City of Richmond shall be named as loss payee as its interest may appear. The insurer shall waive all rights of subrogation against City.

Contractor’s Pollution Liability (if
applicable)
Protects against:
unexpected/unintended release of
pollution resulting from contractors
covered operations such as:

HVAC, paving, carpentry, pipeline
& tank installation, drillers,
remediation contractors,
maintenance, mechanical,
demolition, excavation, grading,
street/road construction,
residential & commercial builders.

Same limits as General Liability.

Required Policy Conditions
A. M. Best Rating A:VII or Better. If the A.M. Best Rating falls below the required rating, CONTRACTOR must replace coverage immediately and provide notice to City.

Additional Insured Endorsement Applicable to General Liability Coverage.

The City of Richmond, its officers, officials, employees, agents and volunteers are to be named as additional insureds for all liability arising out of the operations by or on behalf of the named insured, including but not limited to bodily injury, deaths and property damage or destruction arising in any respect directly or indirectly in the performance of this contract.

ISO form CG 20 10 (11/85) or its equivalent is required. The endorsement must not exclude products and completed operations coverage. If it does, then CG 20 37 (10/01) is also required. ___ Exhibit F
___ Section 8
City of Richmond - Insurance Requirements – Type 1:

Consultants and Contractors
Type 1 – Page 3 of 4
Revised: September 2011
Additional Insured Endorsement
(continued)
SAMPLE Endorsements can be found at
http://www.ci.richmond.ca.us/index.aspx?nid=61
Primary and Noncontributory The contractor’s insurance coverage must be primary coverage as it pertains to the City, its officers, officials, employees, agents and volunteers. Any insurance or self insurance maintained by the City is wholly separate from the insurance of the contractor and in no way relieves the contractor from its responsibility to provide insurance.

Waiver of Subrogation
Endorsement Form
Contractor’s insurer will provide a Waiver of Subrogation in favor of the City for Workers Compensation and Builder’s Risk/ Course of Construction coverage during the life of this contract.

SAMPLE Endorsements can be found at
http://www.ci.richmond.ca.us/index.aspx?nid=61
Deductibles and Self-Insured
Retentions
Any deductible or self-insured retention must be declared to and approved by the City. At the option of the City either the insurer shall reduce or eliminate such deductibles or self-insured retention as respects the City or the CONTRACTOR shall procure a financial guarantee in an amount equal to the deductible or self-insured retention guaranteeing payment of losses and related investigations, claims administration and defense expenses.

Contractor is responsible for satisfaction of the deductible and/or self-insured retention for each loss.

Loss Payable Endorsement (only
required when Builder’s Risk
and/or Course of Construction
Insurance is required.)
Applicable to Builder’s Risk/Course of Construction naming the City of Richmond as Loss Payee.

SURETY BONDS
(If a Public Works/Engineering
Project)
The Contractor shall provide:

1. A Bid bond

2. A Performance Bond

3. A Payment Bond
Umbrella/Excess Liability Policies
If an Umbrella or Excess Liability Policy is used to meet the liability limits, coverage shall be as broad as specified for underlying coverages and cover those insured in the underlying policies.

Claims-Made Policies
If any insurance policy is written on a claims-made form: 1) the retroactive date must be shown, and must be before the date of the contract or the beginning of contract work. 2) Insurance must be maintained and evidence of insurance must be provided for at least five (5) years after completion of the contract of work. 3) If coverage is canceled or nonrenewed, and not replaced with another claims-made policy form with a retroactive date prior to the contract effective date, the Contractor must purchase an extended period coverage for a minimum of five (5) years after completion of contract work.

Subcontractors
CONTRACTOR shall include all subcontractors as insured under its policies or shall furnish to the City for review and approval, separate certificates and endorsements for each subcontractor. All coverage for subcontractors shall be subject to all of the requirements stated herein.

CONTRACTOR agrees to defend and indemnify the City of Richmond for any damage resulting to it from failure of either CONTRACTOR or any subcontractor to take out or maintain the required insurance policies. The fact that insurance is obtained by CONTRACTOR, and/or CONTRACTOR’s subcontractors, will not be deemed to release or diminish the liability of CONTRACTOR, including, without limitation, liability under the indemnity provisions of this contract. Damages recoverable by CITY from CONTRACTOR or any third party will not be limited by the amount of the required insurance coverage.
___ Exhibit F
___ Section 8
City of Richmond - Insurance Requirements – Type 1:

Consultants and Contractors
Type 1 – Page 4 of 4
Revised: September 2011
Verification of Coverage
All original certificates and endorsements shall be received and approved by the City before work may begin. The City of Richmond reserves the right to require complete, certified copies of all required insurance policies including endorsements affecting the coverage at any time.

Original insurance certificates and required policy endorsements shall be mailed, or delivered to the Designated Project Manager for the City of Richmond.

Insurance certificates and endorsements may be faxed to the Designated Project Manager. However, Contractor must mail the original certificates and endorsements to Designated Project Manager once faxed.

Continuous Coverage
CONTRACTOR shall maintain the required insurance for the life of the contract. Should the CONTRACTOR cease to have insurance as required during this time, all work by the CONTRACTOR pursuant to this agreement shall cease until insurance acceptable to the City is provided. In the event that CONTRACTOR fails to comply with the City’s insurance requirements, the City may take such action as it deems necessary to protect the City’s interests. Such action may include but is not limited to termination of the contract, withholding of payments, or other actions as the City deems appropriate.

If services or the scope of work extend beyond the expiration dates of the required insurance policies initially approved by the City, CONTRACTOR must provide updated certificates and endorsements indicating that the required coverage, terms and conditions are still in place. Renewal certificates and updated endorsements shall be mailed to the Designated Project Manager.

Cancellation
CONTRACTOR shall ensure that coverage shall not be cancelled, reduced or otherwise materially changed except after thirty (30) days’ prior written notice has been given to the City.

Reporting Requirements
Any failure to comply with reporting or other provisions of the policies including breaches of warranties shall not affect coverage provided to the City, its officers, officials, employees or volunteers.

Consistent with Public Policy
The insuring provisions, insofar as they may be judged to be against public policy shall be void and unenforceable only to the minimum extent necessary so that the remaining terms and provisions herein may be consistent with public policy and thus enforceable.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
FIRST SOURCE AGREEMENT 00 70 00 - 1
DOCUMENT 00 70 00

CITY OF RICHMOND

FIRST SOURCE AGREEMENT

1.1 GENERAL INFORMATION
A. The City of Richmond First Source Agreement shall be executed between the Prime Contractor and the City of Richmond at a time during the Contract Award as directed by the City of Richmond.

B. A sample copy of this agreement along with any pertinent exhibits is bound herein for reference.

END OF DOCUMENT
11 CITY OF RICHMOND

FIRST SOURCE AGREEMENT

RECITALS
THIS FIRST SOURCE AGREEMENT is entered into on the date stated below by and between the CITY OF RICHMOND, a municipal corporation and charter city (hereinafter the “City”), and (hereinafter the “Employer”).

WHEREAS, the Employer has been awarded a contract, forgivable loan or subsidy by the City and/or the Richmond Community Redevelopment Agency, dated ,20 (hereinafter the “Contract”) to perform certain work and provide certain services at in Richmond, California, described as follows:

WHEREAS, the Employer, in addition to the Contract, agrees to enter into this First Source Agreement (hereinafter the “FSA”) with the City; NOW, THEREFORE, the parties hereto mutually agree as follows:

1. Compliance with Chapter 2.56. Employer will comply with the terms of Chapter 2.56 of the Richmond Municipal Code, Local Employment Program (hereinafter the “Ordinance”), a copy of which is attached hereto and incorporated herein by reference.

2. Liaison. Employer shall designate a liaison for issues related to the Ordinance and this FSA. The liaison shall work with designated City of Richmond staff to facilitate effective implementation of the Ordinance and this FSA (hereinafter the “Designated City Staff”).

3. First Source Hiring Process for CONSTRUCTION and NON-CONSTRUCTION JOBS -Employer shall take the following steps regarding hiring in furtherance of the Contract. (a) Long-Range Planning. Employer shall, prior to hiring in furtherance of the Contract, and as soon as practicable, provide to the Designated City Staff the approximate number and type of hires that it will make for employment, and the basic qualifications necessary for each projected hire.
(b) Dual Notification Process (CONSTRUCTION ONLY). Where there is a signatory agreement with the local union and the associated craft, Employer shall work with the local union and the City of Richmond Employment and Training Department (hereinafter the “ETD”) to fill those positions. The Employer shall forward to the ETD a copy of all personnel requests made to the trade unions, specifying the residency of personnel requested (this process is 12 hereinafter referred to as the "dual notification process" and a description of it is attached hereto along with the Request for Craft form for use by the Employer). In the dual notification process, the Employer shall utilize the "name call," "rehires," "transfers," or "sponsorship" options in maximizing the participation of Richmond, California residents. (c) Notification of job opportunities. Prior to hiring in furtherance of the Contract, Employer shall notify the Designated City Staff, by email or fax, of available job openings and provide a description of job responsibilities and qualifications, including expectations, salary, work schedule, duration of employment, required standard of appearance, and any special requirements, e.g., language skills, driver’s license, etc. Job qualifications shall be limited to skills directly related to performance of job duties.
(d) Filling of job opportunities. Prior to announcing or advertising in any form and by any means (except for compliance with internal posting procedures) the availability of an employment position created by the vacancy of an existing position or a new employment position, the Employer shall utilize the dual notification process to notify the pertinent union, if appropriate, and ETD in writing of such position, including a general description of the position and Employer's minimum requirements for qualified applicants, and shall request any pertinent union and ETD to refer qualified applicants for such position to Employer's trade union and/or personnel representative, as appropriate. The Employer shall refrain from any general announcement or advertisement of the availability of such position for a period of ten (10) business days after notification to the ETD. This ten-day period shall be known as the "Advance Notice Period.”
(e) Job Site Applications. In the event that any persons seek employment with the Employer at the job site, the Employer shall have the person complete a Job Site Application consisting of name, address, telephone number, social security number and trade. The Employer will then submit this information to the ETD.
(f) Transfer and Promotion. Nothing contained herein shall prevent the Employer from filling job vacancies or newly created positions without compliance with the foregoing procedures by transfer or promotion from its existing staff.

4. Monthly Reports. Employer shall, on a monthly basis, furnish certified payroll sheets to ETD. Failure to provide the City with this information shall result in delay of progress payments for that portion which is deemed not in compliance with the provisions of this FSA.

5. Quarterly Reports. Employer shall prepare quarterly reports detailing the number of hires for employment in furtherance of the Contract during the quarter and stating what percentage of such hires were residents of Richmond, California. The Designated City Staff shall assist Employer by preparing forms to be completed for this purpose. Reports shall be filed with the ETD within thirty (30) days after the completion of each quarter. Reports may include a description of any difficulties the Employer is having with obtaining qualified referrals through the Designated City Staff.
13 6. Non-compliance Procedure. In the event the City believes the Employer may not be in compliance with the requirements of this FSA, the following procedure will be followed:
(a) The Community and Economic Development Executive Director (hereinafter the “Executive Director”) or designee shall cause to be delivered to the Employer a written “Notice of Non-Compliance” (hereinafter the “Notice”). The Notice shall specify the matters which constitute the non-compliance; the specific action required to correct the non-compliance; and the time period during which such correction shall occur. In no event shall this time period be more than thirty (30) days after receipt of the Notice by the Employer. If the Notice is mailed, it will be deemed received five (5) days after the date of mailing. (b) If the Employer disagrees with the Notice, they shall have the burden of proving compliance with the provisions of the Ordinance and shall submit any evidence and argument to the Executive Director or designee to establish compliance no more than thirty (30) days after receipt of the Notice by the Employer.
(c) In the event the Executive Director or designee subsequently agrees that compliance has occurred, the Executive Director or designee shall cause to be delivered promptly to the Employer a written “Notice of Correction of Non-Compliance,” specifying the original noncompliance which has been corrected. (d) In the event the Executive Director or designee does not agree that compliance has occurred, the Executive Director or designee shall promptly notify the Employer by a written “Notice of Failure to Correct Non-Compliance” (“hereinafter the “Notice of Failure to Correct”), describing the facts constituting the non-compliance.
(e) After the issuance of the Notice of Failure to Correct, the Employer shall have the right to request a hearing before the City Manager or designee (hereinafter “Request for Hearing”), who shall make the final determination. The Request for a Hearing must be made within ten (10) working days after receipt of the Notice of Failure to Correct. If the Notice of Failure to Correct is mailed, it will be deemed received five (5) days after the date of mailing. The hearing shall be held no sooner than twenty (20) and no later than thirty (30) days after receipt by the City of the Request for Hearing, unless otherwise agreed to by the parties. At the hearing, the Employer will be allowed to present any evidence and argument it believes proves compliance. The City Manager or designee shall issue their final determination no later than ten (10) business days after the hearing. The Employer must exhaust this administrative remedy prior to commencing legal action.
(f) In the event no Request for Hearing is timely made, the determination of failure to correct non-compliance shall be deemed to be final.
(g) Should the Employer fail to comply with the Notice of Non-Compliance as specified above, and a final determination of non-compliance is made, the City may exercise any of its powers as specified in §2.56.080 of the Ordinance.

Executed this day of , 20
14 EMPLOYER
By: ________________________
Name: ______________________
Its:

CITY OF RICHMOND
By: ___________________________
Name: _________________________
Title: __________________________
Approved as to form:
_______________________________
City Attorney

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
COMMUNITY WORKFORCE AGREEMENT 00 80 00 - 1
DOCUMENT 00 80 00

CITY OF RICHMOND

COMMUNITY WORKFORCE & PROJECT STABILIZATION AGREEMENT

1.1 GENERAL INFORMATION
A. The Community Workforce & Project Stabilization Agreement for the City of Richmond shall be adhered to and complied with by the Prime Contractor as directed by the City of Richmond.

B. A sample copy of the agreement requirements along with any pertinent exhibits is bound herein for reference.

END OF DOCUMENT

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SUMMARY OF WORK 01 11 00 - 1
SECTION 01 11 00

SUMMARY OF WORK

1. GENERAL

1.1. RELATED DOCUMENTS AND PROVISIONS
Contractor shall review all Contract Documents for applicable provisions related to the provisions in this document, including without limitation:

1.1.1. General Conditions;

1.1.2. Supplementary Conditions (if any);

1.1.3. Submittals; and

1.1.4. Temporary Facilities and Controls.

1.2. SUMMARY OF WORK COVERED BY CONTRACT DOCUMENTS
The Work may consist of the following:

Project consists the improvements to the Shields-Reid Park, as described in the Contract Documents. The project site is located at: 1410 Kelsey St. Richmond, CA 94801 The scope of work includes, but not limited to,: demolition, earthwork, grading & paving, landscaping & irrigation, bio retention, stage structure, restroom, fencing, utilities, electrical and lighting, site furnishings, play structures etc. Refer to Plan Sheet No. G001 – Title Sheet for additional Scope of Work description.

Contractor to schedule and coordinate bike track pump construction with American Ramp Company (ARC) per bid plans and specifications including but not limited to preparing the site for ARC work, providing assistance as needed, maintaining site security and other site control and maintenance measures as needed.

Add Alternate bid items as per Plan Sheet N0. LC101 – Landscape Construction and Materials Plan includes:

1. Nature Play Area and Site Furnishing

2. Perimeter Fencing

3. Basketball Court Painting

4. Basketball Court Resurfacing and Painting

1.3. CONTRACTS
Perform the Work under a single, fixed-price Contract.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SUMMARY OF WORK 01 11 00 - 2

1.4. DEFERRED PERMIT APPROVAL ITEMS

1.4.1. All items that are subject to subsequent review and approval by the Local Jurisdiction Having Authority are as indicated below. Contractor is responsible for design, permit submittal and approval, procurement and installation of all deferred permit approval items. No deferred permit approval items shall be installed until the Contractor has complied with all the processes in the Contract Documents, including Division 01 Document “Submittals.”

1.4.1.1. Stormwater Pollution Prevention Plan

1.4.1.2. Encroachment Permit

1.4.1.3. Stage and Footings

1.4.1.4. Play Equipemnt and Footings

1.4.1.5. Pre-fabricated Restroom building shop drawings including foundations

1.5. SPECIAL PROJECT REQUIREMENTS

1.5.1. Hours of Work: Work is to be performed between 8am to 5pm. Contractor shall coordinate its operations with activities taking place at the Site. Contractor shall ensure that there are no disruptions to such activities.

1.6. WORK BY OTHERS

1.6.1. Work to be performed and completed by others: Bike Pump Track excluding demolition, clearing and grubbing, storm drain, electrical lighting, planting and mulching in the bike pump track area

1.6.2. Public Art pieces excluding foundations

1.7. CODES, REGULATIONS AND STANDARDS

1.7.1. The codes, regulations, and standards adopted by the Local Jurisdiction Having Authority, State and federal agencies having jurisdiction shall govern minimum requirements for the Project. Where codes, regulations, and standards conflict with the Contract Documents, these conflicts shall be brought to the immediate attention of the City and the Landscape Architect.

1.7.2. Codes, regulations, and standards are as published effective as of date of bid opening, unless otherwise specified or indicated.

1.8. EXAMINATION OF EXISTING CONDITIONS

1.8.1. Contractor shall be held to have examined the Project Site and acquainted itself with the conditions of the Site and of the streets and roads approaching the Site.

1.8.2. Prior to commencement of Work, Contractor shall survey the Site and existing buildings and improvements to observe existing damage and defects such as cracks, sags, broken, missing or damaged glazing, other building elements and Site improvements, and other damage. Contractor shall provide a video, with narrative, and pictures to the City prior to commencement of Work.

1.8.3. Should Contractor observe cracks, sags, and other damage to and defects of the Site and adjacent buildings, paving, and other items not indicated in the Contract Documents,

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SUMMARY OF WORK 01 11 00 - 3
Contractor shall immediately report same to the City and the Landscape Architect.

Contractor shall provide said observances in writing to the City.

1.9. CONTRACTOR'S USE OF PREMISES

1.9.1. Contractor shall take all reasonable precautions for the safety of employees throughout the duration of the Project.

1.9.2. If unoccupied and only with City’s prior written approval, Contractor may use the building(s) at the Project Site without limitation for its operations, storage, and office facilities for the performance of the Work. If the City chooses to beneficially occupy any building(s), Contractor must obtain the City's written approval for Contractor's use of spaces and types of operations to be performed within the building(s) while so occupied. Contractor's access to the building(s) shall be limited to the areas indicated.

1.9.3. If the space at the Project Site is not sufficient for Contractor's operations, storage, office facilities and/or parking, Contractor shall arrange and pay for any additional facilities needed by Contractor, at no expense to City.

1.9.4. Contractor shall not interfere with others use of or access to occupied portions of the building(s) or adjacent property.

1.9.5. Contractor shall maintain corridors, stairs, halls, and other exit-ways of building clear and free of debris and obstructions at all times.

1.9.6. No one other than those directly involved in the demolition and construction or specifically designated by the City or the Architect shall be permitted in the areas of Work during demolition and construction activities.

1.10. PROTECTION OF EXISTING STRUCTURES AND UTILITIES

1.10.1. The Drawings show above-grade and below-grade structures, utility lines, and other installations that are known or believed to exist in the area of the Work. Contractor shall locate these existing installations before proceeding with excavation and other operations that could damage same; maintain them in service, where appropriate; and repair damage to them caused by the performance of the Work. Should damage occur to these existing installations, the costs of repair shall be at the Contractor's expense and made to the City's satisfaction.

1.10.2. Contractor shall be alert to the possibility of the existence of additional structures and utilities. If Contractor encounters additional structures and utilities, Contractor will immediately report to the City for disposition of same as indicated in the General Conditions.

1.11. UTILITY SHUTDOWNS AND INTERRUPTIONS

1.11.1. Contractor shall give the City a minimum of three (3) days written notice in advance of any need to shut off existing utility services or to effect equipment interruptions. City will set exact time and duration for shutdown, and will assist Contractor with shutdown.

Work required to re-establish utility services shall be performed by the Contractor.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SUMMARY OF WORK 01 11 00 - 4

1.11.2. Contractor shall obtain City's written approval as indicated in the General Conditions in advance of deliveries of material or equipment or other activities that may conflict with City's use of the building(s) or adjacent facilities.

1.12. STRUCTURAL INTEGRITY

1.12.1. Contractor shall be responsible for and supervise each operation and work that could affect structural integrity of various building elements, both permanent and temporary.

1.12.2. Contractor shall include structural connections and fastenings as indicated or required for complete performance of the Work.

END OF SECTION

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
PROJECT MANAGEMENT SOFTWARE 01 12 10 - 1
SECTION 01 12 10

PROJECT MANAGEMENT SOFTWARE

1. GENERAL

1.1. RELATED DOCUMENTS AND PROVISIONS
Contractor shall review all Contract Documents for applicable provisions related to the provisions in this document, including without limitation:

1.1.1. General Conditions;

1.1.2. Supplementary Conditions (if any);

1.1.3. Submittals; and

1.1.4. Construction Schedule.

2. PROJECT MANAGEMENT SOFTWARE

2.1. Contractor shall provide and utilize a web based Project Management software program on this Project for processing of RFIs, Submittals, project document storage including but not limited to drawings, specifications, ASIs, change orders, schedules, photos, site dailies and other project reports, meeting minutes etc. Contractor shall provide training to project team including City Staff, Landscape Architect and Construction Manager if they are not familiar with the system.

Contractor will act as the administrator of the system.

END OF SECTION

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
PRICE AND PAYMENT PROCEDURES 01 20 00 - 1
SECTION 01 20 00

PRICE AND PAYMENT PROCEDURES

1. GENERAL

1.1. RELATED DOCUMENTS AND PROVISIONS
Contractor shall review all Contract Documents for applicable provisions related to the provisions in this document, including without limitation:

1.1.1. General Conditions; and

1.1.2. Supplementary Conditions (if any).

1.2. DESCRIPTION

1.2.1. This Document contains procedures to be followed by the Contractor to request payment.

1.2.2. IF THERE IS ANY INCONSISTENCY IN THIS DOCUMENT WITH THE PROVISIONS IN THE

GENERAL CONDITIONS AND THE SUPPLEMENTARY CONDITIONS THAT THE

CONTRACTOR SHALL COMPLY WITH RELATED TO CHANGES AND/OR REQUESTS FOR CHANGES (e.g., “PAYMENTS,” “SCHEDULE OF VALUES”), THOSE PROVISIONS IN THE

GENERAL CONDITIONS AND THE SUPPLEMENTARY CONDITIONS SHALL TAKE PRECEDENCE.

1.3. MEASUREMENT

1.3.1. The quantities set forth in the Bid Schedule are approximate and are given to establish a uniform basis for the comparison of bids. The City reserves the right to increase or decrease the quantity of any class or portion of the work during the progress of construction in accord with the terms of the Contract.

1.4. PAYMENT

1.4.1. Make payment for the items listed on the Bid Schedule on the basis of the work actually performed and completed, such work including but not limited to, the furnishing of all necessary labor, materials, equipment, transportation, clean up, restoration of disturbed area, and all other appurtenances to complete the construction and installation of the work as shown on the drawings and described in the specification.

1.4.2. Unit prices are used as a means of computing the final figures for bid and Contract purposes, for periodic payments for work performed, for determining value of additions or deletions and wherever else reasonable.

1.5. SCHEDULE OF VALUES

1.5.1. Provide a breakdown of the Contract Price with enough detail to facilitate continued evaluation of Applications for Payment and Progress Reports.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
PRICE AND PAYMENT PROCEDURES 01 20 00 - 2

1.5.2. Contractor must update and resubmit the Schedule of Values before the next Invoice or Application for Payment when Change Orders or Construction Change Directives result in a change in the Contract Price.

1.5.3. Coordination: Coordinate preparation of the Schedule of Values with preparation of Contractor’s Construction Schedule. Comply with the provisions in the General Conditions regarding the Schedule of Values.

1.5.3.1. Correlate line items in the Schedule of Values with other required administrative forms and schedules, including the following:

1.5.3.1.1. Application for Payment forms.

1.5.3.1.2. Submittal Schedule.

1.5.3.1.3. Contractor’s Construction Schedule.

1.5.3.2. Submit the Schedule of Values to City as indicated in the Contract Documents and, if an updated Schedule of Values is needed, then no later than ten (10) days before the date scheduled for submittal of the next Application(s) for Payment.

1.5.3.3. Subschedules: Where the Work is separated into phases requiring separately phased payments, provide subschedules showing values correlated with each phase of payment.

1.5.4. Format and Content: Use the Project Manual table of contents as a guide to establish line items for the Schedule of Values. All aspects of the work shall be refernced in Schedule of Values.

1.5.4.1. Provide a breakdown of the Contract Price in enough detail to facilitate continued evaluation of Applications for Payment and progress reports.

Provide several line items for principal subcontract amounts, where appropriate. Include separate line items under required principal subcontracts for operation and maintenance manuals, punch list activities, Project Record Documents, and demonstration and training.

1.5.4.2. Round amounts to nearest whole dollar; total shall equal the Contract Price.

1.5.4.3. Provide a separate line item in the Schedule of Values for each part of the Work where Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed.

1.5.4.4. Provide separate line items in the Schedule of Values for initial cost of materials, for each subsequent stage of completion, and for total installed value of that part of the Work.

1.5.4.5. Allowances (if any): Provide a separate line item in the Schedule of Values for each allowance. Show line-item value of unit-cost allowances, as a product of the unit cost, multiplied by measured quantity. Use information indicated in the Contract Documents to determine quantities.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
PRICE AND PAYMENT PROCEDURES 01 20 00 - 3

1.5.4.6. Each item in the Schedule of Values and Applications for Payments shall be complete.

1.5.5. Schedule Updating: Update and resubmit the Schedule of Values before the next Application for Payment if there is a change in the Contract Price.

1.6. APPLICATIONS FOR PAYMENT

1.6.1. Form: Contractor shall utilize AIA Form G702 - Application and Certificate for Payment. and AIA Form G703 - Continuation Sheet, or City-approved form with the same information as these AIA forms.

1.6.2. Content and Format: Contractor shall use Schedule of Values for listing items in its Application for Payment.

1.6.3. Each Application for Payment shall be consistent with previous applications and payments as certified and paid for by City.

2. EXECUTION

2.1. MEASUREMENT AND PAYEMENT

2.1.1. Make payment on the basis of work actually performed completing each item in the Bid, such work, including, but not limited to the furnishing of all necessary labor, materials, equipment, transportation, cleanup, and all other appurtenances to complete the construction and installation of the work to the configuration and extent as shown on the drawings and described in the specifications. Payment for each item includes compensation for cleanup and restorations. Cost of cleanup and surface restorations (including pavement replacement) will be considered as the percentage retained in accordance with the Contract Documents, and complete payment will not be made until cleanup, restorations and as-builts are competed.

END OF SECTION

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
ALTERNATES AND UNIT PRICES 01 23 00 - 1
SECTION 01 23 00

ALTERNATES AND UNIT PRICING

1. ALTERNATES AND UNIT PRICES

1.1. RELATED DOCUMENTS AND PROVISIONS
Contractor shall review all Contract Documents for applicable provisions related to the provisions in this document, including without limitation:

1.1.1. General Conditions;

1.1.2. Supplementary Conditions (if any);

1.1.3. Bid Form and Proposal; and

1.1.4. Instruction to Bidders.

2. ADD ALTERNATES

1. Nature Play Area and Site Furnishing

2. Perimeter Fencing

3. Basketball Court Painting

3. Basketball Court Resurfacing and Painting

2.1. DESCRIPTION
Refer to Plan Sheet N0. LC101 – Landscape Construction and Materials Plan and Bid Form for a complete description of each alternate noted.

3. UNIT PRICING

3.1. DESCRIPTION
An amount proposed by Contractor and stated in its Bid Form for certain work defined in the Plans and Bid Form that may be priced by unit. The acceptance or rejection of any of the unit prices is strictly at the option of the City and subject to City's acceptance of Contractor's stated prices contained in the Bid Form and may be subsequently negotiated prior to incorporation on Change Order(s).

3.2. GENERAL
Contractor shall completely state all required figures based on Unit Prices required in the Bid Form.

Where scope of Work is decreased, all Work pertaining to the item, whether specifically stated or not, shall be omitted and where scope of Work is increased, all work pertaining to that item required to render same ready for use on the Project in accordance with intention of Drawings and Specifications shall be included in an agreed upon price amount.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
ALTERNATES AND UNIT PRICES 01 23 00 - 2

3.3. UNIT PRICES
Furnish unit prices for each of the named items on a square foot, lineal foot, or per each basis, as requested and applicable. Unit prices shall include all labor, materials, services, profit, overhead, insurance, bonds, taxes, and all other incidental costs of Contractor, subcontractors, and supplier(s).

END OF SECTION

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
PRODUCT OPTIONS AND SUBSTITUTIONS 00 10 00 - 1
SECTION 01 25 10

PRODUCT OPTIONS AND SUBSTITUTIONS

1. GENERAL

1.1. RELATED DOCUMENTS AND PROVISIONS
Contractor shall review all Contract Documents for applicable provisions related to the provisions in this document, including without limitation:

1.1.1. General Conditions;

1.1.2. Supplementary Conditions (if any); and

1.1.3. Instructions to Bidders.

1.2. DOCUMENT INCLUDES

1.2.1. Product options.

1.2.2. Limitations on Substitutions.

1.2.3. Regulatory Requirements.

1.2.4. Substitution Representation.

1.2.5. Submittal Procedure.

1.2.6. City’s Review.

1.3. DEFINITIONS

1.3.1. Requests for changes in products, materials, or equipment required by Contract Documents proposed by the Contractor prior to and after award of the Contract are considered requests for substitutions. Contractor must refer to the Instructions to Bidders, the General Conditions and the Supplementary Conditions for limitations on when requests for substitution(s) are permitted on Project. The following are not considered substitutions:

1.3.1.1. Revisions to Contract Documents requested by the City or Landscape Architect.

1.3.1.2. Specified options of products, materials, and equipment included in Contract Documents.

1.3.2. Whenever in the Specifications any material, product, thing, or service is indicated or specified by grade, patent, or proprietary name, or by name of manufacturer, that Specification shall be deemed to be used for the purpose of facilitating the description of the material, product, thing, or service, and shall be deemed to be followed by the words "or equal," except:

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
PRODUCT OPTIONS AND SUBSTITUTIONS 00 10 00 - 2

1.3.2.1. When designated to match other material, product, thing, or service in use on a particular public improvement either completed or in the course of completion; or

1.3.2.2. When designated as a field test or experiment.

1.4. PRODUCT OPTIONS

1.4.1. Products Specified by Reference Standards or by Description Only: Any Product meeting those standards or description.

1.4.2. Products Specified by Naming One or More Manufacturers with or without Provision for Substitution: Products of manufacturers named and meeting specifications with substitution of Products or manufacturer only when submitted under provisions of this section.

1.5. LIMITATIONS ON SUBSTITUTIONS

1.5.1. Requests for substitution prior to bid or after bid, shall only be permitted as indicated in and in accordance with requirements specified in the Instructions to Bidders, the General Conditions and the Supplementary Conditions.

1.5.2. The Bid shall be based upon the standards of quality established by those items of equipment and/or materials which are specifically identified in the Contract Documents.

1.5.3. Burden of proof of merit of requested substitution is the responsibility of the Contractor.

1.5.4. It is the sole responsibility of Contractor to submit the proper content of any requests for substitutions. Incomplete submittals will be rejected.

1.6. REGULATORY REQUIREMENTS

1.6.1. It shall be the responsibility of Contractor to obtain all regulatory approvals required for proposed substitutions.

1.6.2. All regulatory approvals shall be obtained for proposed substitutions prior to submittal of substitution request to Landscape Architect.

1.6.3. All costs incurred by the City in obtaining regulatory approvals for proposed substitutions to include the costs of the Landscape Architect and any authority having jurisdiction over the Project shall be reimbursed to the City. Costs of these services shall be reimbursed regardless of final acceptance or rejection of substitution.

1.7. SUBSTITUTION REPRESENTATION

1.7.1. In submitting a request for substitution, Contractor makes the representation that:

1.7.2. Contractor has investigated the proposed substitution and determined that it meets or exceeds the quality level of the specified product;

1.7.3. Contractor has determined that all components of the proposed substitution are

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
PRODUCT OPTIONS AND SUBSTITUTIONS 00 10 00 - 3
identical and fully interchangeable with the product name and number specified;

1.7.4. Contractor will provide the same warranty or guarantee for the substitution as for the specified product;

1.7.5. Contractor will coordinate installation and make changes to other work which may be required for the work to be completed with no additional cost to the City;

1.7.6. Contractor waives claims for additional cost or time extension which may subsequently become apparent; and

1.7.7. Contractor will reimburse City for the cost of City’s and Landscape Architect's review or redesign services associated with substitution request.

1.8. SUBMITTAL PROCEDURE

1.8.1. Submit two (2) copies of each request or pdf format electronically as directed by the City.

1.8.2. Submit request using City’s Substitution Request Form, if available, as indicated in Contract Forms and Submittals. Substitution requests that are not on City’s required form, if available, shall be returned without review.

1.8.3. Limit each request to one proposed substitution.

1.8.4. Request to include sufficient data so that direct comparison of proposed substitution can be made.

1.8.5. Provide complete documentation for each request. Documentation shall include the following information, as appropriate, as a minimum:

1.8.5.1. Statement of cause for substitution request.

1.8.5.2. Identify product by specification section and article number.

1.8.5.3. Provide manufacturer's name, address, and phone number. List fabricators, suppliers, and installers as appropriate.

1.8.5.4. List similar projects where proposed substitution has been used, dates of installation and names of Landscape Architect and City.

1.8.5.5. List availability of maintenance services and replacement materials.

1.8.5.6. Documented or confirmation of regulatory approval.

1.8.5.7. Product data, including drawings and descriptions of products.

1.8.5.8. Fabrication and installation procedures.

1.8.5.9. Samples of proposed substitutions.

1.8.5.10.Itemized comparison of significant qualities of the proposed substitution with

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
PRODUCT OPTIONS AND SUBSTITUTIONS 00 10 00 - 4
those of the product specified. Significant qualities may include size, weight, durability, performance requirements and visual effects.

1.8.5.11.Coordination information, including a list of changes or modifications needed to other items of work that will become necessary to accommodate proposed substitution.

1.8.5.12.Statement on the substitutions effect on the Construction Schedule.

1.8.5.13.Cost information including a proposal of the net reduction in cost to the Contract Price if the proposed substitution is accepted.

1.8.5.14.Certification that the substitution is equal to or better in every respect to that required by the Contract Documents and that substitution will perform adequately in the application intended.

1.8.5.15.Waiver of right to additional payment or time that may subsequently become necessary because of failure of substitution to perform adequately.

1.8.6. Inadequate warranty, vagueness of submittal, failure to meet specified requirements, or submittal of insufficient data will be cause for rejection of substitution request.

1.9. CITY’S REVIEW

1.9.1. The City will accept or reject proposed substitution within a reasonable amount of time.

1.9.2. If a request is made prior to bid opening and the City has not completed its review, Contractor shall base its bid on the product specified only.

1.9.3. There shall be no claim for additional time for review of proposed substitutions.

1.9.4. Final acceptance of a substitution submitted prior to the date established for the receipt of bids will be in the form of an addendum.

END OF SECTION

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CONTRACT MODIFICATION PROCEDURES 01 26 00 - 1
SECTION 01 26 00

CONTRACT MODIFICATION PROCEDURES

1. GENERAL

1.1. RELATED DOCUMENTS AND PROVISIONS
Contractor shall review all Contract Documents for applicable provisions related to the provisions in this document, including without limitation:

1.1.1. General Conditions;

1.1.2. Supplementary Conditions (if any);

1.1.3. Allowances;

1.1.4. Product Options and Substitutions; and

1.1.5. Project Coordination.

1.2. DESCRIPTION

1.2.1. This Document contains procedures to be followed by the Contractor to request changes in the Contract Time of the Contract Price.

1.2.2. IF THERE IS ANY INCONSISTENCY IN THIS DOCUMENT WITH THE PROVISIONS IN THE

GENERAL CONDITIONS AND THE SUPPLEMENTARY CONDITIONS THAT THE

CONTRACTOR SHALL COMPLY WITH RELATED TO CHANGES AND/OR REQUESTS FOR CHANGES (e.g., “Change in the Work”), THOSE PROVISIONS IN THE GENERAL CONDITIONS AND THE SUPPLEMENTARY CONDITIONS SHALL TAKE PRECEDENCE.

1.3. SUMMARY
This Document specifies administrative and procedural requirements for handling and processing Contract modifications.

1.4. CONSTRUCTION CHANGE DIRECTIVE
The City may as provided by law, by Construction Directive and without invalidating the Contract, order changes in the Work consisting of additions, deletions, or other revisions.

1.5. PRICE REQUESTS

1.5.1. Do not consider Price Requests to be instructions either to stop work in progress or to execute the proposed change.

1.5.2. Within time specified in Price Request after receipt of Price Request, submit a quotation estimating cost adjustments to the Contract Price and the Contract Time necessary to execute the change.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CONTRACT MODIFICATION PROCEDURES 01 26 00 - 2

1.5.2.1. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

1.5.2.2. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

1.5.2.3. Include costs of labor and supervision directly attributable to the change.

1.5.2.4. Include an updated Contractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

1.6. PROPOSED CHANGE ORDERS
Contractor may propose changes by submitting a request for a change on City’s Proposed Change Order form (PCO) to City.

1.6.1. Include an updated Contractor's Construction Schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

1.6.2. Comply with Contract Document requirements if the proposed change requires substitution of one product or system for product or system specified.

END OF SECTION

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
REQUESTS FOR INFORMATION 01 26 10 - 1
SECTION 01 26 10

REQUESTS FOR INFORMATION

1. GENERAL

1.1. RELATED DOCUMENTS AND PROVISIONS
Contractor shall review all Contract Documents for applicable provisions related to the provisions in this document, including without limitation:

1.1.1. General Conditions;

1.1.2. Supplementary Conditions (if any);

1.1.3. Documentation Requirements;

1.1.4. Electronic Data Transfer;

1.1.5. Submittals;

1.1.6. Contract Closeout and Final Cleaning;

1.1.7. Operation and Maintenance Data;

1.1.8. Warranties; and

1.1.9. Record Documents;

1.2. DESCRIPTION
This Document contains procedures to be followed by the Contractor to request Landscape Architect provide additional information necessary to clarify or amplify an item in the Contract Documents that Contractor thinks is not clearly shown or called for in the Drawings or Specifications or other portions of the Contract Documents, or to address issues that have arisen under field conditions.

1.3. PROCEDURES

1.3.1. Notification by Contractor:

1.3.1.1. Submit all requirements for clarification or additional information, whether originated by the Contractor, a Subcontractor, or supplier at any tier, in writing to City as required by the Contract Documents through the Project Management software.

1.3.1.2. Number RFIs sequentially. Follow RFI number with sequential alphabetical suffix as necessary for each resubmission. For example, the first RFI would be “001.” The second RFI would be “002.”

1.3.1.3. All RFIs shall reference all applicable Contract Document(s), including Specification section(s), detail(s), page number(s), drawing number(s), and sheet number(s), etc. Contractor shall make suggestions and interpretations of

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
REQUESTS FOR INFORMATION 01 26 10 - 2
the issue raised by each RFI. An RFI cannot modify the Contract Price, Contract Time, or the Contract Documents.

1.3.1.4. Limit each RFI to one subject.

1.3.2. Contractor shall not:

1.3.2.1. Submit an RFI as a request for substitution.

1.3.2.2. Submit an RFI as a submittal.

1.3.2.3. Submit an RFI without first having thoroughly reviewed the Contract Documents.

1.3.2.4. Submit an RFI in a manner that suggests that specific portions of the Contract Documents are assumed to be excluded or by taking an isolated portion of the Contract Documents in part rather than whole.

1.3.2.5. Submit an RFI in an untimely manner without proper coordination and scheduling of Work related trades.

1.3.2.6. If Contractor submits an RFI contrary to the above, Contractor shall pay the cost of any review, which cost shall be deducted from the Contract Price.

1.3.3. Contractor shall be liable to the City for all costs incurred by the City associated with the processing, reviewing, evaluating and responding to any RFI, including without limitation, fees of the Landscape Architect and any other design consultant to the Landscape Architect or the City, that City reasonably determines:

1.3.3.1. Does not reflect adequate or competent supervision or coordination by the Contractor or any Subcontractor; or

1.3.3.2. Does not reflect the Contractor's adequate or competent knowledge of the requirements of the Work or the Contract Documents;

1.3.3.3. Requests an interpretation or decision of a matter where the information sought is equally available to the Contractor; or

1.3.3.4. Is not justified for any other reason.

1.4. RESPONSE TIME

1.4.1. Landscape Architect shall review RFIs and issue a response and instructions to Contractor within a reasonable time frame (5 business days), from the date the RFI is received and dated by the City.

1.4.2. Responses from the City will not change any requirement of the Contract unless so noted by the City in the response to the RFI. Should the Contractor contend that a response to an RFI causes a change to the Contract that requires a Change Order, the Contractor shall, before proceeding, give written notice to the City, indicating that the Contractor considers the City’s response to the RFI to be a Change Order, as required by the Contract Documents.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
REQUESTS FOR INFORMATION 01 26 10 - 3

1.4.3. Should Contractor direct its Subcontractors to proceed with the Work affected before receipt of a response from Landscape Architect, any portion of the Work which is not done in accordance with the Landscape Architect’s ultimate interpretations, clarifications, instructions, or decisions is subject to removal or replacement at Contractor’s sole expense and responsibility.

END OF SECTION

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
PROJECT MEETINGS 01 31 00 - 1
SECTION 01 31 00

PROJECT MEETINGS

1. GENERAL

1.1. RELATED DOCUMENTS AND PROVISIONS:

Contractor shall review all Contract Documents for applicable provisions related to the provisions in this document, including without limitation:

1.1.1. General Conditions;

1.1.2. Supplementary Conditions (if any); and

1.1.3. Technical Specifications.

1.2. SECTION INCLUDES

1.2.1. Coordination Responsibilities of the Contractor.

1.2.2. Field Engineering Responsibilities of the Contractor.

1.2.3. Preconstruction Conference.

1.2.4. Progress Meetings.

1.2.5. Pre-Installation Conferences.

1.3. COORDINATION RESPONSIBILITIES OF THE CONTRACTOR

1.3.1. Coordinate scheduling, submittals, and Work of the Specifications to assure efficient and orderly sequence of installation of interdependent construction elements, with provisions for accommodating items installed later.

1.3.2. Prior to commencement of a particular type or kind of Work examine relevant information, contract documents, and subsequent data issued to the Project.

1.3.3. Verify that utility requirement characteristics of operating equipment are compatible with building utilities. Coordinate Work of various sections having interdependent responsibilities for installing, connecting to, and placing in service such equipment.

1.3.4. Closing up of holes, backfilling, and other covering up operations shall not proceed until all enclosed or covered Work and inspections have been completed. Verify before proceeding.

1.3.5. Coordinate space requirements and installation of mechanical and electrical Work which are indicated diagrammatically on Drawings. Follow routing shown for pipes, ducts, and conduit as closely as practicable; place runs parallel with line of building. Utilize spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
PROJECT MEETINGS 01 31 00 - 2

1.3.6. In finished areas except as otherwise indicated, conceal pipes, ducts, and wiring within the construction. Coordinate locations of fixtures and outlets with finish elements.

1.3.7. In locations where several elements of mechanical and electrical Work must be sequenced and positioned with precision in order to fit into available space, prepare coordination drawings showing the actual conditions required for the installation.

Prepare coordination drawings prior to purchasing, fabricating, or installing any of the elements required to be coordinated.

1.3.8. Closing up of walls, partitions or furred spaces, backfilling, and other covering up operations shall not proceed until all enclosed or covered Work and inspections have been completed. Verify before proceeding.

1.3.9. Coordinate completion and cleanup of Work of separate sections in preparation for completion and for portions of Work designated for City’s occupancy.

1.3.10. After City occupancy of Project, coordinate access to Site for correction of defective Work and Work not in accordance with Contract Documents, to minimize disruption of City's activities.

1.3.11. Coordinate all utility company Work in accordance with the Contract Documents.

1.3.12. Key Personnel Names: Within five (5) working days of receiving Notice to Proceed, submit a list of key personnel and their assignments and contact information, including superintendent and other personnel in attendance at Project site.

1.4. FIELD ENGINEERING RESPONSIBILITIES OF THE CONTRACTOR

1.4.1. Contractor shall employ a Land Surveyor registered in the State of California and acceptable to the Landscape Architect.

1.4.2. Control datum for survey is that established by City provided survey. Contractor to locate and protect survey control and reference points.

1.4.3. Replace dislocated survey control points based on original survey control.

1.4.4. Provide field engineering services. Establish elevations, lines, and levels utilizing recognized engineering survey practices.

1.4.5. Upon completion of Work, submit certificate signed by the Land Surveyor that elevations and locations of Work are in conformance with Contract Documents. Record deviations on Record Drawings.

1.5. PRECONSTRUCTION CONFERENCE

1.5.1. Construction Manager or City Project Manager will schedule a conference immediately after, and in no case more than ten (10) days after issuing of Notice to Proceed and/or receipt of fully executed Contract Documents prior to Project mobilization.

1.5.2. Mandatory Attendance: Construction Manager, Project Engineer, City Project Manager, Landscape Architect of Record, Contractor, Contractor's Project Manager, and Contractor's Job/Project Superintendent.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
PROJECT MEETINGS 01 31 00 - 3

1.5.3. Optional Attendance: Landscape Architect's consultants, and utility company representatives.

1.5.4. Construction Manager shall preside at conference and the Construction Manager shall prepare and record minutes and distribute copies.

1.6. PROGRESS MEETINGS

1.6.1. Contractor shall schedule and administer meetings throughout progress of the Work at a minimum of every week.

1.6.2. Contractor will make arrangements for meetings, prepare agenda, and preside at meetings. Contractor shall record and distribute meeting minutes.

1.6.3. Attendance Required: Job Superintendent, Construction Manager, Project Engineer, City Project Manager, Landscape Architect of Record, Subcontractors, and suppliers as appropriate to agenda topics for each meeting.

1.6.4. City has authority to schedule mandatory meetings other than those listed, as necessary.

1.7. PRE-INSTALLATION CONFERENCES

1.7.1. When required in individual specification section, Contractor shall convene a preinstallation conference prior to commencing Work of the section. Refer to individual specification section for timing requirements of conference.

1.7.2. Contractor shall require its Subcontractors and suppliers directly affecting, or affected by, Work of the specific section to attend.

1.7.3. Notify the Construction Manager, City Project Manager and Landscape Architect of Record five (5) working days in advance of meeting date.

1.7.4. A pre-installation conference may coincide with a regularly scheduled progress meeting.

1.7.5. Contractor shall prepare agenda, preside at conference, record minutes, and distribute copies.

1.7.6. Pre-installation Schedule: As a minimum, Work being installed under the Contract Documents technical sections will require pre-installation conferences. Contractor shall review the technical specifications and add all additional requirements for preinstallation meetings contained in those sections.

END OF SECTION

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CONSTRUCTION SCHEDULE 01 32 16 - 1
SECTION 01 32 16

CONSTRUCTION SCHEDULE

1. GENERAL

1.1. RELATED DOCUMENTS AND PROVISION
Contractor shall review all Contract Documents for applicable provisions related to the provisions in this document, including without limitation:

1.1.1. General Conditions;

1.1.2. Supplementary Conditions (if any);

1.1.3. Coordination and Meetings; and

1.1.4. Submittals.

1.2. REFERENCES

1.2.1. Construction Planning and Scheduling Manual - A Manual for General Contractors and the Construction Industry, The Associated General Contractors of America (AGC).

1.2.2. CSI - Construction Specifications Institute MP-2-1 Master Format.

1.2.3. U.S. National Weather Service - Local Climatological Data.

1.3. PERFORMANCE REQUIREMENTS

1.3.1. Ensure adequate scheduling during construction activities so Work may be prosecuted in an orderly and expeditious manner within stipulated Contract Time.

1.3.2. Ensure coordination of Contractor and Subcontractors at all levels.

1.3.3. Ensure coordination of submittals, fabrication, delivery, erection, installation, and testing of products, materials and equipment.

1.3.4. Ensure on-time delivery of City furnished products, materials and equipment.

1.3.5. Ensure coordination of jurisdictional reviews.

1.3.6. Monitor progress of Work.

1.3.7. Prepare proper requests for changes to Contract Time.

1.3.8. Prepare proper requests for changes to Construction Schedule.

1.3.9. Assist in detection of schedule delays and identification of corrective actions.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CONSTRUCTION SCHEDULE 01 32 16 - 2

1.4. QUALITY ASSURANCE

1.4.1. Perform scheduling work in accordance with Construction Planning and Scheduling Manual published by the AGC.

1.4.2. Maintain one copy of Construction Planning and Scheduling Manual on Site.

1.4.3. In the event of discrepancy between the AGC publication and the Contract Documents, provisions of the Contract Documents shall govern.

1.5. QUALIFICATIONS

1.5.1. Scheduler:

1.5.1.1. Contractor shall retain a construction scheduler to work in enough capacity to perform all of the Contractor’s requirements to prepare the Construction Schedule. The Scheduler shall plan, coordinate, execute, and monitor a cost/resource loaded CPM schedule as required for Project and have a minimum of five (5) years direct experience using Project Scheduling software, as approved by Owner..

1.5.1.2. Scheduler will cooperate with City and shall be available on site for monitoring, maintaining and updating schedules in a timely manner.

1.5.1.3. City has the right to reject the Scheduler based upon a lack of experience as required by this Document or based on lack of performance and timeliness of schedule submittals/fragnets on past projects. Contractor shall within seven (7) calendar days of City’s rejection, propose another scheduler who meets the experience requirements stated above.

1.5.2. Administrative Personnel: Five (5) years minimum experience in using and monitoring schedules on comparable projects.

1.6. SUBMITTALS

1.6.1. Submit Master Construction Schedule at the beginning of construction. During construction, submit updated Master Construction Schedule within first week of each month.

1.6.2. Submit Short Interval Schedule at each Construction Progress Meeting.

1.6.3. Submit Time Adjustment Schedule within five (5) days of commencement of a claimed delay.

1.6.4. Submit Recovery Schedules as required for timely completion of Work or when demanded by the City.

1.6.5. Submit job cost reports when requested by the City.

1.6.6. Submit one (1) reproducible and two (2) copies of each schedule and cost report.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CONSTRUCTION SCHEDULE 01 32 16 - 3

1.7. REVIEW AND EVALUATION

1.7.1. Contractor shall participate in joint review of Construction Schedule and Reports with City, Construction Manager and Landscape Architect.

1.7.2. Within seven (7) days of receipt of City and/or Construction Manager’s comments provide satisfactory revision to Construction Schedule or adequate justification for activities in question.

1.7.3. In the event that an activity or element of Work is not detected by City or Construction Manager review, such omission or error shall be corrected by next scheduled update and shall not affect Contract Time.

1.7.4. Acceptance by City of corrected Construction Schedule shall be a condition precedent to making any progress payments.

1.7.5. Review and acceptance by City and Construction Manager of Preliminary Construction Schedule or Construction Schedule does not constitute responsibility whatsoever for accuracy or feasibility of schedules nor does such acceptance expressly or impliedly warrant, acknowledge or admit reasonableness of activities, logic, duration, manpower, cost or equipment loading stated or implied on schedules.

1.8. FORMAT

1.8.1. Prepare diagrams and supporting mathematical analyses using Precedence Diagramming Method, under concepts and methods outlined in AGC Construction Planning and Scheduling Manual, or other method pre-approved by City.

1.8.2. Illustrate order and interdependence of activities and sequence of Work.

1.8.3. Illustrate complete sequence of construction by activity.

1.8.4. Provide legend of symbols and abbreviations used.

1.9. COST AND SCHEDULE REPORTS

1.9.1. Activity Analysis: Tabulate each activity of network diagram and identify for each activity:

1.9.1.1. Description.

1.9.1.2. Interface with outside contractors or agencies.

1.9.1.3. Number.

1.9.1.4. Preceding and following number.

1.9.1.5. Duration.

1.9.1.6. Earliest start date.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CONSTRUCTION SCHEDULE 01 32 16 - 4

1.9.1.7. Earliest finish date.

1.9.1.8. Actual start date.

1.9.1.9. Actual finish date.

1.9.1.10. Latest start date.

1.9.1.11. Latest finish date.

1.9.1.12. Total and free float.

1.9.1.13. Identification of critical path activity.

1.9.1.14. Monetary value keyed to Schedule of Values.

1.9.1.15. Manpower requirements.

1.9.1.16. Responsibility.

1.9.1.17. Percentage complete.

1.9.1.18. Variance positive or negative.

1.9.2. Required Sorts: List activities in sorts or groups:

1.9.2.1. By activity number.

1.9.2.2. By amount of float time in order of early start.

1.9.2.3. By responsibility in order of earliest start date.

1.9.2.4. In order of latest start dates.

1.9.2.5. In order of latest finish dates.

1.9.2.6. Application for payment sorted by Schedule of Values.

1.9.2.7. Listing of activities on critical path.

1.9.3. Listing of basic input data which generates schedule.

1.10. CONSTRUCTION SCHEDULE

1.10.1. Contractor shall develop and submit a preliminary schedule of construction (or Preliminary Construction Schedule) as required by this Document and the Contract Documents. It shall be submitted in computer generated network format and shall be organized by Activity Codes representing the intended sequencing of the Work, and with time scaled network diagrams of activities. The Preliminary Construction Schedule shall include activities such as mobilization, preparation of submittals, specified review periods, procurement items, fabrication items, milestones, and all detailed construction

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CONSTRUCTION SCHEDULE 01 32 16 - 5
activities.

1.10.2. Upon City’s acceptance of the Preliminary Construction Schedule, Contractor shall update the accepted Preliminary Construction Schedule until Contractor’s Construction Schedule is fully developed and accepted. Since updates to the Construction Schedule are the basis for payment to Contractor, submittal and acceptance of the Construction Schedule and updates shall be a condition precedent to making of monthly payments, as indicated in the General Conditions.

1.10.3. Failure to submit an adequate or accurate Preliminary Construction Schedule, Construction Schedule, updates thereto or failure to submit on established dates, will be considered a breach of Contract.

1.10.4. The Construction Schedule shall comply with the following and include the following:

1.10.4.1. Provide a written narrative describing Contractor’s approach to mobilization, procurement, and construction during the first thirty (30) calendar days including equipment and material delivery, Site access, submittals, and permits.

1.10.4.2. Shall designate critical path or paths.

1.10.4.3. Procurement activities to include mobilization, shop drawings and sample submittals.

1.10.4.4. Identification of key and long-lead elements and realistic delivery dates.

1.10.4.5. Approximate duration of each activity.

1.10.4.6. Shall contain seasonal weather considerations.

1.10.4.7. Indicate a date for Project Completion that is no later than Completion Date subject to any time extensions processed as part of a Change Order.

1.10.4.8. Conform to mandatory dates specified in the Contract Documents.

1.10.4.9. Contractor shall allow for inclement weather in the Proposed Baseline Schedule by incorporating an activity titled “Rain Day Impact Allowance” as the last activity prior to the Completion Milestone. No other activities may be concurrent with it. The duration of the Rain Day Impact Allowance activity will be in accordance with the Supplementary Conditions, and will be calculated from the Notice to Proceed until the Completion.

1.10.4.10. Level of detail shall correspond to complexity of work involved.

1.10.4.11. Indicate procurement activities, delivery, and installation of City furnished material and equipment.

1.10.4.12. Subcontractor work at all levels shall be included in schedule.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CONSTRUCTION SCHEDULE 01 32 16 - 6

1.10.4.13. As developed, shall show sequence and interdependence of activities required for complete performance of Work.

1.10.4.14. Shall be logical and show a coordinated plan of Work.

1.10.4.15. Duration of activities shall be coordinated with Subcontractors and suppliers and shall be best estimate of time required.

1.10.4.16. Shall show description, duration and float for each activity.

1.10.5. Equipment and Materials. For major equipment and materials show a sequence of activities including:

1.10.5.1. Preparation of shop drawings and sample submissions.

1.10.5.2. Review of shop drawings and samples.

1.10.5.3. Finish and color selection.

1.10.5.4. Fabrication and delivery.

1.10.5.5. Erection or installation.

1.10.5.6. Testing.

1.10.6. Include a minimum of fifteen (15) days prior to Completion Date for punch lists and clean up. No other activities shall be scheduled during this period.

1.11. SHORT INTERVAL SCHEDULE

1.11.1. The Four-Week Rolling Schedule (one week prior to current week, current week and two weeks after current week) shall be based on the most recent City Accepted Construction Schedule or Update. It shall include weekly updates to all construction, submittal, fabrication/procurement, and separate Work Contract activities. Contractor shall ensure that it accurately reflects the current progress of the Work.

1.11.2. Shall be fully developed horizontal bar-chart-type schedule directly derived from Construction Schedule.

1.11.3. Prepare schedule on sheet of sufficient width to clearly show data.

1.11.4. Provide continuous heavy vertical line identifying first day of week.

1.11.5. Provide continuous subordinate vertical line identifying each day of week.

1.11.6. Identify activities by same activity number and description as Construction Schedule.

1.11.7. Show each activity in proper sequence.

1.11.8. Indicate graphically sequences necessary for related activities.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CONSTRUCTION SCHEDULE 01 32 16 - 7

1.11.9. Indicate activities completed or in progress for previous two (2) week period.

1.11.10. Indicate activities scheduled for succeeding three (3) week period.

1.11.11. Further detail should be added if necessary to monitor schedule or if requested by City.

1.12. REQUESTED TIME ADJUSTMENT SCHEDULE

1.12.1. Updated Construction Schedule shall not show a Completion Date later than the Contract Time, subject to any time extensions processed as part of a Change Order.

1.12.2. If an extension of time is requested, a separate schedule entitled "Requested Time Adjustment Schedule" shall be submitted to City and Landscape Architect.

1.12.3. Indicate requested adjustments in Contract Time which are due to changes or delays in completion of Work.

1.12.4. Extension request shall include forecast of Project Completion date and actual achievement of any dates listed in Contract Documents.

1.12.5. To the extent that any requests are pending at time of any Construction Schedule update, Time Adjustment Schedule shall also be updated.

1.12.6. Schedule shall be a time-scaled network analysis.

1.12.7. Accompany schedule with formal written time extension request and detailed impact analysis justifying extension.

1.12.8. Time impact analysis shall demonstrate time impact based upon date of delay, and status of construction at that time and event time computation of all affected activities.

Event times shall be those as shown in latest Construction Schedule.

1.12.9. Activity delays shall not automatically constitute an extension of Contract Time.

1.12.10. Failure of Subcontractors shall not be justification for an extension of time.

1.12.11. Float is not for the exclusive use or benefit of any single party. Float time shall be apportioned according to needs of Project, as determined by the City.

1.12.12. Float suppression techniques such as preferential sequencing, special lead/lag logic restraints, extended activity durations, or imposed dates shall be apportioned according to benefit of Project.

1.12.13. Extensions will be granted only to extent that time adjustments to activities exceed total positive float of the critical path and extends Completion date.

1.12.14. City shall not have an obligation to consider any time extension request unless requirements of Contract Documents, and specifically, but not limited to these requirements, are complied with.

1.12.15. City shall not be responsible or liable for any construction acceleration due to failure of City to grant time extensions under Contract Documents should requested adjustments

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CONSTRUCTION SCHEDULE 01 32 16 - 8
in Contract Time not substantially comply with submission and justification requirements of Contract for time extension requests.

1.12.16. In the event a Requested Time Adjustment Schedule and Time Impact Analysis are not submitted within ten (10) days after commencement of a delay it is mutually agreed that delay does not require a Contract Time extension.

1.13. RECOVERY SCHEDULE

1.13.1. When activities are behind Construction Schedule a supplementary Recovery Schedule shall be submitted.

1.13.2. Contractor shall prepare and submit to the City a Recovery Schedule whenever activities are behind Construction Schedule or at any time requested by the City, at no cost to the City.

1.13.3. Form and detail shall be sufficient to explain and display how activities will be rescheduled to regain compliance with Construction Schedule and to complete the Work by the Completion Date.

1.13.4. Maximum duration shall be one (1) month and shall coincide with payment period.

1.13.5. Ten (10) days prior to expiration of Recovery Schedule, Contractor shall have to show verification to determine if activities have regained compliance with Construction Schedule. Based upon this verification the following will occur:

1.13.5.1. Supplemental Recovery Schedule will be submitted to address subsequent payment period.

1.13.5.2. Construction Schedule will be resumed.

1.14. UPDATING SCHEDULES

1.14.1. Review and update schedules at least ten (10) days prior to submitting an Application for Payment. Submit the schedule in the original format, pdf format, and hard copy.

1.14.2. Maintain schedules to record actual prosecution and progress.

1.14.3. Approved Change Orders which affect schedules shall be identified as separate new activities.

1.14.4. No other revisions shall be made to schedules unless authorized by City.

1.14.5. Schedule Narrative Report: Contractor shall include a written report to explain the Monthly Schedule Update. The narrative shall, at a minimum, include the following headings with appropriate discussions of each topic:

1.14.5.1. Activities or portions of activities completed during previous reporting period.

1.14.5.2. Actual start dates for activities currently in progress.

1.14.5.3. Deviations from critical path in days ahead or behind.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CONSTRUCTION SCHEDULE 01 32 16 - 9

1.14.5.4. List of major construction equipment used during reporting period and any equipment idle.

1.14.5.5. Number of personnel by trade engaged on Work during reporting period.

1.14.5.6. Progress analysis describing problem areas.

1.14.5.7. Current and anticipated delay factors and their impact.

1.14.5.8. Proposed corrective actions and logic revisions for Recovery Schedule.

1.14.5.9. Proposed modifications, additions, deletions and changes in logic of Construction Schedule.

1.14.5.10. In updating the Schedule, Contractor shall not modify Activity ID numbers, schedule calculation rules/criteria, or the Activity Coding Structure required.

1.14.6. Schedule update will form basis upon which progress payments will be made.

1.14.7. City will not be obligated to review or process Application for Payment until the Construction Schedule and Schedule Narrative Report have been submitted.

1.15. DISTRIBUTION

1.15.1. Following joint review and acceptance of updated schedules distribute copies to City, Construction Manager, Landscape Architect, and all other concerned parties.

1.15.2. Instruct recipients to promptly report in writing any problem anticipated by projections shown in schedules.

2. PRODUCTS

2.1. SCHEDULING SOFTWARE
Contractor shall utilize City-approved software and shall employ the Critical Path Method (CPM) in the development and maintenance of the Construction Schedule . It shall be capable of generating timescaled logic diagrams, resource histograms and profiles, bar charts, layouts and reports with any and/or all activity detail.

2.2. ELECTRONIC DATA
Provide electronic copies of all schedules in a format approved by the City.

END OF SECTION

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SUBMITTALS 01 33 00 - 1
SECTION 01 33 00

SUBMITTALS

1. GENERAL

1.1. RELATED DOCUMENTS AND PROVISION
Contractor shall review all Contract Documents for applicable provisions related to the provisions in this document, including without limitation:

1.1.1. General Conditions;

1.1.2. Supplementary Conditions;

1.1.3. Instructions to Bidders;

1.1.4. Summary of Work;

1.1.5. Contract Forms and Submittals;

1.1.6. Product Options and Substitutions;

1.1.7. Requests for Information;

1.1.8. Contract Closeout and Final Cleaning;

1.1.9. Operation and Maintenance Data;

1.1.10. Warranties;

1.1.11. Record Documents; and

1.1.12. Demonstration and Training;

1.2. DOCUMENT INCLUDES

1.2.1. Submittal procedures

1.2.2. Shop drawings.

1.2.3. Electronic Submittal Process

1.2.4. Product data.

1.2.5. Samples.

1.2.6. Manufacturers' Instructions.

1.2.7. Manufacturers' Certificates.

1.2.8. Mock-Up.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SUBMITTALS 01 33 00 - 2

1.2.9. Deferred permit approval requirements.

1.3. SUBMITTAL PROCEDURES –
Contractor shall utilize City-approved web-based Project Management software for the submittal process.

1.3.1. Contractor shall transmit each submittal in conformance with requirements of this Document. For each submittal, Contractor shall:

1.3.1.1. Sequentially number the transmittal forms. Resubmitted submittals must have the original number with an alphabetic suffix;

1.3.1.2. Identify Project and Landscape Architect's project number, Contractor, Subcontractor or supplier; pertinent Drawing sheet and detail number(s), and specification Section number, as appropriate;

1.3.1.3. Apply Contractor's stamp, signed or initialed certifying that review, verification of Products required, field dimensions, adjacent construction work, and coordination of information is in accordance with the requirements of the Work and Contract Documents. Submittals without Contractor's stamp and signature will be returned without review.

1.3.2. Coordinate preparation and processing of submittals with performance of Work.

Transmit each submittal sufficiently in advance of performance of Work to avoid delay.

1.3.2.1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

1.3.2.2. Coordinate transmittal of different types of submittals for related parts of Work so processing will not be delayed because of the need to review submittals concurrently for coordination.

1.3.2.3. Landscape Architect reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

1.3.3. Comply with Contract Documents for list of submittals and time requirements for scheduled performance of Work.

1.3.4. No extension of Contract Time will be authorized because of failure to transmit submittals to the Landscape Architect sufficiently in advance of the Work to permit processing.

1.3.5. Identify variations from Contract Documents and Product or system limitations which may be detrimental to successful performance of the completed Work.

1.3.6. Provide space for Contractor and Landscape Architect review stamps.

1.3.7. Revise and resubmit submittals as required, identify all changes made since previous submittal.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SUBMITTALS 01 33 00 - 3

1.3.8. Distribute copies of reviewed submittals to concerned parties. Instruct parties to promptly report any inability to comply with provisions.

1.3.9. Submittals not requested will not be recognized or processed. Submittals not requested will be returned without review.

1.4. SHOP DRAWINGS

1.4.1. Prepare Project-specific information, drawn accurately to scale. Do not reproduce Contract Documents or copy standard information as the basis of shop drawings.

Standard information prepared without specific reference to the Project is not a shop drawing.

1.4.2. Do not use or allow others to use Shop Drawings which have been submitted and have been rejected.

1.4.3. Preparation: Fully illustrate requirements in Contract Documents. Include the following information, as applicable:

1.4.3.1. Dimensions.

1.4.3.2. Identification of products.

1.4.3.3. Fabrication and installation drawings.

1.4.3.4. Roughing-in and setting diagrams.

1.4.3.5. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.

1.4.3.6. Shop work manufacturing instructions.

1.4.3.7. Templates and patterns.

1.4.3.8. Schedules.

1.4.3.9. Design calculations.

1.4.3.10. Compliance with specified standards.

1.4.3.11.Notation of coordination requirements.

1.4.3.12.Notation of dimensions established by field measurements.

1.4.3.13.Relationship to adjoining construction clearly indicated.

1.4.3.14.Seal and signature of professional engineer if specified.

1.4.3.15.Wiring Diagrams: Differentiate between manufacturer-installed and fieldinstalled wiring.

1.4.3.16.All deviations from the Contract Documents, clearly indicated.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SUBMITTALS 01 33 00 - 4

1.4.3.17.Copy of letter indicating acceptance of deviations indicated on the submittal.

1.4.4. Sheet Size: Except for templates, patterns, and similar full-size drawings, submit Shop Drawings on sheets at least 8-1/2 by 11 inches (215 by 280 mm) but no larger than 30 by 40 inches (750 by 1000 mm).

1.4.5. Do not use Shop Drawings without an appropriate final stamp from the Contractor and City indicating action taken in connection with construction.

1.4.6. Deviations from Contract Documents require specific written acceptance by the City of the noted deviation and clear indication on the submittal.

1.5. ELECTRONIC SUBMITTAL PROCESS

1.5.1. Submittal Procedure for Large Format Shop Drawings.

1.5.1.1. Contractor shall provide two (2) paper copies of the large format Shop Drawings directly to the Landscape Architect and Contractor will upload/post an electronic drawing file with a transmittal (with a detailed description of the submittal including the subject, specification number and number of drawings) on the Project Management software

1.5.1.2. Contractor shall verify that the Schedule of Submittals and all submittal log(s) on Project Management software are accurate and up to date.

1.5.1.3. The Landscape Architect will review and markup each Submittal and provide changes to Contractor for Contractor’s incorporation into the Submittal.

1.5.1.4. This process will continue until the Contractor has provided a Submittal that is acceptable to the City and the Landscape Architect.

1.5.1.5. Once a Submittal is accepted, the Landscape Architect will provide a final accepted Submittal to the Contractor and the Contractor will closeout that one Submittal.

1.5.1.6. Contractor shall send one (1) copy of the completed record submittal of the large format documents to a vendor for scanning and upload on Project Management software .

1.5.2. Product Data, Calculations and Small Format Drawings

1.5.2.1. Contractor shall upload/post one (1) electronic copy (from manufacturer’s website or pre-scanned) of the product literature, data, calculations, and/or small format shop drawings to Project Management software with a Transmittal (with a detailed description of the submittal) directly to the CM.

1.5.2.2. The Landscape Architect will review and markup each Submittal and provide changes to Contractor for Contractor’s incorporation into the Submittal.

1.5.2.3. This process will continue until the Contractor has provided a Submittal that is acceptable to the City and the Landscape Architect.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SUBMITTALS 01 33 00 - 5

1.5.2.4. Once a Submittal is accepted, the Landscape Architect will provide a final accepted Submittal to the Contractor and the Contractor will closeout that one Submittal.

1.5.2.5. Contractor shall send one (1) copy of the completed record submittal of the documents to a vendor for scanning and upload on Project Management software.

1.5.3. Sample Submittal Procedure – (Product / Assembly Samples)

1.5.3.1. Contractor shall provide four (4) physical samples directly to the Landscape Architect and Contractor will upload/post an electronic transmittal (with a detailed description of the submittal including the subject, specification number and number of drawings) on Project Management software.

1.5.3.2. The Landscape Architect will review and markup each Submittal and provide changes to Contractor for Contractor’s incorporation into the Submittal.

1.5.3.3. This process will continue until the Contractor has provided a Submittal that is acceptable to the City and the Landscape Architect.

1.5.3.4. Once a Submittal is accepted, the Landscape Architect will provide a final accepted Submittal to the Contractor and the Contractor will closeout that one Submittal.

1.5.3.5. Contractor shall send one (1) copy of the completed record submittal of the documents to a vendor for scanning and upload on Project Management software.

1.6. PRODUCT DATA

1.6.1. In addition to the above requirements, mark each copy to identify applicable products, models, options, and other data. Supplement manufacturers' standard data to provide information unique to this Project.

1.6.2. After review, distribute in accordance with the above provisions and provide copies for Record Documents described in the Contract Documents.

1.7. SAMPLES

1.7.1. In addition to the above requirements, submit samples to illustrate functional and aesthetic characteristics of the Product in accordance with this Document, with integral parts and attachment devices. Coordinate sample submittals for interfacing work.

1.7.2. Where specific colors or patterns are not indicated, provide materials and products specified in the full range of color, texture and pattern for selection by City. Range shall include standard stocked color/texture/pattern, standard color/texture/pattern not stocked, but available from manufacturer, and special color/ texture/pattern available from manufacturer as advertised in product data and brochures. Unless otherwise indicated in individual specification sections, City may select from any range at no additional cost to City.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SUBMITTALS 01 33 00 - 6

1.7.3. Include identification on each sample, with full Project information.

1.7.4. Submit the number of samples that Contractor requires, plus one that will be retained by Landscape Architect and one by City.

1.7.5. Reviewed samples which may be used in the Work are indicated in individual specification Sections.

1.8. MANUFACTURERS’ INSTRUCTIONS

1.8.1. When specified in individual specification Sections, submit manufacturers' printed instructions for delivery, storage, assembly, installation, start-up, adjusting, and finishing, in quantities specified for Product Data.

1.8.2. Identify conflicts between manufacturers' instructions and Contract Documents.

1.9. MANUFACTURERS’ CERTIFICATES

1.9.1. When specified in individual specification Sections, submit manufacturers' certificates to Landscape Architect for review, in quantities specified for Product Data.

1.9.2. Indicate material or Product conforms to or exceeds specified requirements. Submit supporting reference date, affidavits, and certifications as appropriate.

1.9.3. Certificates may be recent or previous test results on material or Product, but must be acceptable to City.

1.10. MOCK-UP

1.10.1. Where indicated, provide mock-ups as required. Mock-ups shall be prepared per the specifications and shall accurately and reasonably represent the quality of construction the Contractor will provide. If the mock-up or portions thereof do not adequately represent the quality of the work specified, the Contractor shall modify the mock-up as needed.

1.10.2. Once completed to the City’s satisfaction, the mock-up shall serve as the standard of quality for the work.

1.10.3. All mock-ups, at City’s option, shall remain the property of the City. If not required by the City, Contractor shall remove and dispose of the mock-up.

1.10.4. Where indicated, on-site mock-ups, if accepted, may be integrated into the Work.

1.11. LANDSCAPE ARCHITECT'S REVIEW OF SUBMITTALS

1.11.1. Landscape Architect will review and respond to the submittals within a reasonable time period (typically 10 working days, 15 working days requiring review from multiple consultants) from the date of submission of a complete submittal.

1.11.2. Submittals will be reviewed and stamped by the Landscape Architect "No exceptions taken," "Submit specified item" or "Make corrections noted" to indicate full or

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SUBMITTALS 01 33 00 - 7
conditioned approval or "Revise and resubmit" or "Rejected" to indicate disapproval.

Terms are defined as follows:

1.11.2.1. No Exceptions Taken: Accepted subject to its compatibility with future submittals and additional partial submittals for portions of the work not covered in this submittal. Does not constitute approval or deletion of specified or required items not shown in the partial submittal.

1.11.2.2. Submit specified item: Submit to the Landscape Architect the items indicated for review.

1.11.2.3. Correct as noted: Same as 1., except that minor corrections as noted shall be made by the Contractor. No resubmittal required.

1.11.2.4. Revise and resubmit: Rejected because of major inconsistencies or errors which shall be resolved or corrected by the Contractor prior to subsequent review by the Landscape Architect.

1.11.2.5. Rejected: Submitted material does not conform to plans and specifications in major respect. For example, wrong size, model, capacity or material.

Resubmit.

1.11.2.6. Receipt Acknowledged. Received, recorded and distributed without further action.

1.11.3. Submittals reviewed by the Landscape Architect which have been stamped shall be deemed to have the following language affixed and made a part thereof, regardless of the initial or subsequent readability of the actual stamp.

1.11.3.1. Corrections or comments made on submittals during this review do not relieve the contractor from compliance with the requirements of the drawings and specifications. This check is for review of general conformance with the design concept of the project and general compliance with information given in the Contract Documents. The contractor is responsible for confirming and correlating all quantities and dimensions, selection of fabrication processes and techniques of construction, coordinating the work of the trades; and performing the work in a safe and satisfactory manner.

1.11.4. Landscape Architect’s review of submittals shall be completed within ten working days of the date of submission. Any requests by Landscape Architect for additional time shall not be unreasonably withheld.

1.11.5. Landscape Architect's review of submittals has, as a primary objective, to assist in the completion of the project on time and in conformance with the Contract requirements by permitting review of material and fabricated items prior to ordering. Landscape Architect's review of submittals is based only on the data presented and extends only to conformance with general design intent and information contained in the Contract Documents.

1.11.6. Landscape Architect's approval of submittals does not constitute final acceptance or unqualified approval of items or work proposed or put in place, nor does it constitute

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SUBMITTALS 01 33 00 - 8
acceptance of responsibility for the accuracy, coordination or completeness of submittals. Landscape Architect's approval of submittals does not relieve the Contractor from the responsibility for errors, omissions, or compliance with all the requirements of the Contract Documents.

1.11.7. Reimbursement of the Landscape Architect's costs for review:

1.11.7.1. Landscape Architect will record all time and expenses incurred to review submittals requiring more than two reviews.

1.11.7.2. Contractor shall reimburse the City through deduction from amounts due the Contractor upon receipt of the Landscape Architect's billing and that of the Landscape Architect's consultants at standard billing rates for all time and expenses incurred in unanticipated reviews.

1.11.8. Landscape Architect's review of submittals does not change the Contract in any manner.

1.12. RESUBMITTAL

1.12.1. Make all corrections or revisions required by reviewer's comments at Contractor’s expense and resubmit as initially specified above. No additional costs will be authorized for corrections or revisions.

1.12.2. Product data and shop drawings:

1.12.2.1. Revise initial drawings or data and resubmit as initially specified.

1.12.2.2. Indicate changes which have been made other than those requested by reviewer.

1.12.3. Submit new samples as initially specified.

1.13. DISTRIBUTION

1.13.1. Distribute only submittals with Landscape Architect/Engineer stamps of review.

Contractor is responsible for coordination of submittals and comments following review. Contractor to provide all additional reproduction costs for copies required by the Contractor at its expense. No additional costs will be authorized for Contractor costs pertaining to submittals.

1.14. DEFERRED PERMIT APPROVAL REQUIREMENTS

1.14.1. Installation of deferred permit approval items shall not be started until detailed plans, specifications, and engineering calculations have been accepted and signed by the Landscape Architect or Engineer in general responsible charge of design and signed by a California registered Landscape Architect or professional engineer who has been delegated responsibility covering the work shown on a particular plan or specification and approved by the agency having authority (e.g., State Fire Marshall, local jurisdiction having authority, gas company, electrical utility company, water City, etc.).

Deferred permit approval items for this Project are as indicated in the Summary of Work, the Plans, and/or the Specifications.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SUBMITTALS 01 33 00 - 9

1.14.2. Unless otherwise indicated in the Contract Documents or if City provides written approval of a longer time period, Contractor shall submit all deferred permit approval items for approval within thirty (30) days of the notice to proceed with the Construction Phase.

1.14.3. Deferred permit approval drawings and specifications become part of the approved documents for the Project when they are submitted to and approved by the City.

1.14.4. Contractor is responsible for coordinating the review and approval of all deferred permit approval items.

1.14.5. Submit documents to Landscape Architect for review.

1.14.6. Documents shall bear the stamp and signature of the design architect and/or engineer licensed in the State of California who is responsible for the work shown on the documents.

1.14.7. Landscape Architect and its subconsultants will review the documents only for conformance with design concept shown on the documents. The contractor will then forward the Submittal to agency having authority for approval.

1.14.8. Contractor shall respond to review comments made by the agency having authority for approval and revise and resubmit submittal to the Landscape Architect for resubmittal to the agency having authority for approval.

1.14.9. Contractor is notified that significant lead time is required for deferred approval review by the agency having authority for approval and shall schedule work accordingly. No extension of Contract Time will be allowed for delays incurred by deferred approval review. The Landscape Architect is not responsible for delays by the agency having authority for approval in deferred approval review.

END OF SECTION

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
QUALITY REQUIREMENTS 01 40 00 - 1
SECTION 01 40 00

QUALITY REQUIREMENTS

1. GENERAL

1.1. RELATED DOCUMENTS AND PROVISIONS
Contractor shall review all Contract Documents for applicable provisions related to the provisions in this document, including without limitation:

1.1.1. General Conditions;

1.1.2. Supplementary Conditions (if any);

1.1.3. Drawings;

1.1.4. Construction Schedule – Network Analysis; and

1.1.5. General Definitions and References.

1.2. SUMMARY

1.2.1. This Document includes administrative and procedural requirements for quality assurance and quality control.

1.2.2. Testing and inspecting services by the City are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility for compliance with the Contract Documents’ requirements.

1.2.2.1. Specific quality-assurance and -control requirements for individual construction activities are specified in the Specifications for those activities. Requirements in those Specifications may also cover production of standard products.

1.2.2.2. Specified tests, inspections, and related actions do not limit Contractor's other quality-assurance and -control procedures that facilitate compliance with the Contract Documents’ requirements.

1.2.2.3. Requirements for Contractor to provide quality-assurance and -control services required by City, City’s consultants, or authorities having jurisdiction are not limited by provisions of this Document.

1.3. DEFINITIONS

1.3.1. Quality-Assurance Services: Activities, actions, and procedures performed before and during execution of the Work to guard against defects and deficiencies and substantiate that proposed construction will comply with requirements.

1.3.2. Quality-Control Services: Tests, inspections, procedures, and related actions during and after execution of the Work to evaluate that actual products incorporated into the Work and completed construction comply with requirements. Services do not include contract enforcement activities performed by City or its consultants.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
QUALITY REQUIREMENTS 01 40 00 - 2

1.3.3. Mock-ups: Full-size, physical assemblies that are constructed on-site. Mock-ups are used to verify selections made under sample submittals, to demonstrate aesthetic effects and, where indicated, qualities of materials and execution, and to review construction, coordination, testing, or operation; they are not Samples. Approved mock-ups establish the standard by which the Work will be judged.

1.3.4. Laboratory Mock-ups: Full-size, physical assemblies that are constructed at testing facility to verify performance characteristics.

1.3.5. Preconstruction Testing: Tests and inspections that are performed specifically for the Project before products and materials are incorporated into the Work to verify performance or compliance with specified criteria.

1.3.6. Product Testing: Tests and inspections that are performed by an NRTL (National Recognized Testing Laboratory), an NVLAP (National Voluntary Laboratory Accreditation Program), or a testing agency qualified to conduct product testing and acceptable to authorities having jurisdiction, to establish product performance and compliance with industry standards.

1.3.7. Source Quality-Control Testing: Tests and inspections that are performed at the source, i.e., plant, mill, factory, or shop.

1.3.8. Field Quality-Control Testing: Tests and inspections that are performed on-site for installation of the Work and for completed Work.

1.4. CONFLICTING REQUIREMENTS

1.4.1. General: If compliance with two or more standards is specified and the standards establish different or conflicting requirements for minimum quantities or quality levels, comply with the most stringent requirement. Refer uncertainties and requirements that are different but apparently equal, to City for a decision before proceeding.

1.4.2. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits. To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of requirements. Refer uncertainties to City for a decision before proceeding.

1.5. SUBMITTALS

1.5.1. Qualification Data: For testing agencies specified in "Quality Assurance" below to demonstrate their capabilities and experience. Include proof of qualifications in the form of a recent report on the inspection of the testing agency by a recognized authority.

1.5.2. Schedule of Tests and Inspections

1.5.3. Reports: Prepare and submit certified written reports

1.5.3.1. Descriptions of deficiencies noted, and corrective action undertaken to resolve such deficiencies.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
QUALITY REQUIREMENTS 01 40 00 - 3

1.5.3.1.1. Deficiencies observed shall immediately be brought to the attention of the Contractor’s field superintendent, and trade foreman. In the event deficiencies are not corrected, or if an interpretation of the Contract Documents is required, the Testing Agency shall immediately notify the City and
applicable consultant, Landscape Architect, or Engineer.

1.5.3.1.2. The Testing Agency shall maintain a deficiency list of all items not corrected and shall reinspect the area after the deficiency has been corrected. The list shall include a description of the deficiency, the date and time the deficiency was observed, who was notified, the date of reinspection and description of any corrective action taken. Distribute the deficiency list at least once per month.

1.5.3.1.3. At the end of the Project, the Testing Agency shall submit a final signed report stating whether the work tested and inspected conforms to the Contract Documents’
requirements.

1.5.4. Permits, Licenses, and Certificates: For City's records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents established for compliance with standards and regulations bearing on performance of the Work.

1.6. QUALITY ASSURANCE

1.6.1. General: Qualifications paragraphs in this Article establish the minimum qualification levels required; individual Specifications specify additional requirements.

1.6.2. Installer Qualifications: A firm or individual experienced in installing, erecting, or assembling work similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful in-service performance. Where required by the individual Specifications, Installer employing workers trained and approved by manufacturer, Installer being acceptable to manufacturer, and/or Installer being an authorized representative of manufacturer for both installation and maintenance.

1.6.3. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.

1.6.4. Fabricator Qualifications: A firm experienced in producing products similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.

1.6.5. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in the State of California, and who is experienced in providing engineering services of the kind indicated.

1.6.6. Engineering services are defined as those performed for installations of the system, assembly, or products that are similar to those indicated for this Project in material, design, and extent.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
QUALITY REQUIREMENTS 01 40 00 - 4

1.6.7. Specialists: Certain Specifications may require that specific construction activities shall be performed by entities who are recognized experts in those operations. Specialists shall satisfy qualification requirements indicated and shall be engaged for the activities indicated.

1.6.7.1. Requirement for specialists shall not supersede building codes or regulations governing the Work.

1.6.8. Testing Agency Qualifications: An NRTL, an NVLAP, Division of the State of Landscape Architect’s Accepted Laboratory, or an independent agency with the experience and capability to conduct testing and inspecting indicated; and with additional qualifications stated in individual Specifications; and where required by and acceptable to authorities having jurisdiction.

1.6.8.1. NRTL: A Nationally Recognized Testing Laboratory according to 29 CFR 1910.7.

1.6.8.2. NVLAP: A testing agency accredited according to NIST's (National Institute of Standards and Technology) National Voluntary Laboratory Accreditation Program.

1.6.8.3. Tests shall be made by an accredited testing agency with a minimum of 5 years of experience in the specific type of testing to be performed. Except as otherwise provided, sampling and testing of all materials and the laboratory methods and testing equipment shall be in accordance with the applicable standards and methods of the California Building Standards code.

1.6.8.4. For each type of inspection and testing service to be performed, the Testing Agency shall submit certification, signed and sealed by the Agency's professional engineer, of compliance with all applicable requirements of the following:

1.6.8.4.1. ASTM E329, "Specification for Agencies Engaged in the Testing and/or Inspection of Materials Used in Construction."

1.6.8.4.2. "Recommended Requirements for Independent Laboratory Qualifications" published by the American Council of
Independent Laboratories.

1.6.8.5. Furnish written certification to the City that all equipment to be used has been calibrated in accordance with applicable ASTM standards within the last year and is in proper working order.

1.6.8.6. Testing Agency Personnel Qualifications: Testing and inspection services shall be performed only by trained and experienced technicians currently qualified for the work they are to perform. Documentation of such training and experience shall be submitted to the City and/or its consultants upon request.

1.6.8.7. Each independent inspection and testing agency engaged on the Project shall be authorized by authorities having jurisdiction to operate in the state where the Project is located.

1.6.8.8. Factory-Authorized Service Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
QUALITY REQUIREMENTS 01 40 00 - 5
to inspect installation of manufacturer's products that are similar in material, design, and extent to those indicated for this Project.

1.6.9. Preconstruction Testing: Where a testing agency is indicated to perform preconstruction testing for compliance with specified requirements for performance and test methods, comply with the following:

1.6.9.1. Contractor responsibilities include the following:

1.6.9.1.1. Verify by its Quality Assurance/Quality Control procedures that an element is ready for testing prior to requesting a test.

1.6.9.1.2. Provide test specimens representative of proposed products and construction.

1.6.9.1.3. Submit specimens in a timely manner with sufficient time for testing and analyzing results to prevent delaying the Work.

1.6.9.1.4. Provide sizes and configurations of test assemblies, mockups, and laboratory mock-ups to adequately demonstrate capability of products to comply with performance
requirements.

1.6.9.1.5. Build site-assembled test assemblies and mock-ups using installers who will perform same tasks for Project.

1.6.9.1.6. Build laboratory mock-ups at testing facility using personnel, products, and methods of construction indicated for the completed Work.

1.6.9.1.7. When testing is complete, remove test specimens, assemblies, mock-ups, and laboratory mock-ups; do not reuse products on Project.

1.6.9.2. Testing Agency Responsibilities: Submit a certified written report of each test, inspection, and similar quality-assurance service to City with copy to Contractor. Interpret tests and inspections and state in each report whether tested and inspected Work complies with or deviates from the Contract Documents’ requirements.

1.6.10. Mock-ups: Before installing portions of the Work requiring mock-ups, build mock-ups for each form of construction and finish required to comply with the following requirements, using materials indicated for the completed Work:

1.6.10.1.Build mock-ups in location and of size indicated or, if not indicated, as directed by City or its consultant.

1.6.10.2.Notify City and its consultants seven (7) days in advance of dates and times when mock-ups will be constructed.

1.6.10.3.Demonstrate the proposed range of aesthetic effects and workmanship.

1.6.10.4.Obtain City and its consultant's approval of mock-ups before starting work, fabrication, or construction.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
QUALITY REQUIREMENTS 01 40 00 - 6

1.6.10.4.1. Allow seven (7) days for initial review and each re-review of each mock-up.

1.6.10.5.Incorporate seismic design of nonstructural components as listed in Division 01 Document “Seismic Design Requirements for Non-Structural Components” into mock-ups.

1.6.10.6.Maintain mock-ups during construction in an undisturbed condition as a standard for judging the completed Work.

1.6.10.7.Demolish and remove mock-ups when directed, unless otherwise indicated.

1.6.11. Laboratory Mock-Ups: Comply with requirements of preconstruction testing and those specified in individual Specifications in Divisions 02 through 49.

1.7. QUALITY CONTROL

1.7.1. City Responsibilities: Where quality-control services are indicated as City's responsibility, City will engage a qualified testing agency to perform these services.

1.7.1.1. City will furnish Contractor with names, addresses, and telephone numbers of testing agencies engaged and a description of types of testing and inspecting the testing agencies are engaged to perform.

1.7.1.2. Costs for retesting and reinspecting construction that replaces or is necessitated by Work that failed to comply with the Contract Documents will be charged to Contractor, and the Guaranteed Maximum Price will be adjusted by Change Order per the Contract Documents.

1.7.2. Tests and inspections not explicitly assigned to City are Contractor’s responsibility.

Unless otherwise indicated, provide quality-control services specified and those required by authorities having jurisdiction. Perform quality-control services required of Contractor by authorities having jurisdiction, whether specified or not.

1.7.2.1. Where services are indicated as Contractor’s responsibility, engage a qualified testing agency to perform the quality-control services.

1.7.2.1.1. Contractor shall not employ same entity engaged by City, unless agreed to in writing by City.

1.7.2.2. Notify testing agencies at least 72 hours in advance of time when Work that requires testing or inspecting will be performed.

1.7.2.3. Where quality-control services are indicated as Contractor’s responsibility, submit a certified written report, in duplicate, of each quality-control service.

1.7.2.4. Testing and inspecting requested by Contractor and not required by the Contract Documents are Contractor’s responsibility.

1.7.2.5. Submit additional copies of each written report directly to authorities having jurisdiction, when they so direct.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
QUALITY REQUIREMENTS 01 40 00 - 7

1.7.3. Manufacturer's Field Services: Where indicated, engage a factory-authorized service representative to inspect field-assembled components and equipment installation, including service connections. Report results in writing as specified in Document “Submittal Procedures.”

1.7.4. Retesting/Reinspecting: Regardless of whether original tests or inspections were Contractor's responsibility, provide quality-control services, including retesting and reinspecting, for construction that replaced Work that failed to comply with the Contract Documents’ requirements.

1.7.5. Testing Agency Responsibilities: Cooperate with City, City’s consultants, and Contractor in performance of duties. Provide qualified personnel to perform required tests and inspections.

1.7.5.1. Notify City, City’s consultants, and Contractor promptly of irregularities or deficiencies observed in the Work during performance of its services.

1.7.5.2. Determine the location from which test samples will be taken and in which insitu tests are conducted.

1.7.5.3. Conduct and interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from requirements.

1.7.5.4. Submit a certified written report, in duplicate, of each test, inspection, and similar quality-control service through Contractor.

1.7.5.5. Do not release, revoke, alter, or increase the Contract Documents’ requirements or approve or accept any portion of the Work.

1.7.5.6. Do not perform any duties of Contractor.

1.7.6. Associated Services: Cooperate with agencies performing required tests, inspections, and similar quality-control services, and provide reasonable auxiliary services as requested. Notify testing agency sufficiently in advance of operations to permit assignment of personnel. Provide the following:

1.7.6.1. Access to the Work.

1.7.6.2. Incidental labor and facilities necessary to facilitate tests and inspections.

1.7.6.3. Adequate quantities of representative samples of materials that require testing and inspecting. Assist agency in obtaining samples.

1.7.6.4. Facilities for storage and field curing of test samples.

1.7.6.5. Delivery of samples to testing agencies.

1.7.6.6. Preliminary design mix proposed for use for material mixes that require control by testing agency.

1.7.6.7. Security and protection for samples and for testing and inspecting equipment at Project Site.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
QUALITY REQUIREMENTS 01 40 00 - 8

1.7.6.8. Furnish tools, samples of materials, design mixes, equipment and assistance as requested.

1.7.6.9. Provide and maintain, for the sole use of the Testing Agency, adequate facilities for the safe storage and proper curing of concrete test cylinders on the project site for the first 24 hours after casting as required by ASTM C31, Method of Making and Curing Concrete Test Specimens in the Field.

1.7.6.10.Build and store masonry test prisms in a manner acceptable to the Testing Agency. Prisms to be tested shall remain at the job site until moved by Testing Agency personnel.

1.7.6.11.Notify Testing Agency at least 10 working days in advance of any qualification testing for welding required herein.

1.7.6.12.Notify Testing Agency at least 24 hours prior to expected time for operations requiring testing or inspection services.

1.7.6.13.Make arrangements with the Testing Agency and pay for additional samples and tests made for the Contractor’s convenience or for retesting of failed samples.

1.7.6.14.For deficiencies requiring corrective action, submit in writing a description of the deficiency and a proposed correction to the City. After review and approval, the proposed corrective action shall be implemented and inspected by the Testing Agency. It is Contractor’s responsibility to ascertain that the deficiency is corrected and inspected prior to the work being covered.

1.7.6.15.Retention of an independent Testing Agency by the City shall in no way relieve Contractor of responsibility for performing all work in accordance with the Contract Documents’ requirements.

1.7.7. Coordination: Coordinate sequence of activities to accommodate required qualityassurance and -control services with a minimum of delay and to avoid necessity of removing and replacing construction to accommodate testing and inspecting.

1.7.7.1. Schedule times for tests, inspections, obtaining samples, and similar activities.

1.8. TESTS AND SPECIAL INSPECTIONS

1.8.1. Special Tests and Inspections: Conducted by a qualified testing agency as required by authorities having jurisdiction, as indicated in individual Specifications, and as follows:

1.8.1.1. Verifying that manufacturer maintains detailed fabrication and quality-control procedures and reviewing the completeness and adequacy of those procedures to perform the Work.

1.8.1.2. Notifying City, City’s consultants, and Contractor promptly of irregularities and deficiencies observed in the Work during performance of its services.

1.8.1.3. Submitting a certified written report of each test, inspection, and similar quality-control service to City, with copy to Contractor and to authorities having jurisdiction.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
QUALITY REQUIREMENTS 01 40 00 - 9

1.8.1.4. Submitting a final report of special tests and inspections at Project Completion, which includes a list of unresolved deficiencies.

1.8.1.5. Interpreting tests and inspections and stating in each report whether tested and inspected Work complies with or deviates from the Contract Documents.

1.8.1.6. Retesting and reinspecting corrected work.

2. PRODUCTS

2.1. GENERAL

2.1.1. Do not use any materials or equipment represented by samples until tests, if required, have been made and the materials or equipment found to be acceptable. Any product which becomes unfit for use after acceptance shall not be incorporated into the Work.

3. EXECUTION

3.1. TEST AND INSPECTION LOG

3.1.1. Prepare a record of tests and inspections.

3.1.2. Maintain log at Project Site. Post changes and modifications as they occur. Provide access to test and inspection log for City’s reference during normal working hours.

3.2. REPAIR AND PROTECTION

3.2.1. General: On completion of testing, inspecting, sample taking, and similar services, repair damaged construction and restore substrates and finishes.

3.2.1.1. Provide materials and comply with installation requirements specified in other Specifications. Restore patched areas and extend restoration into adjoining areas with durable seams that are as invisible as possible.

3.2.1.2. Comply with Document "Cutting and Patching" and all related Contract Documents’ requirements.

3.2.2. Protect construction exposed by or for quality-control service activities.

3.2.3. Repair and protection are Contractor’s responsibility, regardless of the assignment of responsibility for quality-control services.

END OF SECTION

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
ABBREVIATIONS AND ACRONYMS 01 42 13 - 1
SECTION 01 42 13

ABBREVIATIONS AND ACRONYMS

1. GENERAL

1.1. RELATED DOCUMENTS AND PROVISIONS
Contractor shall review all Contract Documents for applicable provisions related to the provisions in this document, including without limitation:

1.1.1. General Conditions including without limitation, Contract Terms and Definitions; and

1.1.2. Supplementary Conditions (if any).

1.2. ABBREVIATIONS AND ACRONYMS FOR STANDARDS AND REGULATIONS

1.2.1. Abbreviations and Acronyms for Standards and Regulations: Where abbreviations and acronyms are used in Specifications or other Contract Documents, they shall mean the recognized name of the standards and regulations as indicated in Thomson Gale™ (www.gale.com), Gale Research's “Encyclopedia of Associations” or “Encyclopedia of Associations: National Organizations of the U.S,” or in Columbia Books' “National Trade & Professional Associations of the U.S.”

1.2.2. Some of the applicable abbreviations and acronyms referenced in the Specifications or other Contract Documents have the following meanings, subject to updates or revisions based on the above-referenced publications:
• AA: Aluminum Association
• AAMA: Landscape Architectural Aluminum Manufacturers Association • AASHTO: American Association of State Highway and Transportation Officials
• ABPA: Acoustical and Board Products Association
• ACI: American Concrete Institute
• AGA: American Gas Association
• AGC: Associated General Contractors
• AHC: Landscape Architectural Hardware Consultant
• AI: Asphalt Institute
• AIA: American Institute of Landscape Architects
• AIEE: American Institute of Electrical Engineers
• AISC: American Institute of Steel Construction
• AISI: American Iron and Steel Institute
• AMCA: Air Moving and Conditioning Association
• ANSI: American National Standards Institute
• APA: American Plywood Association
• ARI: Air Conditioning and Refrigeration Institute
• ASHRAE: American Society of Heating, Refrigeration and Air Conditioning Engineers
• ASME: American Society of Mechanical Engineers
• ASSE: American Society of Structural Engineers
• ASTM: American Society of Testing and Materials
• AWPB: American Wood Preservers Bureau
• AWPI: American Wood preservers Institute

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
ABBREVIATIONS AND ACRONYMS 01 42 13 - 2
• AWS: American Welding Society
• AWSC: American Welding Society Code
• AWI: Landscape Architectural Woodwork Institute
• AWWA: American Water Works Association
• BIA: Brick Institute of America
• CCR: California Code of Regulations
• CLFMI: Chain Link Fence Manufacturers Institute
• CMG: California Masonry Guild
• CRA: California Redwood Association
• CRSI: Concrete Reinforcing Steel Institute
• CS: Commercial Standards
• CSI: Construction Specifications Institute
• CTI: Cooling Tower Institute
• FGMA: Flat Glass Manufacturer’s Association
• FIA: Factory Insurance Association
• FM: Factory Mutual
• FS: Federal Specification
• FTI: Facing Title Institute
• GA: Gypsum Association
• ICC: International Code Council
• IEEE: Institute of Electrical and Electronic Engineers • IES: Illumination Engineering Society
• LIA: Lead Industries Association
• MIA: Marble Institute of America
• MLMA: Metal Lath Manufacturers Association
• MS: Military Specifications
• NAAMM: National Association of Landscape Architectural Metal Manufacturers
• NBHA: National Builders Hardware Association
• NBFU: National Board of Fire Underwriters
• NBS: National Bureau of Standards
• NCMA: National Concrete Masonry Association
• NEC: National Electrical Code
• NEMA: National Electrical Manufacturers Association
• NFPA: National Fire Protection Association/National Forest Products Association
• NMWIA: National Mineral Wool Insulation Association
• NTMA: National Terrazzo and Mosaic Association
• NWMA: National Woodwork Manufacturer’s Association
• ORS: Office of Regulatory Services (California)
• OSHA: Occupational Safety and Health Act
• PCI: Precast Concrete Institute
• PCA: Portland Cement Association
• PDCA: Painting and Decorating Contractors of America
• PDI: Plumbing Drainage Institute
• PEI: Porcelain Enamel Institute
• PG&E: Pacific Gas & Electric Company
• PS: Product Standards
• SDI: Steel Door Institute; Steel Deck Institute
• SJI: Steel Joist Institute
• SSPC: Steel Structures Painting Council
• TCA: Tile Council of America

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
ABBREVIATIONS AND ACRONYMS 01 42 13 - 3
• TPI: Truss Plate Institute
• UBC: Uniform Building Code
• UL: Underwriters Laboratories Code
• UMC: Uniform Mechanical Code
• USDA: United States Department of Agriculture
• VI: Vermiculite Institute
• WCLA: West Coast Lumberman’s Association
• WCLB: West Coast Lumber Bureau
• WEUSER: Western Electric Utilities Service Engineering Requirements • WIC: Woodwork Institute of California
• WPOA: Western Plumbing Officials Association

1.2.3. Additional Abbreviations and Symbols: Refer to the above-referenced publications or to Drawings for additional abbreviations and for symbols.

END OF SECTION

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
GENERAL DEFINITIONS AND REFERENCES 01 42 16 - 1
SECTION 01 42 16

GENERAL DEFINITIONS AND REFERENCES

1. GENERAL

1.1. RELATED DOCUMENTS AND PROVISION
Contractor shall review all Contract Documents for applicable provisions related to the provisions in this document, including without limitation:

1.1.1. General Conditions including without limitation, Contract Terms and Definitions; and

1.1.2. Supplementary Conditions (if any).

1.2. DEFINITIONS
General: Basic Contract definitions are included in the General Conditions of the Contract for Construction. The following are in addition to those definitions.

1.2.1. “Alternate”: A cost or credit for certain Work that may be added to or deducted from the Project.

1.2.2. “Indicated”: Requirements expressed by graphic representations or in written form on Drawings, in Specifications, and in other Contract Documents. Other terms including “shown,” “noted,” “scheduled,” and “specified” have the same meaning as “indicated.”

1.2.3. “Regulations”: Laws, ordinances, statutes, and lawful orders issued by authorities having jurisdiction, and rules, conventions, and agreements within the construction industry that control performance of the Work.

1.2.4. “Furnish”: Supply and deliver to Project site, ready for unloading, unpacking, assembly, installation, and similar operations.

1.2.5. “Install”: Operations at Project site including unloading, temporarily storing, unpacking, assembling, erecting, placing, anchoring, applying, working to dimension, finishing, curing, protecting, cleaning, and similar operations.

1.2.6. “Provide”: Furnish and install, complete and ready for the intended use.

1.3. QUALITY ASSURANCE

1.3.1. For products or workmanship specified by association, trade, or Federal Standards, Contractor shall comply with requirements of the standard, except when more stringent requirements are specified in the Contract Documents, or are required by applicable codes.

1.3.2. Contractor shall conform to current reference standard publication in effect on the date of bid opening.

1.3.3. Unless directed otherwise by the Contract Documents, Contractor shall obtain copies of referenced standards.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
GENERAL DEFINITIONS AND REFERENCES 01 42 16 - 2

1.3.4. Unless directed otherwise by the Contract Documents, Contractor shall maintain a copy of referenced standards at jobsite until Completion.

1.3.5. If specified standards conflict with Contract Documents, Contractor shall request clarification from the City or the Landscape Architect before proceeding.

1.3.6. Governing Codes shall be as shown in the Contract Documents including, without limitation, the Specifications.

1.4. STANDARDS

1.4.1. Standard Specifications: References to codes, specifications and standards referred to in the Contract Documents shall mean, and are intended to be, the latest edition, amendment or revision of such reference standard in effect as of the date of these Contract Documents. If those standard specifications are revised prior to Completion of any part of the Work to which such revision would pertain, Contractor may, if acceptable to and approved by the City, perform such Work in accordance with the revised standard specifications.

1.4.2. Conflicting Requirements: Where compliance with two or more standards is specified, and the standards may establish different or conflicting requirements for minimum quantities or quality levels, refer requirements that are different, but apparently equal, and uncertainties to the City for a decision before proceeding.

1.4.3. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits. To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of the requirements. Refer uncertainties to City for a decision before proceeding.

1.4.4. Copies of Standards: Each entity engaged in construction on the Project is required to be familiar with industry standards applicable to that entity's construction activity. Copies of applicable standards are not bound with the Contract Documents.

1.4.5. Copies from the Publication Source: Where copies of standards are needed for performance of a required construction activity, Contractor shall obtain copies directly from the publication source.

1.5. SCHEDULE OF REFERENCES
The following information is intended only for the general assistance of Contractor. City does not represent the accuracy of the information. Contractor shall independently verify the information for all entities listed below:

AA Aluminum Association 202/862-5100
900 19th Street NW, Suite 300
Washington, DC 20006
www.aluminum.org
AAMA American Landscape Architectural Manufacturers Association 847/303-5664 1827 Walden Office Sq., Suite 104
Schaumburg, IL 60173-4268
www.aamanet.org

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
GENERAL DEFINITIONS AND REFERENCES 01 42 16 - 3
AASHTO American Association of State Highway and 202/624-5800 Transportation Officials
444 North Capitol Street, Suite 249
Washington, DC 20001
www.aashto.org
ACI American Concrete Institute 248/848-3700
P.O. Box 9094
Farmington Hills, MI 48333-9094
www.aci-int.org
ACPA American Concrete Pipe Association 972/506-7216
222 West Las Colinas Blvd., Suite 641
Irving, TX 75039-5423
www.concrete-pipe.org
AFPA American Forest and Paper Association 202/463-2700 1111 19th St., NW, Suite 800
Washington, DC 20036
http://www.afandpa.org/
AGA American Gas Association 703/841-8400
1515 Wilson Blvd.

Arlington VA 22209
www.aga.com
AI Asphalt Institute 606/288-4960
Research Park Drive
P.O. Box 14052
Lexington, KY 40512-4052
www.asphaltinstitute.org
AIA The American Institute of Landscape Architects 202/626-7300 1735 New York Avenue, NW
Washington, DC 20006-5292
www.aia.org
AISC American Institute of Steel Construction 800/644-2400 One East Wacker Drive, Suite 3100
Chicago, IL 60601-2001
http://www.aisc.org/
AITC American Institute of Timber Construction 303/792-9559 7012 S. Revere Pkwy., Suite 140
Englewood, CO 80112
www.aitc-glulam.org
ALCA Associated Landscape Contractors of America 703/620-6363 12200 Sunrise Valley Drive, Suite 150
Reston, VA 20191
www.alca.org

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
GENERAL DEFINITIONS AND REFERENCES 01 42 16 - 4
ALSC American Lumber Standards Committee 301/972-1700
P.O. Box 210
Germantown, MD 20875
ANLA American Nursery and Landscape Association 202/789-2900 1250 Eye Street, NW, Suite 500
Washington, DC 20005
ANSI American National Standards Institute 212/642-4900 11 West 42nd Street, 13th Floor
New York, NY 10036-8002
www.ansi.org
APA APA-The Engineered Wood Association 206/565-6600
P.O. Box 11700
Tacoma, WA 98411-0700
www.apawood.org
APA Landscape Architectural Precast Association 941/454-6989 P.O. Box 08669
Fort Myers, FL 33908-0669
ARMA Asphalt Roofing Manufacturers Association 301/231-9050 Center Park
4041 Powder Mill Road, Suite 404
Calverton, MD 20705
ASA Acoustical Society of America 516/576-2360
500 Sunnyside Blvd.

Woodbury, NY 11797
ASCE American Society of Civil Engineers- 800/548-2723
World Headquarters 703/295-6000
1801 Alexander Bell Drive
Reston, VA 20190-4400
www.asce.org
ASHRAE American Society of Heating, Refrigerating and 800/527-4723 Air Conditioning Engineers 404/636-8400
1791 Tullie Circle, NE
Atlanta, GA 30329-2305
www.ashrae.org
ASLA American Society of Landscape Architects 202/686-2752 4401 Connecticut Ave., NW, 5th Floor
Washington, DC 20008-2369
www.asla.org
ASME American Society of Mechanical Engineers 800/434-2763 345 East 47th Street
New York, NY 10017-2392
www.asme.org

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
GENERAL DEFINITIONS AND REFERENCES 01 42 16 - 5
ASPE American Society of Plumbing Engineers 805/495-7120 3617 Thousand Oaks Blvd., Suite 210
Westlake, CA 91362-3649
ASQC American Society for Quality Control 800/248-1946
611 E. Wisconsin Avenue 414/272-8575
Milwaukee, WI 53201-3005
www.asqc.org
ASSE American Society of Sanitary Engineering 216/835-3040 28901 Clemens Road
Westlake, OH 44145
www.asse-plumbing.org
ASTM American Society for Testing and Materials 610/832-9500 100 Barr Harbor Drive
West Conshohocken, PA 19428-2959
www.astm.org
AWPA American Wood-Preservers' Association 817/326-6300 3246 Fall Creek Highway, Suite 1900
Granbury, TX 76049-7979
AWS American Welding Society 800/443-9373
550 NW LeJeune Road 305/443-9353
Miami, FL 33126
www.amweld.org
BHMA Builders' Hardware Manufacturers Association 212/661-4261 355 Lexington Avenue, 17th Floor
New York, NY 10017-6603
CISPI Cast Iron Soil Pipe Institute 423/892-0137
5959 Shallowford Road, Suite 419
Chattanooga, TN 37421
CPSC Consumer Product Safety Commission 800/638-2772
East West Towers
4330 East-West Hwy.

Bethesda, MD 20814
CPPA Corrugated Polyethylene Pipe Association 800/510-2772 432 N. Superior Street 419/241-2221
Toledo, OH 43604
CRA California Redwood Association 415/382-0662
405 Enfrente Drive, Suite 200
Novato, CA 94949
CRSI Concrete Reinforcing Steel Institute 847/517-1200
933 N. Plum Grove Road
Schaumburg, IL 60173-4758
www.crsi.org

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
GENERAL DEFINITIONS AND REFERENCES 01 42 16 - 6
CTI Ceramic Tile Institute of America 310/574-7800
12061 W. Jefferson Blvd.

Culver City, CA 90230-6219
DHI Door and Hardware Institute 703/222-2010
14170 Newbrook Drive
Chantilly, VA 20151-2223
www.dhi.org
DIPRA Ductile Iron Pipe Research Association 205/988-9870 245 Riverchase Pkwy East, Suite O
Birmingham, AL 35244
DOC Department of Commerce 202/482-2000
14th Street and Constitution Avenue, NW
Washington, DC 20230
DOT Department of Transportation 202/366-4000
400 Seventh Street, SW
Washington, DC 20590
EPA Environmental Protection Agency 202/260-2090
401 M Street, SW
Washington, DC 20460
GA Gypsum Association 202/289-5440
810 First Street NE, Suite 510
Washington, DC 20002
www.usg.com
GANA Glass Association of North America 913/266-7013
3310 SW Harrison Street
Topeka, KS 66611-2279
www.glasswebsite.com/gana
HMA Hardwood Manufacturers Association 412/828-0770
400 Penn Center Blvd., Suite 530
Pittsburgh, PA 15235-5605
www.hardwood.org
HPVA Hardwood Plywood and Veneer Association 703/435-2900 1825 Michael Farraday Drive
P.O. Box 2789
Reston, VA 22195-0789
www.hpva.org
IEEE Institute of Electrical and Electronic Engineers 800/678-4333 345 E. 47th Street 212/705-7900
New York, NY 10017-2394
www.ieee.org
MCAA Mechanical Contractors Association of America 301/869-5800 1385 Piccard Drive

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
GENERAL DEFINITIONS AND REFERENCES 01 42 16 - 7
Rockville, MD 20850-4329
ML/SFA Metal Lath/Steel Framing Association 312/456-5590 (A Division of the NAAMM)
8 South Michigan Avenue, Suite 1000
Chicago, IL 60603
NAA National Arborist Association 800/733-2622
P.O. Box 1094 603/673-3311
Amherst, NH 03031-1094
www.natlarb.com
NAAMM National Association of Landscape Architectural 312/782-5590 Metal Manufacturers
8 South Michigan Avenue, Suite 1000
Chicago, IL 60603
www.gss.net/naamm
NAPA National Asphalt Pavement Association 301/731-4748 NAPA Building
5100 Forbes Blvd.

Lanham, MD 20706-4413
NCSPA National Corrugated Steel Pipe Association 202/452-1700 1255 23rd Street, NW, Suite 850
Washington, DC 20037
www.ncspa.org
NECA National Electrical Contractors Association 301/657-3110 3 Bethesda Metro Center, Suite 1100
Bethesda, MD 20814-5372
NEI National Elevator Industry 201/944-3211
185 Bridge Plaza North, Suite 310
Fort Lee, NJ 07024
NEMA National Electrical Manufacturers' Association 703/841-3200 1300 N. 17th Street, Suite 1847
Rosslyn, VA 22209
www.nema.org
NFPA National Fire Protection Association 800/344-3555
One Batterymarch Park 617/770-3000
P.O. Box 9101
Quincy, MA 02269-9101
www.nfpa.org
NHLA National Hardwood Lumber Association 901/377-1818
P.O. Box 34518
Memphis, TN 38184-0518
www.natlhardwood.org
NPA National Particleboard Association 301/670-0604
18928 Premiere Court

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
GENERAL DEFINITIONS AND REFERENCES 01 42 16 - 8
Gaithersburg, MD 20879-1569
www.pbmdf.com
NPCA National Paint and Coatings Association 202/462-6272 1500 Rhode Island Avenue, NW
Washington, DC 20005-5597
www.paint.org
NRCA National Roofing Contractors Association 800/323-9545 O'Hare International Center
10255 W. Higgins Road, Suite 600
Rosemont, IL 60018-5607
www.roofonline.org
NRMCA National Ready Mixed Concrete Association 301/587-1400 900 Spring Street
Silver Spring, MD 20910
www.nrmca.org
NWWDA National Wood Window and Door Association 800/223-2301 1400 E. Touhy Avenue, G-54 847/299-5200
Des Plaines, IL 60018
www.nwwda.org
SHA Occupational Safety and Health Administration 202/219-8148 (U.S. Department of Labor)
200 Constitution Ave., NW
Washington, DC 20210
PCA Portland Cement Association 847/966-6200
5420 Old Orchard Road
Skokie, IL 60077-1083
www.portcement.org
PDCA Painting and Decorating Contractors of 800/332-7322 America 703/359-0826
3913 Old Lee Hwy, Suite 33-B
Fairfax, VA 22030
www.pdca.com
PDI Plumbing and Drainage Institute 800/589-8956
45 Bristol Drive, Suite 101 508/230-3516
South Easton, MA 02375
RFCI Resilient Floor Covering Institute 301/340-8580
966 Hungerford Drive, Suite 12-B
Rockville, MD 20805-1714
SDI Steel Deck Institute 847/462-1930
P.O. Box 25
Fox River Grove, IL 60012
www.sdi.org
SDI Steel Door Institute 216/889-0010

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
GENERAL DEFINITIONS AND REFERENCES 01 42 16 - 9
30200 Detroit Road
Cleveland, OH 44145-1967

SMA Stucco Manufacturers Association 213/789-8733
14006 Ventura Blvd.

Sherman Oaks, CA 91403
SMACNA Sheet Metal and Airconditioning Contractors 703/803-2980 National Association, Inc.

P.O. Box 221230
Chantilly, VA 20151-1209

TPI Turfgrass Producers International 800/405-8873
1855-A Hicks Road 847/705-9898
Rolling Meadows, IL 60008
UL Underwriters Laboratories, Inc. 800/704-4050
333 Pfingston Road 847/272-8800
Northbrook, IL 60062
www.ul.com
UNI Uni-Bell PVC Pipe Association 972/243-3902
2655 Villa Creek Drive, Suite 155
Dallas, TX 75234
www.members.aol.com/unibell1
USDA U.S. Department of Agriculture 202/720-8732
14th St. and Independence Ave., SW
Washington, DC 20250

WIC Woodwork Institute of California 916/372-9943
P.O. Box 980247
West Sacramento, CA 95798-0247
WMMPA Wood Moulding & Millwork Producers 800/550-7889
Association 916/661-9591
507 First Street
Woodland, CA 95695
www.wmmpa.com
WRI Wire Reinforcement Institute 703/779-2339
203 Loudoun Street, SW
Leesburg, VA 20175-2718

END OF SECTION

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
TESTING LABORATORY SERVICES 01 45 29 - 1
SECTION 01 45 29

TESTING LABORATORY SERVICES

1. GENERAL

1.1. RELATED DOCUMENTS AND PROVISION
Contractor shall review all Contract Documents for applicable provisions related to the provisions in this document, including without limitation:

1.1.1. General Conditions, including “Tests and Inspections”; and

1.1.2. Supplementary Conditions (if any).

1.2. DOCUMENT INCLUDES

1.2.1. Observation and Supervision.

1.2.2. Testing Laboratories and Agencies

1.2.3. Tests and Inspections

1.2.4. Selection and Payment

1.2.5. City's Testing Laboratory Responsibilities

1.2.6. Laboratory reports.

1.2.7. Limits on testing laboratory authority.

1.2.8. Contractor responsibilities.

1.2.9. Schedule of inspections and tests.

1.2.10. Project Inspector, Local Authority Having Jurisdiction, Access to Site

1.3. REFERENCES

1.3.1. ASTM D3740 - Practice for Evaluation of Agencies Engaged in Testing and/or Inspection of Soil and Rock as Used in Engineering Design and Construction.

1.3.2. ASTM E329 - Recommended Practice for Inspection and Testing Agencies for Concrete, Steel, and Bituminous Materials as Used in Construction.

1.3.3. CBC - California Building Code.

1.3.4. UBC - Uniform Building Code.

1.4. OBSERVATION AND SUPERVISION

1.4.1. The City, and/or Construction Manager and Landscape Architect or their appointed representatives will review the Work and the Contractor shall provide facilities and access to the Work at all times as required to facilitate this review. Administration by

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
TESTING LABORATORY SERVICES 01 45 29 - 2
the Landscape Architect and any consulting Structural Engineer will be in accordance with applicable regulations.

1.4.2. One or more Project Inspector(s) will observe the Work.

1.4.3. Project Inspector shall have access to the Work wherever it is in preparation or progress for ascertaining that the Work is in accordance with all applicable code sections.

Contractor shall provide facilities and access as required and shall provide assistance for sampling or measuring materials.

1.4.3.1. Project Inspector will notify Construction Manager, City and Landscape Architect and inform Contractor of any observed failure of Work or material to conform to Contract Documents.

1.4.3.2. Project Inspector, if required by the local authority having jurisdiction, shall observe and monitor all testing and inspection activities required.

1.4.4. Contractor shall conform with all applicable laws as indicated in the Contract Documents. Contractor shall supervise and direct the Work and maintain a competent superintendent on the Project who is authorized to act in all matters pertaining to the Work. The Contractor shall inspect all materials, as they arrive, for compliance with the Contract Documents. Contractor shall reject defective Work or materials immediately upon delivery or failure of the Work or material to comply with the Contract Documents. The Contractor shall submit verified reports as indicated in the Contract Documents, including, without limitation, the Specifications.

1.5. TESTING LABORATORIES AND AGENCIES

1.5.1. Testing agencies and tests shall be in conformance with the Contract Documents.

1.5.2. Testing and inspection in connection with earthwork shall be under the direction of the City's consulting soils engineer ("Soils Engineer”).

1.5.3. Testing and inspection of construction materials and workmanship shall be performed by a qualified laboratory ("Testing Laboratory" or “Laboratory”). The Testing Laboratory shall be under direction of an engineer registered in the State of California, shall conform to requirements of ASTM E329, and shall be employed by or in contract with the City.

1.6. TESTS AND INSPECTIONS

1.6.1. Contractor shall be responsible for notifying Construction Manager, City and Project Inspector of all required tests and inspections. Contractor shall notify Construction Manager, City and Project Inspector forty-eight (48) hours in advance of performing any Work requiring testing or inspection.

1.6.2. Contractor shall provide access to Work to be tested and furnish incidental labor, equipment, and facilities to facilitate all inspections and tests.

1.6.3. City will pay for first inspections and tests that City and/or Landscape Architect may direct to have made, including, but not limited to, the following principal items:

1.6.3.1. Tests and observations for earthwork and pavings.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
TESTING LABORATORY SERVICES 01 45 29 - 3

1.6.3.2. Tests for concrete mix designs, including tests of trial batches.

1.6.3.3. Tests and inspections for structural steel work.

1.6.3.4. Field tests for framing lumber moisture content.

1.6.3.5. Additional tests directed by City that establish that materials and installation comply with the Contract Documents.

1.6.3.6. Test and observation of welding and expansion anchors.

1.6.3.7. Factory observation of components and assembly of modular prefabrication structures and buildings.

1.6.4. City may at its discretion, pay and back charge Contractor for:

1.6.4.1. Retests or reinspections, if required, and tests or inspection required due to Contractor error or lack of required identifications of material.

1.6.4.2. Uncovering of work in accordance with Contract Documents.

1.6.4.3. Testing done on weekends, holidays, and overtime will be chargeable to Contractor for the overtime portion.

1.6.4.4. Testing done off site.

1.6.5. Testing and inspection reports and certifications:

1.6.5.1. If initially received by Contractor, Contractor shall provide to each of the following a copy of the agency or laboratory report of each test or inspection or certification: City; Construction Manager, if any; Landscape Architect; Consulting Engineer, if any; Other Engineers on the Project, as appropriate; and; Project Inspector.

1.7. SELECTION AND PAYMENT

1.7.1. City will hire and pay for services of an independent Testing Laboratory to perform specified inspection and testing as specified by City's Testing Laboratory.

1.7.2. City’s hiring of Testing Laboratory shall in no way relieve Contractor of its obligation to perform work in accordance with requirements of Contract Documents.

1.8. CITY'S TESTING LABORATORY RESPONSIBILITIES

1.8.1. Test samples of mixes submitted by Inspector.

1.8.2. Perform specified inspection, sampling, and testing of Products in accordance with specified standards.

1.8.3. Notify Construction Manager, Landscape Architect and Contractor of observed irregularities or non-conformance of Work or Products.

1.8.4. Attend preconstruction conferences and progress meetings when requested by Landscape Architect.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
TESTING LABORATORY SERVICES 01 45 29 - 4

1.9. LABORATORY REPORTS

1.9.1. After each inspection and test, City shall then submit one copy of laboratory report to Contractor. Reports of test results of materials and inspections found not to be in compliance with the requirements of the Contract Documents shall be forwarded immediately.

1.9.2. Each Testing Laboratory shall submit a verified report covering all of the tests which were required to be made by that agency during the progress of the Project. Such report shall be furnished each time that Work is suspended, covering the tests up to that time and at the Completion of the Project, covering all tests.

1.10. LIMITS ON TESTING LABORATORY AUTHORITY

1.10.1. Laboratory may not release, revoke, alter, or enlarge on requirements of Contract Documents.

1.10.2. Laboratory may not approve or accept any portion of the Work.

1.10.3. Laboratory may not assume any duties of Contractor.

1.10.4. Laboratory has no authority to stop the Work.

1.11. CONTRACTOR RESPONSIBILITIES

1.11.1. Submit proposed items for testing as required herein and/or as further required in the Contract Documents to Landscape Architect for review in accordance with applicable specifications.

1.11.2. Cooperate with Laboratory personnel, and provide access to the Work and to manufacturer's facilities.

1.11.3. Notify Landscape Architect, City, and Testing Laboratory 48 hours prior to expected time for operations requiring inspection and testing services.

1.11.4. When tests or inspections cannot be performed after such notice, reimburse City for Laboratory personnel and travel expenses incurred due to the Contractor's negligence.

1.11.5. Contractor shall notify City a sufficient time in advance of the manufacture of material to be supplied by Contractor pursuant to the Contract Documents, which must by terms of the Contract be tested, in order that the City may arrange for the testing of same at the source of supply.

1.11.5.1.Any material shipped by the Contractor from the source of supply prior to having satisfactorily passed such testing and inspection or prior to the receipt of notice that such testing and inspection will not be required shall not be incorporated in the Work.

1.11.6. Contract and pay for services of City's Testing Laboratory to perform additional inspections, sampling and testing required when initial tests indicate Contractor's work and/or materials does not comply with Contract Documents.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
TESTING LABORATORY SERVICES 01 45 29 - 5

1.12. SCHEDULE OF INSPECTIONS AND TESTS
The Testing Laboratory shall perform tests and inspections for the following in conformance with the (CBC) California Building Code (International Building Code with State of California Amendments), California Code of Regulations, Title 24, Part 2:

1.12.1. Plumbing
Testing as specified in Division 15 including, but not limited to: Sterilization, soil waste and vent, water piping, source of water, gas piping, downspouts and storm drains.

1.12.2. Automatic Fire Sprinklers (where applicable)
Testing as specified in Division 15 shall include, but not be limited to: hydrostatic pressure.

1.12.3. Heating, Ventilating and Air Conditioning (where applicable) Testing as specified in Division 15 shall include, but not be limited to: Ductwork tests, cooling tower tests, boiler tests, controls testing, piping tests, water and air systems, and test and balance of heating and air conditioning systems.

1.12.4. Electrical
Testing as specified in Division 16, including, but not limited to: Equipment testing, all electrical system operations, grounding system and checking insulation after cable is pulled.

1.13. PROJECT INSPECTOR, LOCAL JURISDICTION HAVING AUTHORITY, ACCESS TO SITE

1.13.1. A Project Inspector with the local jurisdiction having authority will be authorized to inspect the Work.

1.13.2. City and Construction Manager shall at all times have access for the purpose of inspection to all parts of the Work and to the shops wherein the Work is in preparation, and Contractor shall at all times maintain proper facilities and provide safe access for such inspection.

1.13.3. The Work in all stages of progress shall be subject to the personal continuous observation of the Project Inspector. Project Inspector shall have free access to any or all parts of the Work at any time. Contractor shall furnish the Project Inspector reasonable facilities for obtaining such information as may be necessary to keep Inspector fully informed respecting the progress and manner of the Work and the character of the materials. Inspection of the Work shall not relieve the Contractor from any obligation set forth in the Contract Documents.

1.13.4. The Project Inspector is not authorized to change, revoke, alter, enlarge or decrease in any way any requirement of the Contract Documents, drawings, specifications or subsequent change orders.

END OF SECTION

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
TEMPORARY FACILITIES AND CONTROLS 01 50 00 - 1
SECTION 01 50 00

TEMPORARY FACILITIES AND CONTROLS

1. GENERAL

1.1. RELATED DOCUMENTS AND PROVISIONS
Contractor shall review all Contract Documents for applicable provisions related to the provisions in this document, including without limitation:

1.1.1. General Conditions;

1.1.2. Supplementary Conditions (if any);

1.1.3. Site Standards; and

1.1.4. Temporary Tree and Plant Protection.

1.2. TEMPORARY UTILITIES

1.2.1. Electric Power and Lighting:

1.2.1.1. Contractor will furnish and pay for power during the course of the work.

Contractor shall be responsible for providing temporary facilities required on the Site to point of intended use.

1.2.1.2. Contractor shall furnish, wire for, install, and maintain temporary electrical lights wherever it is necessary to provide illumination for the proper performance and/or observation of the Work: a minimum of 20 foot-candles for rough work and 50 foot-candles for finish work.

1.2.1.3. Contractor shall be responsible for maintaining existing lighting levels in the Project vicinity should temporary outages or service interruptions occur.

1.2.2. Heat and Ventilation:

1.2.2.1. Contractor shall provide temporary heat to maintain environmental conditions to facilitate progress of the Work, to meet specified minimum conditions for the installation and curing of materials, and to protect materials and finishes from damage due to improper temperature and humidity conditions. Portable heaters shall be standard units complete with controls.

1.2.2.2. Contractor shall provide forced ventilation and dehumidification, as required, of enclosed areas for proper installation and curing of materials, to disperse humidity, and to prevent hazardous accumulations of dust, fumes, vapors, and gases.

1.2.2.3. Contractor shall pay the costs of installation, maintenance, operation, and removal of temporary heat and ventilation, including costs for fuel consumed, required for the performance of the Work.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
TEMPORARY FACILITIES AND CONTROLS 01 50 00 - 2

1.2.3. Water:

1.2.3.1. Contractor will furnish and pay for water during the course of the work.

Contractor shall be responsible for providing temporary facilities required.

1.2.3.2. Contractor shall make potable water available for human consumption.

1.2.4. Sanitary Facilities:

1.2.4.1. Contractor shall provide sanitary temporary facilities in no fewer numbers than required by law and such additional facilities as may be directed by the Inspector for the use of all workers. The facilities shall be maintained in a sanitary condition at all times and shall be left at the Site until removal is directed by the City or Contractor completes all Work.

1.2.4.2. Use of toilet facilities in the Site shall not be permitted except by consent of the Project Inspector and City.

1.2.5. Telephone Service:

1.2.5.1. Contractor shall arrange with local telephone service company for telephone service for the performance of the Work. Contractor shall, at a minimum, provide in its field office one line for telephone and one line for internet.

Cellular signal is acceptable. Contractor to provide internet wifi signal at project trailer for general use by Project team while on site.

1.2.5.2. Contractor shall pay the costs for telephone and fax lines installation, maintenance, service, and removal; for Construction Site Office, Construction Manager’s Office and Inspector’s Office.

1.2.6. Fire Protection:

1.2.6.1. Contractor shall provide and maintain fire extinguishers and other equipment for fire protection. Such equipment shall be designated for use for fire protection only and shall comply with all requirements of the California Fire, State Fire Marshall and/or its designee.

1.2.6.2. Where on-site welding and burning of steel is unavoidable, Contractor shall provide protection for adjacent surfaces.

1.2.7. Trash Removal:

1.2.7.1. Contractor shall provide trash removal on a timely basis from all Site Offices and throughout the Site.

1.2.8. Temporary Facilities:

1.2.8.1. Contractor shall provide sufficient space and facilities for its own force’s needs.

1.3. CONSTRUCTION AIDS

1.3.1. Plant and Equipment:

1.3.1.1. Contractor shall furnish, operate, and maintain a complete plant for fabricating,

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
TEMPORARY FACILITIES AND CONTROLS 01 50 00 - 3
handling, conveying, installing, and erecting materials and equipment; and for conveyances for transporting workmen. Include elevators, hoists, debris chutes, and other equipment, tools, and appliances necessary for performance of the Work.

1.3.1.2. Contractor shall maintain plant and equipment in safe and efficient operating condition. Damages due to defective plant and equipment, and uses made thereof, shall be repaired by Contractor at no expense to the City.

1.3.2. No City tools or equipment shall be used by Contractor or its subcontractors for the performance of the Work.

1.4. BARRIERS AND ENCLOSURES

1.4.1. Contractor shall obtain City's written permission for locations and types of temporary barriers and enclosures, including fire-rated materials proposed for use, prior to their installation.

1.4.2. Contractor shall provide a six (6) foot high, chain link perimeter fence with posts driven into the ground and fabric screen as a temporary barrier around construction area.

Contractor shall provide and maintain temporary enclosures to prevent public entry and to protect persons using other buildings and portions of the Site and/or Premises.

Contractor shall remove temporary fence, barriers and enclosure upon Completion of the Work.

1.4.3. Contractor shall provide site access to existing facilities for persons using other buildings and portions of the Site, for the public, and for deliveries and other services and activities.

1.5. SECURITY
Contractor shall secure all construction equipment, machinery and vehicles, park and store only within fenced area, and render inoperable during non-work hours. Contractor is responsible for ensuring that no construction materials, tools, equipment, machinery or vehicles can be used for unauthorized entry or other damage or interference to activities and security of existing facilities adjacent to and in the vicinity of the Project Site.

1.6. TEMPORARY CONTROLS

1.6.1. Noise Control:

1.6.1.1. Contractor acknowledges that the project is in a residential neighborhood next to neighbor houses, and such Contractor shall take all reasonable precautions to minimize noise as required by applicable laws and the Contract Documents.

1.6.1.2. Notice of proposed noisy operations, including without limitation, operation of pneumatic demolition tools, concrete saws, and other equipment, shall be submitted to City a minimum of forty-eight (48) hours in advance of their performance.

1.6.2. Noise and Vibration:

1.6.2.1. Equipment and impact tools shall have intake and exhaust mufflers.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
TEMPORARY FACILITIES AND CONTROLS 01 50 00 - 4

1.6.2.2. Contractor shall cooperate with City to minimize and/or cease the use of noisy and vibratory equipment if that equipment becomes objectionable by its longevity.

1.6.3. Dust and Dirt:

1.6.3.1. Contractor shall conduct demolition and construction operations to minimize the generation of dust and dirt, and prevent dust and dirt from interfering with the progress of the Work and from accumulating in the Work and adjacent areas including, without limitation, occupied facilities.

1.6.3.2. Contractor shall periodically water exterior demolition and construction areas to minimize the generation of dust and dirt.

1.6.3.3. Contractor shall ensure that all hauling equipment and trucks carrying loads of soil and debris shall have their loads sprayed with water or covered with tarpaulins, and as otherwise required by local and state ordinance.

1.6.3.4. Contractor shall prevent dust and dirt from accumulating on walks, roadways, parking areas, and planting, and from washing into sewer and storm drain lines.

1.6.4. Surface and Subsurface Water:

Contractor shall not permit surface and subsurface water, and other liquids, to accumulate in or about the vicinity of the Premises. Should accumulation develop, Contractor shall control the water or other liquid, and suitably dispose of it by means of temporary pumps, piping, drainage lines, troughs, ditches, dams, or other methods.

1.6.5. Pollution:

1.6.5.1. No burning of refuse, debris, or other materials shall be permitted on or in the vicinity of the Premises.

1.6.5.2. Contractor shall comply with applicable regulatory requirements and antipollution ordinances during the conduct of the Work including, without limitation, demolition, construction, and disposal operations.

1.6.6. Lighting
If portable lights are used after dark, all light must be located so as not to direct light into neighboring property.

1.7. JOB SIGN(S)

1.7.1. General:

1.7.1.1. Contractor shall provide and maintain and locate 2 Project identification signs with the design, text, and colors designated by City and/or the Landscape Architect.

1.7.1.2. Signs other than the specified Project sign and or signs required by law, for safety, or for egress, shall not be permitted, unless otherwise approved in advance by the City.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
TEMPORARY FACILITIES AND CONTROLS 01 50 00 - 5

1.7.1.3. Contractor shall obtain the City's approval for the digital proof of the project sign within SEVEN (7) days following the date of the Notice to Award.

1.7.1.4. The approved project sign shall be installed on the project site within 48 hours after Notice to Proceed.

1.7.2. Materials:

1.7.2.1. Structure and Framing: Structurally sound, new or used wood or metal; wood shall be nominal 3/4-inch exterior grade plywood.

1.7.2.2. Sign Surface: Minimum 3/4-inch exterior grade plywood.

1.7.2.3. Rough Hardware: Galvanized.

1.7.2.4. Paint: Exterior quality, of type and colors selected by the City and/or the Landscape Architect.

1.7.3. Fabrication:

1.7.3.1. Contractor shall fabricate to provide smooth, even surface for painting.

1.7.3.2. Size: 4'-0" x 8'-0", unless otherwise indicated.

1.7.3.3. Contractor shall paint exposed surfaces of supports, framing, and surface material with exterior grade paint: one coat of primer and one coat of finish paint.

1.7.3.4. Text and Graphics: Layout shall be as shown below and a digital file will be provided by the City. The graphics shall have colors as shown in the digital file.

Contractor shall provide project contact name, phone numbers and email as required.

1.8. PUBLICITY RELEASES
Contractor shall not release any information, story, photograph, plan, or drawing relating to information about the Project to anyone, including press and other public communications medium, including, without limitation, on website(s) without the City’s prior written approval.

END OF SECTION

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SITE STANDARDS 01 52 10 - 1
SECTION 01 52 10

SITE STANDARDS

1. GENERAL

1.1. RELATED DOCUMENTS AND PROVISIONS:

Contractor shall review all Contract Documents for applicable provisions related to the provisions in this document, including without limitation:

1.1.1. General Conditions, including without limitation, Site Access, Conditions, and Regulations;

1.1.2. Supplementary Conditions (if any);

1.1.3. Drug-Free Workplace Certification;

1.1.4. Tobacco-Free Environment Certification;

1.1.5. Criminal Background Investigation/Fingerprinting Certification; and

1.1.6. Temporary Facilities and Controls.

1.2. REQUIREMENTS OF THE CITY

1.2.1. Language: Unacceptable and/or loud language will not be tolerated, "Cat calls" or other derogatory language toward staff or public will not be allowed.

1.2.2. Disturbing the Peace (Noise and Lighting):

1.2.2.1. Contractor shall observe the noise ordinance of the Site at all times including, without limitation, all applicable local, city, and/or state laws, ordinances, and/or regulations regarding noise and allowable noise levels.

1.2.2.2. The use of radios, etc., shall be controlled to keep all sound at a level that cannot be heard beyond the immediate area of use. City reserves the right to prohibit the use of radios at the Site, except for handheld communication radios.

1.2.2.3. If portable lights are used after dark, the lights must be located so as not to direct light into neighboring properties.

1.2.3. Traffic:

1.2.3.1. Driving on the Premises shall be limited to periods when public are not present.

In no case shall driving take place across playgrounds or other pedestrian paths. The speed limit on-the Premises shall be five (5) miles per hour (maximum) or less if conditions require.

1.2.3.2. All paths of travel for deliveries, including without limitation, material, equipment, and supply deliveries, shall be reviewed and approved by City in advance. Any damage will be repaired to the pre-damaged condition by the Contractor.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SITE STANDARDS 01 52 10 - 2

1.2.3.3. City shall designate a construction entry to the Site. If Contractor requests, City determines it is required, and to the extent possible, City shall designate a staging area so as not to interfere with the normal functioning of the Site.

Location of gates and fencing shall be approved in advance with City and at Contractor's expense.

1.2.3.4. Parking areas shall be reviewed and approved by City in advance. No parking is to occur under the drip line of trees or in areas that could otherwise be damaged.

1.2.3.5. All of the above shall be observed and complied with by the Contractor and all workers on the Site. Failure to follow these directives could result in individual(s) being suspended or removed from the work force at the discretion of the City. The same rules and regulations shall apply equally to delivery personnel, inspectors, consultants, and other visitors to the Site.

END OF SECTION

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
TEMPORARY TREE AND PLANT PROTECTION 01 56 39 - 1
SECTION 01 56 39

TEMPORARY TREE AND PLANT PROTECTION

1. GENERAL

1.1. RELATED DOCUMENTS
Contractor shall review all Contract Documents for applicable provisions related to the provisions in this document, including without limitation:

1.1.1. General Conditions;

1.1.2. Supplementary Conditions (if any); and

1.1.3. Temporary Facilities and Controls.

1.2. SUMMARY
This Document includes the protection and trimming of existing trees that interfere with, or are affected by, execution of the Work, whether temporary or permanent construction.

1.3. DEFINITIONS
Tree Protection Zone: Area surrounding individual trees or groups of trees to remain during construction, and defined by the drip line of individual trees or the perimeter drip line of groups of trees, unless otherwise indicated.

1.4. SUBMITTALS

1.4.1. Product Data: For each type of product indicated.

1.4.2. Tree Pruning Schedule: Written schedule from arborist detailing scope and extent of pruning of trees to remain that interfere with or are affected by construction.

1.4.3. Qualification Data: For tree service firm and arborist.

1.4.4. Certification: From arborist, certifying that trees indicated to remain have been protected during construction according to recognized standards and that trees were promptly and properly treated and repaired when damaged.

1.4.5. Maintenance Recommendations: From arborist, for care and protection of trees affected by construction during and after completing the Work.

1.5. QUALITY ASSURANCE

1.5.1. Tree Service Firm Qualifications: An experienced tree service firm that has successfully completed tree protection and trimming work similar to that required for this Project and that will assign an experienced, qualified arborist to Project site during execution of tree protection and trimming.

1.5.2. Arborist Qualifications: An arborist certified by ISA (International Society of Arboriculture) or licensed in the jurisdiction where Project is located.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
TEMPORARY TREE AND PLANT PROTECTION 01 56 39 - 2

1.5.3. Tree Pruning Standard: Comply with ANSI A300 (Part 1), "Tree, Shrub, and Other Woody Plant Maintenance--Standard Practices (Pruning)."

1.5.3.1. Before tree protection and trimming operations begin, meet with City to review tree protection and trimming procedures and responsibilities.

1.5.3.2. Before pruning any roots larger than two inches (2”) in diameter, the Contractor shall consult with an Arborist or Landscape Landscape Architect.

Contractor shall be responsible for hiring the Arborist or Landscape Landscape Architect. The Arborist or Landscape Landscape Architect shall provide a report that includes recommendations to the Contractor who shall supply this report to the Construction Manager, the City and the Landscape Architect.

2. PRODUCTS

2.1. MATERIALS

2.1.1. Unless otherwise specified, Contractor shall select materials as recommended by arborist or landscape Landscape Architect.

2.1.2. Drainage Fill: Selected crushed stone, or crushed or uncrushed gravel, washed, ASTM D 448, Size 24, with 90 to 100 percent passing a 2-1/2-inch (63-mm) sieve and not more than 10 percent passing a 3/4-inch (19-mm) sieve.

2.1.3. Topsoil: Natural or cultivated surface-soil layer containing organic matter and sand, silt, and clay particles; friable, pervious, and black or a darker shade of brown, gray, or red than underlying subsoil; reasonably free of subsoil, clay lumps, gravel, and other objects more than 1 inch (25 mm) in diameter; and free of weeds, roots, and toxic and other nonsoil materials.

2.1.3.1. Obtain topsoil only from well-drained sites where topsoil is 4 inches (100 mm) deep or more; do not obtain from bogs or marshes.

2.1.4. Filter Fabric: Manufacturer's standard, nonwoven, pervious, geotextile fabric of polypropylene, nylon, or polyester fibers.

2.1.5. Chain-Link Fence: Metallic-coated steel chain-link fence fabric of 0.120-inch- (3-mm-) diameter wire; a minimum of 72 inches (1800 mm) high; with 1.9-inch- (48-mm-) diameter line posts; 2-3/8-inch- (60-mm-) diameter terminal and corner posts; 1-5/8- inch- (41-mm-) diameter top rail; and 0.177-inch- (4.5-mm-) diameter bottom tension wire; with tie wires, hog ring ties, and other accessories for a complete fence system.

2.1.6. Select mulch as recommended by arborist or landscape Landscape Architect.

2.1.7. Organic Mulch: Use shredded hardwood, ground or shredded bark, or wood and bark chips, all free of deleterious materials.

3. EXECUTION

3.1. PREPARATION

3.1.1. Preconstruction Meeting: Review methods and procedures related to temporary pl ant protection including, but not limited to:

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
TEMPORARY TREE AND PLANT PROTECTION 01 56 39 - 3

3.1.1.1. Construction schedule. Verify availability of materials, personnel, and equ ipment needed to make progress and avoid delays.

3.1.1.2. Enforcing requirements for protection zones.

3.1.1.3. Project Arborist's responsibilities.

3.1.1.4. Field quality control.

3.1.2. Temporary Fencing: Install temporary fencing around tree protection zones to protect remaining trees and vegetation from construction damage prior to any site preparation, demolition, or grading work. Maintain temporary fence and remove when construction is complete.

3.1.3. Install chain-link fence according to ASTM F 567 and manufacturer's written instructions.

3.1.4. Protect tree root systems from damage caused by runoff or spillage of noxious materials while mixing, placing, or storing construction materials. Protect root systems from ponding, eroding, or excessive wetting caused by dewatering operations.

3.1.5. Mulch areas inside tree protection zones and other areas indicated.

3.1.5.1. Select mulch as recommended by arborist or landscape Landscape Architect.

3.1.5.2. Apply 2-inch (50-mm) to 3-inch (75-mm) average thickness of organic mulch.

Do not place mulch within 6 inches (150 mm)] of tree trunks.

3.1.6. Do not store construction materials, debris, or excavated material inside tree protection zones. Do not permit vehicles or foot traffic within tree protection zones; prevent soil compaction over root systems.

3.1.7. Maintain tree protection zones free of weeds and trash.

3.1.8. Do not allow fires within tree protection zones.

3.2. EXCAVATION

3.2.1. Install shoring or other protective support systems to minimize sloping or benching of excavations where construction or utility excavation is near trees to be protected.

3.2.2. Do not excavate within tree protection zones, unless otherwise indicated.

3.2.3. Where excavation for new construction is required within tree protection zones, hand clear and excavate to minimize damage to root systems. Use narrow-tine spading forks and comb soil, or compressed air-powered tool or water to remove soil, to expose roots.

3.2.3.1. Do not allow exposed roots to dry out before placing permanent backfill.

Provide temporary earth cover or pack with peat moss and wrap with burlap.

Water and maintain in a moist condition. Temporarily support and protect roots from damage until they are permanently relocated and covered with soil.

3.2.4. Where utility trenches are required within tree protection zones, tunnel under or around roots by drilling, auger boring, pipe jacking, or digging by hand.

3.2.4.1. Root Pruning: Do not cut main lateral roots or taproots; cut only smaller roots (2-inch diameter and smaller) that interfere with installation of utilities. Cut

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
TEMPORARY TREE AND PLANT PROTECTION 01 56 39 - 4
roots with sharp pruning instruments; do not break or chop. Consult with an Arborist or Landsacpe Landscape Architect for roots latger than 2-inch diameter.

3.3. REGRADING

3.3.1. Grade Lowering: Where new finish grade is indicated below existing grade around trees, slope grade beyond tree protection zones. Maintain existing grades within tree protection zones.

3.3.2. Grade Lowering: Where new finish grade is indicated below existing grade around trees, slope grade away from trees as recommended by arborist, unless otherwise indicated.

3.3.2.1. Root Pruning: Prune tree roots exposed during grade lowering. Do not cut main lateral roots or taproots; cut only smaller roots. Cut roots with sharp pruning instruments; do not break or chop.

3.3.3. Minor Fill: Where existing grade is 6 inches (150 mm) or less below elevation of finish grade, fill with topsoil. Place topsoil in a single uncompacted layer and hand grade to required finish elevations.

3.3.4. Moderate Fill: Where existing grade is more than 6 inches (150 mm) but less than 12 inches (300 mm) below elevation of finish grade, place drainage fill, filter fabric, and topsoil on existing grade as follows:

3.3.4.1. Carefully place drainage fill against tree trunk approximately 2 inches (50 mm) above elevation of finish grade and extend not less than 18 inches (450 mm) from tree trunk on all sides. For balance of area within drip-line perimeter, place drainage fill up to 6 inches (150 mm) below elevation of grade.

3.3.4.2. Place filter fabric with edges overlapping 6 inches (150 mm) minimum.

3.3.4.3. Place fill layer of topsoil to finish grade. Do not compact drainage fill or topsoil.

Hand grade to required finish elevations.

3.4. TREE PRUNING

3.4.1. Prune trees to remain that are affected by temporary and permanent construction.

3.4.2. Prune trees to remain to compensate for root loss caused by damaging or cutting root system as directed by an Arborist or Landscape Landscape Architect. Provide subsequent maintenance during Contract period as recommended by arborist.

3.4.3. Prune trees to be preserved to clean the crown of dead branches 2” and larger in diameter and raise canopies as needed for construction activities.

3.4.4. Prune to raise the canopies of all trees 8 feet above ground unless otherwise directed by an Arborist of Landscape Landscape Architect.

3.4.5. Pruning Standards: Prune trees according to ANSI A300 (Part 1), as recommended by arborist report.

3.4.6. Adjust pruning requirements per arborist’s recommendations.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
TEMPORARY TREE AND PLANT PROTECTION 01 56 39 - 5

3.4.7. Cut branches with sharp pruning instruments; do not break or chop.

3.4.8. Modify below to specific project requirements.

3.4.9. Chip removed tree branches and dispose of or spread over areas identified by City.

Tree(s) to be removed that have branches extending into the canopy of tree(s) to remain must be removed by a qualified arborist or certified tree workers and not by construction contractors. The qualified arborist shall remove the tree in a manner that causes no damage to the tree(s) and understory to remain. Tree stumps shall be ground 12” below ground surface.

3.5. TREE REPAIR AND REPLACEMENT

3.5.1. Promptly repair trees damaged by construction operations within 24 hours. Treat damaged trunks, limbs, and roots according to arborist's written instructions.

3.5.2. Remove and replace trees indicated to remain that die or are damaged during construction operations or that are incapable of restoring to normal growth pattern.

3.5.2.1. Provide new trees of 6-inch (150-mm) caliper size and of a when damaged trees more than 6 inches (150 mm) in caliper size, measured 12 inches (300 mm) above grade, are required to be replaced. Plant and maintain new trees as specified in Contract Documents.

3.5.3. Where recommended by arborist report, aerate surface soil, compacted during construction, 10 feet (3 m) beyond drip line and no closer than 36 inches (900 mm) to tree trunk. Drill 2-inch (50-mm) diameter holes a minimum of 12 inches (300 mm) deep at 24 inches (600 mm) o.c. Backfill holes with an equal mix of augered soil and sand.

3.6. DISPOSAL OF WASTE MATERIALS

3.6.1. Burning is not permitted.

3.6.2. Disposal: Remove excess excavated material and displaced trees from Site.

END OF SECTION

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
STORM WATER POLLUTION PREVENTION PLAN (SWPPP) - CONSTRUCTION 01 57 10 - 1 SECTION 01 57 10
STORM WATER POLLUTION PREVENTION PLAN (SWPPP) – CONSTRUCTION

1. GENERAL

1.15. RELATED DOCUMENTS AND PROVISION
Contractor shall review all Contract Documents for applicable provisions related to the provisions in this document, including without limitation:

1.15.1. General Conditions;

1.15.2. Supplementary Conditions;

1.15.3. Site Standards;

1.16. The Clean Water Act and Porter Cologne Water Quality Act prohibit the discharge of any water containing pollutants from certain construction sites unless a National Pollutant Discharge Elimination System permit is first obtained and followed. The National Pollutant Discharge Elimination System General Permit for Storm Water Discharges Associated with Construction and Land Disturbance Activities (Construction Storm Water Permit) Order No. 2009-0009-DWQ as amended by Order No. 2010-0014-DWQ (NPDES No. CAS000002) issued by the California State Water Resources Control Board (State Water Board) authorizes the discharge of storm water and certain non-storm water from construction sites if certain conditions and measures are taken.

The City has determined that the construction of this Project requires enrollment in the Construction Storm Water Permit.

2. SUBMITTALS

2.1. GENERAL
All submittals shall be made in a form conducive for the City to electronically upload the approved submittals to the Storm water Multi-Application Reporting and Tracking System (SMARTS).

2.2. RISK ASSESSMENT

2.2.1. Concurrent with the Submittal Schedule as indicated in the General Conditions, Contractor shall prepare and submit a proposed “Risk Assessment” as set forth in the Construction Storm Water Permit.

2.2.2. The Contractor’s Qualified SWPPP Developer (“QSD”) will review the Contractor’s proposed Risk Assessment for compliance with the Construction Storm Water Permit. If changes to the proposed Risk Assessment are required to comply with the Construction Storm Water Permit, the City QSD will identify such changes to the Contractor.

2.2.3. Contractor shall make the changes specified by the QSD and shall submit the revised Risk Assessment to the City within seven (7) days of receipt of the changes identified by the QSD. If the changes had been acceptably made, the QSD will approve the Risk Assessment and provide the Contractor with a copy within seven (7) days of receipt of the revised Risk Assessment.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
STORM WATER POLLUTION PREVENTION PLAN (SWPPP) - CONSTRUCTION 01 57 10 - 2

2.3. SITE MAPS

2.3.1. Concurrent with the Submittal Schedule as indicated in the General Conditions, Contractor shall prepare and submit proposed “Site Maps” as described in Attachment B of the Construction Storm Water Permit.

2.3.2. The QSD will review the Contractor’s proposed Site Maps for compliance with the Construction Storm Water Permit. If changes to the proposed Site Maps are required to comply with the Construction Storm Water Permit, the QSD will identify such changes to the Contractor.

2.3.3. Contractor shall make the changes specified by the QSD and shall submit the revised Site Maps to the City within seven (7) days of receipt of the changes identified by the City’s QSD. If the changes had been acceptably made, the QSD will approve the Site Maps and provide the Contractor with a copy within seven (7) days of receipt of the revised SWPPP.

2.4. SWPPP

2.4.1. Concurrent with the Submittal Schedule as indicated in the General Conditions, Contractor shall prepare and submit to the City a proposed SWPPP for the Work.

2.5. RAIN EVENT ACTION PLAN (REAP) – CONTRACTOR’S OBLIGATIONS TO PREPARE

2.5.1. A Rain Event Action Plan (REAP) is a written document, specific for each rain event. A REAP should be designed so that when implemented it protects all exposed portions of the site within 48 hours of any likely rain.

2.5.2. The General Permit requires Risk Level 2 and 3 dischargers to develop and implement a REAP designed to protect all exposed portions of their sites within 48 hours prior to any likely precipitation event. The REAP requirement is designed to ensure that the discharger has adequate materials, staff, and time to implement erosion and sediment control measures that are intended to reduce the amount of sediment and other pollutants generated from the active site. A REAP must be developed when there is likely a forecast of 50% or greater probability of precipitation in the Project area. (The National Oceanic and Atmospheric Administration (NOAA) defines a chance of precipitation as a probability of precipitation of 30% to 50% chance of producing precipitation in the project area. The NOAA defines the probability of precipitation as the likelihood of occurrence (expressed as a percent) of a measurable amount (0.01 inch or more) of liquid precipitation (or the water equivalent of frozen precipitation) during a specified period of time at any given point in the forecast area). Forecasts are normally issued for 12-hour time periods.

2.5.3. Contractor shall prepare and submit to the City a proposed REAP for the Work.

2.6. ACTIVE TREATMENT SYSTEM (ATS)

2.6.1. If Contractor determines that Site requires an ATS under the Construction Storm Water Permit, concurrent with the Submittal Schedule as indicated in the General Conditions, Contractor shall prepare and submit to the City a proposed ATS for the Work.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
STORM WATER POLLUTION PREVENTION PLAN (SWPPP) - CONSTRUCTION 01 57 10 - 3

2.7. RECORDS
All electronic and hardcopy records required by the Construction Storm Water Permit shall be submitted to the City within seven (7) days of Completion of the Project.

3. PERMIT REGISTRATION DOCUMENTS
Prior to any activities on Site that disturb the Site’s surface, the Permit Registration Documents (PRDs) required by the Construction Storm Water Permit must be filed with the Regional Water Quality Control Board. The City shall file the PRDs with the Regional Water Quality Control Board to activate coverage under the Construction Storm Water Permit.

4. IMPLEMENTATION REQUIREMENTS

4.1. Contractor shall not conduct any activities that may affect the Site’s construction runoff water quality until the City provides Contractor with the Waste Discharger Identification Number (WDID) assigned to the Project by the State Water Board.

4.2. Contractor shall keep a copy of the approved SWPPP at the job site. The SWPPP shall be made available when requested by a representative of the Regional Water Quality Control Board, State Water Resources Control Board, United States Environmental Protection Agency, or the local storm water management agency. Requests from the public shall be directed to the City for response.

4.3. Contractor shall designate in writing to the City a Qualified SWPPP Practitioner (QSP) who shall be responsible for implementing the SWPPP, REAP (if applicable), ATS (if applicable), conducting non-storm water and storm water visual observations, and for ensuring that all best management practices (BMPs) required by the SWPPP and General Permit are properly implemented and maintained.

4.4. All measures required by the SWPPP shall be implemented concurrent with the commencement of construction. Pollution practices and devices shall be followed or installed as early in the construction schedule as possible with frequent upgrading of devices as construction progresses.

4.5. Contractor shall ensure that all measures are properly maintained and repaired to protect the water quality of discharges.

5. INSPECTION, SAMPLING, ANALYSIS, AND RECORD KEEPING REQUIREMENTS The Contractor’s QSP shall conduct all required visual observations, sampling, analysis, reporting, and record keeping required by the SWPPP and the Construction Storm Water Permit.

6. REPORTING REQUIREMENTS
Contractor shall prepare and provide all the reports, which include, but are not limited to the Annual Report and any NEL Violation Reports or NAL Exceedance Reports, all of which are required by the SWPPP and the Construction Storm Water Permit.

7. ANNUAL REPORT
By August 1 of each year (defined as July 1 to June 30) that had at least one continuous three (3) month period coverage under the General Permit, Contractor shall complete and submit to the City an Annual Report, as

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
STORM WATER POLLUTION PREVENTION PLAN (SWPPP) - CONSTRUCTION 01 57 10 - 4 required by the General Permit. If the Project is complete prior to August 1, Contractor shall submit the report prior to acceptance of the Project.

8. COMPLETION OF WORK

8.1. Clean-up shall be performed as each portion of the Work progresses. All refuse, excess material, and possible pollutants shall be disposed of in a legal manner off-site and all temporary and permanent SWPPP devices shall be in place and maintained in good condition.

8.2. At Completion of Work, Contractor shall inspect installed SWPPP devices, and present the currently implemented SWPPP with all backup records to the City.

9. NOTICE OF TERMINATION (NOT)
A Notice of Termination (NOT) must be submitted by the Contractor to the City for electronic submittal by the Legally Responsible Person via SMARTS to terminate coverage under the General Permit. The NOT must include a final Site Map and representative photographs of the Project Site that demonstrate final stabilization has been achieved. The NOT shall be submitted to the City on or before the Contractor submits its final application for payment. If the Regional Water Board rejects the NOT for any reason, the Contractor shall revise the NOT as many times as necessary to obtain the Regional Water Board’s approval. The Regional Water Board will consider a construction site complete when the conditions of Section II.D of the General Permit have been met.

10. QUALITY ASSURANCE

10.1. Before performing any of the obligations indicated herein, the Contractor’s QSP shall meet the training and certification requirements in the Construction Storm Water Permit.

10.2. Contractor shall perform the Work in strict compliance with the approved SWPPP, REAP, ATS, and the Construction Storm Water Permit.

10.3. Contractor shall conduct at least a one-hour training session on the requirements of the SWPPP for each employee before an employee conducts any Work on the Site. Contractor shall maintain documentation of this employee training at the Site for review by the City or any regulatory agency.

11. PERFORMANCE REQUIREMENTS

11.1. The SWPPP is a minimum requirement. Revisions and modifications to the SWPPP are acceptable only if they maintain levels of protection equal to or greater than originally specified.

11.2. Read and be thoroughly familiar with all of the requirements of the SWPPP.

11.3. Inspect and monitor all work and storage areas for compliance with the SWPPP prior to any anticipated rain.

11.4. Complete any and all corrective measures as may be directed by the regulatory agency.

11.5. Penalties: Contractor shall pay any fees and any penalties that may be imposed by a regulatory agency for non-compliance with the SWPPP during the course of Work.

11.6. Costs: Contractor shall pay all costs associated with the implementation of the requirements of

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
STORM WATER POLLUTION PREVENTION PLAN (SWPPP) - CONSTRUCTION 01 57 10 - 5 the SWPPP in order to maintain compliance with the Permit. This includes installation of all Housekeeping BMPs, General Site and Material Management BMPs, Inspection requirements, maintenance requirements, and all other requirements specified in the SWPPP.

12. MATERIALS
All temporary and permanent storm water pollution prevention facilities, equipment, and materials as required by or as necessary to comply with the SWPPP as described in the BMP Handbook.

END OF SECTION

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
MATERIALS AND EQUIPMENT 01 60 00 - 1
SECTION 01 60 00

MATERIALS AND EQUIPMENT

1. GENERAL

1.1. RELATED DOCUMENTS AND PROVISIONS
Contractor shall review all Contract Documents for applicable provisions related to the provisions in this document, including without limitation:

1.1.1. General Conditions.

1.1.2. Supplementary Conditions (if any); and

1.1.3. Imported Materials Certification.

1.2. MATERIALS AND EQUIPMENT

1.2.1. Only items approved by the City and/or Landscape Architect shall be used.

1.2.2. Contractor shall submit lists of Products and other Product information in accordance with the Contract Documents, including, without limitation, the provisions regarding the submittals.

1.3. MATERIALS AND EQUIPMENT COLORS

1.3.1. The Contractor shall comply with all schedule(s) of colors provided by the City and/or Landscape Architect.

1.3.2. No individual color selections will be made until after approval of all pertinent materials and equipment and after receipt of appropriate samples in accordance with the Contract Documents, including, without limitation, the provisions regarding the submittals.

1.3.3. Contractor shall request priority in writing for any item requiring advance ordering to maintain the approved Construction Schedule.

1.4. DELIVERY, STORAGE, AND HANDLING

1.4.1. Contractor shall deliver manufactured materials in original packages, containers, or bundles (with seals unbroken), bearing name or identification mark of manufacturer.

City may inspect materials prior to Contractor unloading the delivered materials. City may reject any materials that do not conform to the Contract Documents.

1.4.2. Contractor shall deliver fabrications in as large assemblies as practicable; where specified as shop-primed or shop-finished, package or crate as required to preserve such priming or finish intact and free from abrasion.

1.4.3. Contractor shall store materials in such a manner as necessary to properly protect them from damage. Materials or equipment damaged by handling, weather, dirt, or from any other cause will not be accepted.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
MATERIALS AND EQUIPMENT 01 60 00 - 2

1.4.4. Materials that have been warehoused for long periods of time, stored or transported in improper environment, improperly packaged, inadequately labeled, poorly protected, excessively shipped, deviated from normal distribution pattern, or reassembled are not acceptable.

1.4.5. Contractor shall store materials so as to cause no obstructions of sidewalks, roadways, or underground services. Contractor shall protect materials and equipment furnished pursuant to the Contract Documents.

1.4.6. Contractor may store materials on Site with prior written approval by City; all materials shall remain under Contractor's control and Contractor shall remain liable for any damage to the materials. Should the Project Site not have storage area available, the Contractor shall provide for off-site storage at no cost to City.

1.4.7. When any room in Project is used as a shop or storeroom, Contractor shall be responsible for any repairs, patching, or cleaning necessary due to that use. Location of storage space shall be subject to prior written approval by City.

2. PRODUCTS

2.1. MANUFACTURERS

2.1.1. Manufacturers listed in various sections of the Contract Documents are names of those manufacturers that are believed to be capable of supplying one or more of the items specified therein.

2.1.2. The listing of a manufacturer does not imply that every product of that manufacturer is acceptable or as meeting the requirements of the Contract Documents.

2.2. FACILITIES AND EQUIPMENT
Contractor shall provide, install, maintain, and operate a complete and adequate facility for handling, execution, disposal, and distribution of materials and equipment as required for proper and timely performance of Work.

2.3. MATERIALS REFERENCE STANDARDS
Where materials are specified solely by reference to “standard specifications” or other general reference, and if requested by City, Contractor shall submit for review data on actual materials proposed to be incorporated into Work, listing name and address of vendor, manufacturer, or producer, and trade or brand names of those materials, and data substantiating compliance with standard specifications.

3. EXECUTION

3.1. WORKMANSHIP

3.1.1. Where not more specifically described in any other Contract Documents, workmanship shall conform to methods and operations of best standards and accepted practices of trade or trades involved and shall include items of fabrication, construction, or installation regularly furnished or required for completion (including finish and for successful operation, as intended).

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
MATERIALS AND EQUIPMENT 01 60 00 - 3

3.1.2. Work shall be executed by tradespersons skilled in their respective field of work. When completed, parts shall have been durably and substantially built and present a neat appearance.

3.2. COORDINATION

3.2.1. Contractor shall coordinate installation of materials and equipment so as to not interfere with installation of other Work. Adjustment or rework because of Contractor’s failure to coordinate will be at no additional cost to City.

3.2.2. Contractor shall examine in-place materials and equipment for readiness, completeness, fitness to be concealed or to receive Work , and compliance with Contract Documents.

Concealing or covering work constitutes acceptance of additional cost which will result should in-place materials and equipment be found unsuitable for receiving other work or otherwise deviating from the requirements of the Contract Documents.

3.3. COMPLETENESS
Contractor shall provide all portions of the Work, unless clearly stated otherwise, installed complete and operational with all elements, accessories, anchorages, utility connections, etc., in a manner to ensure well-balanced performance, in accordance with manufacturer's recommendations and in accordance with Contract Documents. For example, electric water coolers require water, electricity, and drain services; roof drains require drain systems; sinks fit within countertop, etc. Terms such as “installed complete,” “operable condition,” “for use intended,” “connected to all utilities,” “terminate with proper cap,” “adequately anchored,” “patch and refinish,” and “to match similar” should be assumed to apply in all cases, except where completeness of functional or operable condition is specifically stated as not required.

3.4. APPROVED INSTALLER OR APPLICATOR
Contractor shall ensure that all installations are only performed by a manufacturer’s approved installer or applicator.

3.5. MANUFACTURER'S RECOMMENDATIONS
All installations shall be in accordance with manufacturer's published recommendations and specific written directions of manufacturer's representative. Should the Contract Documents differ from recommendations of manufacturer or directions of manufacturer’s representative, Contractor shall analyze differences, make recommendations to the City and the Landscape Architect in writing, and shall not proceed until interpretation or clarification has been issued by the City and/or the Landscape Architect.

END OF SECTION

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
DELIVERY, STORAGE AND HANDLING 01 66 10 - 1
SECTION 01 66 10

DELIVERY, STORAGE AND HANDLING

1. GENERAL

1.1. RELATED DOCUMENTS AND PROVISIONS
Contractor shall review all Contract Documents for applicable provisions related to the provisions in this document, including without limitation:

1.1.1. General Conditions, including, without limitation, Site Access, Conditions and Requirements; and

1.1.2. Supplementary Conditions.

1.2. PRODUCTS

1.2.1. Products are as defined in the General Conditions.

1.2.2. Contractor shall not use and/or reuse materials and/or equipment removed from existing Premises, except as specifically permitted by the Contract Documents.

1.2.3. Contractor shall provide interchangeable components of the same manufacturer, for similar components.

1.3. TRANSPORTATION AND HANDLING

1.3.1. Contractor shall transport and handle Products in accordance with manufacturer's instructions.

1.3.2. Contractor shall promptly inspect shipments to confirm that Products comply with Contract requirements, are of correct quantity, and are undamaged.

1.3.3. Contractor shall provide equipment and personnel to properly handle Products to prevent soiling, disfigurement, or damage.

1.4. STORAGE AND PROTECTION

1.4.1. Contractor shall store and protect Products in accordance with manufacturer's instructions, with seals and labels intact and legible. Contractor shall store sensitive Products in weather-tight, climate controlled enclosures.

1.4.2. Contractor shall place fabricated Products that are stored outside, on above-ground sloped supports.

1.4.3. Contractor shall provide off-site storage and protection for Products when Site does not permit on-site storage or protection.

1.4.4. Contractor shall cover Products subject to deterioration with impervious sheet covering and provide ventilation to avoid condensation.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
DELIVERY, STORAGE AND HANDLING 01 66 10 - 2

1.4.5. Contractor shall store loose granular materials on solid flat surfaces in a well-drained area and prevent mixing with foreign matter.

1.4.6. Contractor shall provide equipment and personnel to store Products by methods to prevent soiling, disfigurement, or damage.

1.4.7. Contractor shall arrange storage of Products to permit access for inspection and periodically inspect to assure Products are undamaged and are maintained under specified conditions.

END OF SECTION

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CONSTRUCTION STAKING AND SURVEY 01 71 23 - 1
SECTION 01 71 23

CONSTRUCTION STAKING AND SURVEY
PART 1 -GENERAL

1.01 SUMMARY
A. This section specifies the work for construction staking which consists of providing all labor, tools, equipment, materials and incidentals necessary to locate by staking all improvements, to the line and grade shown on the Plans.

PART 2 - PRODUCTS
Not Used
PART 3 - EXECUTION

3.01 GENERAL
A. Contractor shall furnish all land surveys, establish all base lines and bench marks and make sufficient detailed surveys needed for working points, lines and elevations. The Contractor shall develop all slope stakes and batter boards. Contractor shall also develop all additional working points, lines and elevations as they may desire to facilitate his or her methods and sequence of construction.

B. All work shall be staked in order to meet the lines and grades shown on the Plans. Copies of all survey cut sheets shall be provided to the City Engineer two (2) working days before the planned work begins.

C. Finished grade elevations, pipe flowlines, and walls shall be within minus five hundredths (-0.05) foot of elevation and plan location.

D. Prior to concrete pouring, formwork and survey staking shall be reviewed and approved by the City Engineer.

END OF SECTION 01 71 23

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
EXECUTION 01 73 00 - 1
SECTION 01 73 00

EXECUTION

1. GENERAL

1.1. RELATED DOCUMENTS AND PROVISIONS
Contractor shall review all Contract Documents for applicable provisions related to the provisions in this document, including without limitation:

1.1.1. General Conditions;

1.1.2. Supplementary Conditions (if any);

1.1.3. Coordination and Project Meetings;

1.1.4. Submittals;

1.1.5. Materials and Equipment;

1.1.6. Cutting and Patching;

1.1.7. Contract Closeout and Final Cleaning; and

1.1.8. General Commissioning Requirements.

1.2. SUMMARY

1.2.1. This Document includes general procedural requirements governing execution of the Work including, but not limited to, the following:

1.2.1.1. Construction layout;

1.2.1.2. Field engineering and surveying;

1.2.1.3. General installation of products;

1.2.1.4. Owner furnished, Contractor installed items;

1.2.1.5. Coordination of City-installed products;

1.2.1.6. Progress cleaning;

1.2.1.7. Staring and adjusting;

1.2.1.8. Protection of installed construction; and

1.2.1.9. Correction of the Work.

1.3. SUBMITTALS

1.3.1. Qualification Data: For land surveyor or professional engineer.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
EXECUTION 01 73 00 - 2

1.3.2. Certificates: Submit certificate signed by land surveyor or professional engineer certifying that location and elevation of improvements comply with requirements.

1.3.3. Landfill Receipts: Submit copy of receipts issued by a landfill facility, licensed to accept the materials as classified, for hazardous waste disposal.

1.3.4. Certified Surveys: Submit electronic files and three (3) paper copies signed by land surveyor or professional engineer.

1.3.5. Final Property Survey: Submit electronic files and three (3) paper copies showing the Work performed and record survey data.

2. EXECUTION

2.1. EXAMINATION

2.1.1. Existing Utilities: The existence and location of underground and other utilities and construction indicated as existing are not guaranteed. Before beginning Site Work, investigate and verify the existence and location of underground utilities and other construction affecting the Work.

2.1.1.1. Before construction, verify the location and invert elevation at points of connection of sanitary sewer, storm sewer, and water-service piping; and underground electrical services.

2.1.1.2. Furnish location data for Work related to Project that must be performed by public utilities serving the Project Site.

2.2. PREPARATION

2.2.1. Existing Utility Information: Furnish information to local utility that is necessary to adjust, move, or relocate existing utility structures, utility poles, lines, services, or other utility appurtenances located in or affected by construction. Coordinate with authorities having jurisdiction.

2.2.2. Field Measurements: Take field measurements as required to fit the Work properly.

Recheck measurements before installing each product. Where portions of the Work are indicated to fit to other construction, verify dimensions of other construction by field measurements before fabrication. Coordinate fabrication schedule with construction progress to avoid delaying the Work.

2.2.3. Space Requirements: Verify space requirements and dimensions of items shown diagrammatically on Drawings.

2.2.4. Review of Contract Documents and Field Conditions: Immediately on discovery of the need for clarification of the Contract Documents, submit a request for information to City per requirements of Document “Requests for Information.” Include a detailed description of problem encountered, together with recommendations for any necessary changes to the Contract Documents.

2.3. CONSTRUCTION LAYOUT

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
EXECUTION 01 73 00 - 3

2.3.1. Verification: Before proceeding to lay out the Work, verify layout information shown on Drawings, in relation to the property survey and existing benchmarks. If discrepancies are discovered, notify City and its consultant promptly.

2.3.2. General: Engage a land surveyor or professional engineer to lay out the Work using accepted surveying practices.

2.3.2.1. Establish benchmarks and control points to set lines and levels at each story of construction and elsewhere as needed to locate each element of Project.

2.3.2.2. Establish dimensions within tolerances indicated. Do not scale Drawings to obtain required dimensions.

2.3.2.3. Inform installers of lines and levels to which they must comply.

2.3.2.4. Check the location, level and plumb, of every major element as the Work progresses.

2.3.2.5. Notify City and its consultant when deviations from required lines and levels exceed allowable tolerances.

2.3.2.6. Close site surveys with an error of closure equal to or less than the standard established by authorities having jurisdiction.

2.3.3. Site Improvements: Locate and lay out site improvements, including pavements, grading, fill and topsoil placement, utility slopes, and invert elevations.

2.3.4. Building Lines and Levels: Locate and lay out control lines and levels for structures, building foundations, column grids, and floor levels, including those required for mechanical and electrical work. Transfer survey markings and elevations for use with control lines and levels. Level foundations and piers from two or more locations.

2.3.5. Record Log: Maintain a log of layout control Work. Record deviations from required lines and levels. Include beginning and ending dates and times of surveys, weather conditions, name and duty of each survey party member, and types of instruments and tapes used. Make the log available for reference by City and its consultant.

2.4. FIELD ENGINEERING

2.4.1. Reference Points: Locate existing permanent benchmarks, control points, and similar reference points before beginning the Work. Preserve and protect permanent benchmarks and control points during construction operations.

2.4.1.1. Do not change or relocate existing benchmarks or control points without prior written approval of City and its consultant. Report lost or destroyed permanent benchmarks or control points promptly. Report the need to relocate permanent benchmarks or control points to City and its consultant before proceeding.

2.4.1.2. Require surveyor to replace lost or destroyed permanent benchmarks and control points promptly. Base replacements on the original survey control points.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
EXECUTION 01 73 00 - 4

2.4.2. Benchmarks: Establish and maintain a minimum of two (2) permanent benchmarks on Project Site, referenced to data established by survey control points. Comply with authorities having jurisdiction for type and size of benchmark.

2.4.2.1. Record benchmark locations, with horizontal and vertical data, on Project Record Documents.

2.4.2.2. Where the actual location or elevation of layout points cannot be marked, provide temporary reference points sufficient to locate the Work.

2.4.2.3. Remove temporary reference points when no longer needed. Restore marked construction to its original condition.

2.4.3. Records: Contractor shall maintain a complete, accurate log of all control and survey Work as it progresses. On request of City or Landscape Architect, Contractor shall submit documentation to verify accuracy of field engineering Work at no additional cost to the City.

2.4.4. Certified Survey: On completion of foundation walls, major site improvements, and other Work requiring field-engineering services, prepare a certified survey showing dimensions, locations, angles, and elevations of construction and sitework.

2.4.5. Final Property Survey: Prepare and submit a final property survey showing significant features (real property) for Project. Include on the survey a certification, signed by land surveyor or professional engineer, that principal metes, bounds, lines, and levels of Project are accurately positioned as shown on the survey and are in conformance with Contract Documents.

2.4.5.1. Show boundary lines, monuments, streets, site improvements and utilities, existing improvements and significant vegetation, adjoining properties, acreage, grade contours, and the distance and bearing from a Site corner to a legal point.

2.4.6. Compliance with Laws: Contractor is responsible for meeting all applicable codes, OSHA, safety, and shoring requirements.

2.4.7. Nonconforming Work: Contractor is responsible for any re-surveying required by correction of nonconforming Work.

2.5. INSTALLATION

2.5.1. General: Locate the Work and components of the Work accurately, in correct alignment and elevation, as indicated.

2.5.1.1. Make vertical Work plumb and make horizontal Work level.

2.5.1.2. Where space is limited, install components to maximize space available for maintenance and ease of removal for replacement.

2.5.1.3. Conceal pipes, ducts, and wiring in finished areas, unless otherwise indicated.

2.5.1.4. Maintain minimum headroom clearance of 7 feet in spaces without a suspended ceiling.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
EXECUTION 01 73 00 - 5

2.5.2. Comply with manufacturer's written instructions and recommendations for installing products in applications indicated.

2.5.3. Install products at the time and under conditions that will ensure the best possible results. Maintain conditions required for product performance until Completion.

2.5.4. Conduct construction operations so no part of the Work is subjected to damaging operations or loading in excess of that expected during normal conditions of occupancy.

2.5.5. Tools and Equipment: Do not use tools or equipment that produce harmful noise levels where possible.

2.5.6. Templates: Obtain and distribute to the parties involved templates for work specified to be factory prepared and field installed. Check Shop Drawings of other work to confirm that adequate provisions are made for locating and installing products to comply with indicated requirements.

2.5.7. Anchors and Fasteners: Provide anchors and fasteners as required to anchor each component securely in place, accurately located and aligned with other portions of the Work.

2.5.7.1. Mounting Heights: Where mounting heights are not indicated, mount components at heights directed by City.

2.5.7.2. Allow for building movement, including thermal expansion and contraction.

2.5.7.3. Coordinate installation of anchorages. Furnish setting drawings, templates, and directions for installing anchorages, including sleeves, concrete inserts, anchor bolts, and items with integral anchors, that are to be embedded in concrete or masonry. Deliver such items to Project Site in time for installation.

2.5.8. Joints: Make joints of uniform width. Where joint locations in exposed work are not indicated, arrange joints for the best visual effect. Fit exposed connections together to form hairline joints.

2.5.9. Hazardous Materials: Use products, cleaners, and installation materials that are not classed as hazardous per the MSDS sheets for the products where possible. If hazardous materials are necessary, inform City where and when they will be used no less than 48 hours before use. Take all recommended precautions of the materials’ manufacturers to ensure safe use and clean-up.

2.6. CITY-INSTALLED PRODUCTS

2.6.1. Site Access: Provide access to Project Site for City's construction forces.

2.6.2. Coordination: Coordinate construction and operations of the Work with work performed by City's construction forces.

2.6.2.1. Construction Schedule: Inform City of Contractor’s preferred schedule for City's portion of the Work. Adjust Construction Schedule based on a mutually agreeable timetable. Notify City if changes to schedule are required due to differences in actual construction progress.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
EXECUTION 01 73 00 - 6

2.6.2.2. Preinstallation Conferences: Include City's construction forces at preinstallation conferences covering portions of the Work that are to receive City's work.

Attend preinstallation conferences conducted by City's construction forces if portions of the Work depend on City's construction.

2.7. PROGRESS CLEANING

2.7.1. General: Clean Project Site and work areas daily, including common areas. Coordinate progress cleaning for joint-use areas where more than one installer has worked.

Enforce requirements strictly. Dispose of materials lawfully.

2.7.1.1. Comply with requirements in NFPA 241 for removal of combustible waste materials and debris.

2.7.1.2. Do not hold materials more than seven (7) days during normal weather or three (3) days if the temperature is expected to rise above 80 degrees F.

2.7.1.3. Containerize hazardous and unsanitary waste materials separately from other waste. Mark containers appropriately and dispose of legally, according to regulations. Remove hazardous and unsanitary waste materials daily.

2.7.2. Site: Maintain Project Site free of waste materials and debris.

2.7.3. Work Areas: Clean areas where work is in progress to the level of cleanliness necessary for proper execution of the Work.

2.7.3.1. Remove liquid spills promptly.

2.7.3.2. Where dust would impair proper execution of the Work, broom-clean or vacuum the entire work area, as appropriate.

2.7.4. Installed Work: Keep installed work clean. Clean installed surfaces according to written instructions of manufacturer or fabricator of product installed, using only cleaning materials specifically recommended. If specific cleaning materials are not recommended, use cleaning materials that are not hazardous to health or property and that will not damage exposed surfaces.

2.7.5. Concealed Spaces: Remove debris from concealed spaces before enclosing the space.

2.7.6. Exposed Surfaces in Finished Areas: Clean exposed surfaces and protect as necessary to ensure freedom from damage and deterioration at time of Completion.

2.7.7. Waste Disposal: Burying or burning waste materials on-site will not be permitted.

Washing waste materials down sewers or into waterways will not be permitted.

2.7.8. During handling and installation, clean and protect construction in progress and adjoining materials already in place. Apply protective covering where required to ensure protection from damage or deterioration at Completion.

2.7.9. Clean and provide maintenance on completed construction as frequently as necessary through the remainder of the construction period. Adjust and lubricate operable components to ensure operability without damaging effects.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
EXECUTION 01 73 00 - 7

2.7.10. Limiting Exposures: Supervise construction operations to assure that no part of the construction, completed or in progress, is subject to harmful, dangerous, damaging, or otherwise deleterious exposure during the construction period.

2.8. STARTING AND ADJUSTING

2.8.1. Start equipment and operating components to confirm proper operation. Replace or repair malfunctioning units and retest.

2.8.2. Adjust operating components for proper operation without binding. Adjust equipment for proper operation.

2.8.3. Test each piece of equipment to verify proper operation. Test and adjust controls and safeties. Replace damaged and malfunctioning controls and equipment.

2.8.4. Manufacturer’s Field Service: If a factory-authorized service representative is required to inspect field-assembled components and equipment installation, comply with qualification requirements in Document “Quality Requirements.”

2.9. PROTECTION OF INSTALLED CONSTRUCTION

2.9.1. Provide final protection and maintain conditions that ensure installed Work is without damage or deterioration at time of Completion.

2.9.2. Comply with manufacturer’s written instruction for temperature and relative humidity unless otherwise addressed in the construction planning, sequences, and instructions.

See Section 06 40 00 “Landscape Architectural Woodwork” for additional condition requirements of woodwork.

2.10. CORRECTION OF THE WORK

2.10.1. Repair or remove and replace defective construction. Restore damaged substrates and finishes. Comply with requirements in Document "Cutting and Patching."

2.10.1.1.Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment.

2.10.2. Restore permanent facilities used during construction to their specified condition.

2.10.3. Remove and replace damaged surfaces that are exposed to view if surfaces cannot be repaired without visible evidence of repair.

2.10.4. Repair components that do not operate properly. Remove and replace operating components that cannot be repaired.

2.10.5. Remove and replace chipped, scratched, and broken glass or reflective surfaces.

END OF SECTION

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CUTTING AND PATCHING 01 73 29 - 1
SECTION 01 73 29

CUTTING AND PATCHING

1. GENERAL

1.1. RELATED DOCUMENTS AND PROVISIONS
Contractor shall review all Contract Documents for applicable provisions related to the provisions in this document, including without limitation:

1.1.1. General Conditions, including, without limitation, Inspections, and Tests, Integration of Work, Nonconforming Work, and Correction of Work, and Uncovering Work;

1.1.2. Supplementary Conditions (if any);

1.1.3. Hazardous Materials Procedures and Requirements;

1.1.4. Hazardous Materials Certification;

1.1.5. Lead-Based Materials Certification; and

1.1.6. Imported Materials Certification.

1.2. CUTTING AND PATCHING

1.2.1. Contractor shall be responsible for all cutting, fitting, and patching, including associated excavation and backfill, required to complete the Work or to:

1.2.1.1. Make several parts fit together properly.

1.2.1.2. Uncover portions of Work to provide for installation of ill-timed Work.

1.2.1.3. Remove and replace defective Work.

1.2.1.4. Remove and replace Work not conforming to requirements of Contract Documents.

1.2.1.5. Remove Samples of installed Work as specified for testing.

1.2.1.6. Provide routine penetrations of non-structural surfaces for installation of piping and electrical conduit.

1.2.1.7. Attaching new materials to existing remodeling areas – including painting (or other finishes) to match existing conditions.

1.2.2. In addition to Contract requirements, upon written instructions from City, Contractor shall uncover Work to provide for observations of covered Work in accordance with the Contract Documents, remove samples of installed materials for testing as directed by City, and remove Work to provide for alteration of existing Work.

1.2.3. Contractor shall not cut or alter Work, or any part of it, in such a way that endangers or compromises the integrity of the Work, the Project, or Work of others.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CUTTING AND PATCHING 01 73 29 - 2

1.2.4. Contractor shall not cut and patch operating elements or safety related components in a manner that results in reducing their capacity to perform as intended or that results in increased maintenance or decreased operational life or safety. Operating elements include the following:

1.2.4.1. Primary operational systems and equipment.

1.2.4.2. Air or smoke barriers.

1.2.4.3. Fire-suppression systems.

1.2.4.4. Mechanical systems piping and ducts.

1.2.4.5. Control systems.

1.2.4.6. Communication systems.

1.2.4.7. Conveying systems.

1.2.4.8. Electrical wiring systems.

1.2.5. Contractor shall not cut and patch miscellaneous elements or related components in a manner that could change their load-carrying capacity, that results in reducing capacity to perform as intended, or that results in increased maintenance or decreased operational life of safety. Miscellaneous elements include the following:

1.2.5.1. Water, moisture or vapor barriers.

1.2.5.2. Membranes and flashings.

1.2.5.3. Exterior curtain-wall construction.

1.2.5.4. Equipment supports.

1.2.5.5. Piping, ductwork, vessels and equipment.

1.2.5.6. Noise and vibration control elements and systems.

1.2.5.7. Shoring, bracing and sheeting.

1.3. REQUEST TO CUT, ALTER, PATCH OR EXCAVATE

1.3.1. Contractor shall submit written notice to City pursuant to the applicable notice provisions of the Contract Documents, requesting consent to proceed with the cutting or alteration (“Request”) at least ten (10) days prior to any cutting or alterations that may affect the structural safety of the Project, or Work of others, including the following:

1.3.1.1. The Work of the City or other trades.

1.3.1.2. Structural value or integrity of any element of the Project.

1.3.1.3. Integrity or effectiveness of weather-exposed or weather-resistant elements or systems.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CUTTING AND PATCHING 01 73 29 - 3

1.3.1.4. Efficiency, operational life, maintenance or safety of operational elements.

1.3.1.5. Visual qualities of sight-exposed elements.

1.3.2. Contractor's Request shall also include:

1.3.2.1. Identification of the Project.

1.3.2.2. Description of affected Work.

1.3.2.3. Necessity for cutting, alterations, or excavations.

1.3.2.4. Impacts of that Work on the City, other trades, or structural or weatherproof integrity of the Project.

1.3.2.5. Description of proposed Work:

1.3.2.5.1. Scope of cutting, patching, alterations, or excavations.

1.3.2.5.2. Trades that will execute Work.

1.3.2.5.3. Products proposed to be used.

1.3.2.5.4. Extent of refinishing to be done.

1.3.2.6. Alternates to cutting and patching.

1.3.2.7. Cost proposal, when applicable.

1.3.2.8. The scheduled date the Work is to be performed and the duration of time to complete the Work.

1.3.2.9. Written permission of other trades whose Work will be affected.

1.4. QUALITY ASSURANCE

1.4.1. Contractor shall ensure that cutting, fitting, and patching shall achieve security, strength, weather protection, appearance for aesthetic match, efficiency, operational life, maintenance, safety of operational elements, and the continuity of existing fire ratings.

1.4.2. Contractor shall ensure that cutting, fitting, and patching shall successfully duplicate undisturbed adjacent profiles, materials, textures, finishes, and colors, and that materials shall match existing construction. Where there is dispute as to whether duplication is successful or has been achieved to a reasonable degree, the City's decision shall be final.

1.5. PAYMENT FOR COSTS

1.5.1. Costs caused by ill-timed or defective Work or Work not conforming to Contract Documents, including costs for additional services of the City or its consultants including but not limited to the Landscape Architect, inspector(s), engineers, and agents, will be paid by Contractor and/or deducted from the Contract Price by the City.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CUTTING AND PATCHING 01 73 29 - 4

1.5.2. Contractor shall provide written cost proposals prior to proceeding with cutting and patching. City shall only pay for cost of Work if it is part of the Contract Price or if a change has been made to the Contract in compliance with the provisions of the General Conditions. Cost of Work performed upon instructions from the City, other than defective or nonconforming Work, will be paid by City on approval of written Change Order in accordance with the Contract Documents.

2. PRODUCTS

2.1. MATERIALS

2.1.1. Contractor shall provide for replacement and restoration of Work removed. Contractor shall comply with the Contract Documents and with the industry standard(s), for the type of Work, and the Specification requirements for each specific product involved. If not specified, Contractor shall recommend a product of a manufacturer or appropriate trade association for approval by the City.

2.1.2. Materials to be cut and patched include those damaged by the performance of the Work.

3. EXECUTION

3.1. INSPECTION

3.1.1. Contractor shall inspect existing conditions of the Site and the Work, including elements subject to movement or damage during cutting and patching, excavating and backfilling.

After uncovering Work, Contractor shall inspect conditions affecting installation of new products.

3.1.2. Contractor shall report unsatisfactory or questionable conditions in writing to City as indicated in the General Conditions and shall proceed with Work as indicated in the General Conditions by City.

3.2. PREPARATION

3.2.1. Contractor shall provide shoring, bracing and supports as required to maintain structural integrity for all portions of the Project, including all requirements of the Project.

3.2.2. Contractor shall provide devices and methods to protect other portions of Project from damage.

3.2.3. Contractor shall, provide all necessary protection from weather and extremes of temperature and humidity for the Project, including without limitation any work that may be exposed by cutting and patching Work. Contractor shall keep excavations free from water.

3.3. ERECTION, INSTALLATION AND APPLICATION

3.3.1. With respect to performance, Contractor shall ensure its Subcontractors:

3.3.1.1. Execute fitting and adjustment of products to provide finished installation to comply with and match specified tolerances and finishes.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CUTTING AND PATCHING 01 73 29 - 5

3.3.1.2. Execute cutting and demolition by methods that will prevent damage to other Work, and provide proper surfaces to receive installation of repairs and new Work.

3.3.1.3. Execute cutting, demolition excavating, and backfilling by methods that will prevent damage to other Work and damage from settlement.

3.3.1.4. Contractor shall use original installer or fabricator to perform cutting and patching for:

3.3.1.5. Weather-exposed surfaces and moisture-resistant elements such as roofing, sheet metal, sealants, waterproofing, and other trades.

3.3.1.6. Sight-exposed finished surfaces.

3.3.2. Contractor shall ensure its Subcontractors execute fitting and adjustment of products to provide a finished installation to comply with specified products, functions, tolerances, and finishes as shown or specified in the Contract Documents including, without limitation, the Drawings and Specifications.

3.3.3. Subcontractors shall fit Work airtight to pipes, sleeves, ducts, conduit, and other penetrations through surfaces. Contractor shall conform to all Code requirements for penetrations or the Drawings and Specifications, whichever calls for a higher quality or more thorough requirement. Contractor shall maintain integrity of both rated and nonrated fire walls, ceilings, floors, etc.

3.3.4. Contractor’s Subcontractors shall restore Work which has been cut or removed and install new products to provide completed Work in accordance with requirements of the Contract Documents and as required to match surrounding areas and surfaces.

3.3.5. Contractor’s Subcontractors shall refinish all continuous surfaces to nearest intersection as necessary to match the existing finish to any new finish.

END OF SECTION

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 01 74 19 - 1 SECTION 01 74 19

CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

1. WASTE MANAGEMENT REQUIREMENTS

1.1. City requires that this Project generate the least amount of trash and waste possible.

1.2. Employ processes that ensure the generation of as little waste as possible due to error, poor planning, breakage, mishandling, contamination, or other factors.

1.3. Comply with City of Richmond Construction Waste Recycling requirements.

1.4. Required Recycling, Salvage, and Reuse: The following may not be disposed of in landfills or by incineration:

1.4.1. Aluminum and plastic beverage containers.

1.4.2. Corrugated cardboard.

1.4.3. Wood pallets.

1.4.4. Clean dimensional wood.

1.4.5. Land clearing debris, including brush, branches, logs, and stumps: See Section 31 10 00 for use options.

1.4.6. Metals, including packaging banding, metal studs, sheet metal, structural steel, piping, reinforcing bars, door frames, and other items made of steel, iron, galvanized steel, stainless steel, aluminum, copper, zinc, lead, brass, and bronze.

1.5. Contractor shall submit periodic Waste Disposal Reports; all landfill disposal, recycling, salvage, and reuse must be reported regardless of to whom the cost or savings accrues; use the same units of measure on all reports.

1.6. Methods of trash/waste disposal that are not acceptable are:

1.6.1. Burning on the project site.

1.6.2. Burying on the project site.

1.6.3. Dumping or burying on other property, public or private.

1.6.4. Other illegal dumping or burying.

1.6.5. Incineration, either on- or off-site.

1.6.6. Regulatory Requirements: Contractor is responsible for knowing and complying with regulatory requirements, including but not limited to Federal, state and local requirements, pertaining to legal disposal of all construction and demolition waste materials.

2. RELATED REQUIREMENTS

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 01 74 19 - 2

2.1. General Conditions.

2.2. Section 01 30 00 - Administrative Requirements: Additional requirements for project meetings, reports, submittal procedures, and project documentation.

2.3. Section 01 35 00 - Bay Friendly Landscaping Practice Requirements.

2.4. Section 31 10 00 - Site Clearing: Handling and disposal of land clearing debris.

3. MEASUREMENT AND PAYMENT

3.1. Measurement and payment by the unit method. No separate compensation or payment shall be made for work of this Section.

4. DEFINITIONS

4.1. Clean: Untreated and unpainted; not contaminated with oils, solvents, caulk, or the like.

4.2. Construction and Demolition Waste: Solid wastes typically including building materials, packaging, trash, debris, and rubble resulting from construction, remodeling, repair and demolition operations.

4.3. Hazardous: Exhibiting the characteristics of hazardous substances, i.e., ignitibility, corrosivity, toxicity or reactivity.

4.4. Nonhazardous: Exhibiting none of the characteristics of hazardous substances, i.e., ignitibility, corrosivity, toxicity, or reactivity.

4.5. Nontoxic: Neither immediately poisonous to humans nor poisonous after a long period of exposure.

4.6. Recyclable: The ability of a product or material to be recovered at the end of its life cycle and remanufactured into a new product for reuse by others.

4.7. Recycle: To remove a waste material from the project site to another site for remanufacture into a new product for reuse by others.

4.8. Recycling: The process of sorting, cleansing, treating and reconstituting solid waste and other discarded materials for the purpose of using the altered form. Recycling does not include burning, incinerating, or thermally destroying waste.

4.9. Return: To give back reusable items or unused products to vendors for credit.

4.10.Reuse: To reuse a construction waste material in some manner on the project site.

4.11. Salvage: To remove a waste material from the project site to another site for resale or reuse by others.

4.12. Sediment: Soil and other debris that has been eroded and transported by storm or well production runoff water.

4.13. Source Separation: The act of keeping different types of waste materials separate beginning from the first time they become waste.

4.14.Toxic: Poisonous to humans either immediately or after a long period of exposure.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 01 74 19 - 3

4.15.Trash: Any product or material unable to be reused, returned, recycled, or salvaged.

4.16.Waste: Extra material or material that has reached the end of its useful life in its intended use. Waste includes salvageable, returnable, recyclable, and reusable material.

5. SUBMITTALS

5.1. See Section 01,3000 - Administrative Requirements, for submittal procedures.

5.2. Pre- and Post-Construction Debris Recovery Plans as described in Section 01,3500.

5.3. Waste Disposal Reports: Submit the CONSTRUCTION & DEMOLITION DEBRIS MANAGEMENT PLAN per the Alameda County building permit requirement. The form can be downloaded through the link below. http://www.co.alameda.ca.us/pwa/documents/CD_Form_AC_BID_08_2009.pdf

5.3.1. Submit Construction Debris Management Plan and complete the“Estimated Waste” section of the form at time of pulling the building permit.

5.3.2. During construction, contractor shall submit receipts from approved facilities for diversion of waste and complete the “Actual Waste” section of the form to the County building inspector for approval.

Project will not be finaled until the form is complete and accepted by the County building inspector.

5.3.3. Reuse or donate unused construction materials to donation organization such as ReStore, Oakland (510) 777-1447.

5.4. Submit the City of Hayward “Construction and Demolition Debris Recycling Statement” to the City prior to the construction. The form can be downloaded through the link below https://www.haywardca.gov/sites/default/files/CD%20Recycling%20Form%202017.pdf

6. CONSTRUCTION DEBRIS RECOVERY PLAN IMPLEMENTATION

6.1. Manager: Designate an on-site person or persons responsible for instructing workers and overseeing and documenting results of the Waste Management Plan.

6.2. Communication: Distribute copies of the Waste Management Plan to job site foreman, each subcontractor, City, and Landscape Landscape Architect.

6.3. Instruction: Provide on-site instruction of appropriate separation, handling, and recycling, salvage, reuse, and return methods to be used by all parties at the appropriate stages of the project.

6.4. Hazardous Wastes: Separate, store, and dispose of hazardous wastes according to applicable regulations.

6.5. Recycling: Separate, store, protect, and handle at the site identified recyclable waste products in order to prevent contamination of materials and to maximize recyclability of identified materials. Arrange for timely pickups from the site or deliveries to recycling facility in order to prevent contamination of recyclable materials.

6.6. Reuse of Materials On-Site: Set aside, sort, and protect separated products in preparation for reuse.

6.7. Salvage: Set aside, sort, and protect products to be salvaged for reuse off-site.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL 01 74 19 - 4

END OF SECTION

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CONTRACT CLOSEOUT AND FINAL CLEANING 01 77 00 - 1
SECTION 01 77 00

CONTRACT CLOSEOUT AND FINAL CLEANING

1. GENERAL

1.1. RELATED DOCUMENTS
Contractor shall review all Contract Documents for applicable provisions related to the provisions in this document, including without limitation:

1.1.1. General Conditions including, without limitation, Documents on Work and Completion of Work;

1.1.2. Supplementary Conditions (if any);

1.1.3. Submittals;

1.1.4. Operation and Maintenance Data;

1.1.5. Warranties;

1.1.6. Record Documents;

1.1.7. Demonstration and Training; and

1.1.8. General Commissioning Requirements.

1.2. SUBSTANTIAL COMPLETION

1.2.1. Before requesting inspection for determining date of Final Acceptance, complete the following. List items below that are incomplete in request.

1.2.1.1. Obtain and submit releases permitting City unrestricted use of the Work and access to services and utilities. Include certificate of occupancy, operating certificates, and similar releases, if required.

1.2.1.2. Complete startup testing of systems.

1.2.1.3. Submit test/adjust/balance records, if required.

1.2.2. LIST OF INCOMPLETE ITEMS (PUNCH LIST): Contractor shall notify City and Landscape Architect when Contractor considers the Work Is substantially complete. Upon notification, City and Landscape Architect will prepare a list of minor items to be completed or corrected (“Punch List”).

1.2.3. Contractor and/or its Subcontractors shall proceed promptly to complete and correct items on the Punch List. Failure to include an item on Punch List does not alter the responsibility of the Contractor to complete all Work in accordance with the Contract Documents.

1.3. RECORD DOCUMENTS AND SHOP DRAWINGS

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CONTRACT CLOSEOUT AND FINAL CLEANING 01 77 00 - 2

1.3.1. Contractor shall legibly mark each item to record actual construction, including:

1.3.1.1. Measured depths of foundation in relation to finish floor datum.

1.3.1.2. Measured horizontal and vertical locations of underground utilities and appurtenances, referenced to permit surface improvements.

1.3.1.3. Measured locations of internal utilities and appurtenances concealed in construction, referenced to visible and accessible features of the Work.

1.3.1.4. Field changes of dimension and detail.

1.3.1.5. Details not on original Contract Drawings

1.3.1.6. Changes made by modification(s).

1.3.1.7. References to related Shop Drawings and modifications.

1.3.1.8. Contractor will provide one set of Record Drawings to City.

1.3.1.9. Contractor shall submit all required documents to City and/or Landscape Architect prior to or with its final Application for Payment.

1.4. COMPLETION

1.4.1. Preliminary Procedures: Before requesting inspection for determining date of Completion, complete the following:

1.4.1.1. Submit a final Application for Payment according to the Contract Documents along with final lien releases from the subcontractors.

1.4.1.2. Submit specific warranties, workmanship bonds, maintenance service agreements, final certifications, and similar documents.

1.4.1.3. Prepare and submit Project Record Documents, operation and maintenance manuals, Completion construction photograph prints and electronic files, damage or settlement surveys, property surveys, and similar final record information.

1.4.1.4. Deliver tools, spare parts, extra materials, and similar items to location designated by City. Label with manufacturer's name and model number where applicable.

1.4.1.5. Make final changeover of permanent locks and deliver keys to City. Advise City's personnel of changeover in security provisions.

1.4.1.6. Terminate and remove temporary facilities from Project Site, along with mockups, construction tools, and similar elements.

1.4.1.7. Advise City of changeover in heat and other utilities.

1.4.1.8. Submit changeover information related to City's occupancy, use, operation, and maintenance.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CONTRACT CLOSEOUT AND FINAL CLEANING 01 77 00 - 3

1.4.1.9. Complete final cleaning requirements, including touch-up painting.

1.4.1.10.Touch up and otherwise repair and restore marred exposed finishes to eliminate visual defects.

1.4.1.11.Instruction/Training of City Personnel:

1.4.1.11.1. Before final inspection, at agreed upon times, Contractor shall instruct/provide training to City's designated personnel in operation, adjustment, and maintenance of products,
equipment, and systems.

1.4.1.11.2. For equipment requiring seasonal operation, Contractor shall perform instructions/training for other seasons within six (6) months.

1.4.1.11.3. Contractor shall use operation and maintenance manuals as basis for instruction. Contractor shall review contents of manual with personnel in detail to explain all aspects of operation and maintenance.

1.4.1.11.4. Contractor shall prepare and insert additional data in Operation and Maintenance Manual when need for such
data becomes apparent during instruction.

1.4.1.11.5. Contractor shall use operation and maintenance manuals as basis for instruction. Contractor shall review contents of manual with personnel in detail to explain all aspects of operation and maintenance.

1.4.2. Inspection: Submit a written request for inspection.

1.4.3. Contractor shall comply with Punch List procedures as provided herein and in the Contract Documents, and maintain the presence of a Project Superintendent and Project Manager until the Punch List is complete to ensure proper and timely completion of the Punch List, upon receipt of Contractor’s written notice that all of the Punch List items have been fully completed and the Work is ready for final inspection and acceptance, City and Landscape Architect will inspect the Work and shall submit to Contractor a final inspection report noting the Work, if any, required in order to reach Completion in accordance with the Contract Documents. Absent unusual circumstances, this report shall consist of the Punch List items not yet satisfactorily completed and any additional Punch List items not originally included.

1.4.4. Upon Contractor's completion of all items on the Punch List and any other uncompleted portions of the Work, the Contractor shall notify the City and Landscape Architect, who shall again inspect such Work. If the City and Landscape Architect find the Work complete and acceptable under the Contract Documents, the City will notify Contractor, who shall then jointly submit to the Landscape Architect and City its final Application for Payment.

1.4.5. Costs of Multiple Inspections. More than two (2) requests of City to make a final inspection shall be considered an additional service of City, the Landscape Architect

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CONTRACT CLOSEOUT AND FINAL CLEANING 01 77 00 - 4
and/or the Inspector, and all subsequent costs will be invoiced to Contractor and withheld from remaining payments, if funds are available.

1.4.6. Punch List shall be deemed complete only upon the City’s determination that all items on the Punch List, and all updates to the Punch List, are complete.

1.5. WARRANTIES

1.5.1. Submittal Time: Submit written warranties on request of City for designated portions of the Work where commencement of warranties other than date of Final Completion is indicated.

1.5.2. Organize warranty documents into an orderly sequence as required by the Document 01 78 36 “Warranties.”

2. PRODUCTS

2.1. MATERIALS

2.1.1. Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or fabricator of the surface to be cleaned. Do not use cleaning agents that are potentially hazardous to health or property or that might damage finished surfaces.

3. EXECUTION

3.1. FINAL CLEANING

3.1.1. Provide final cleaning. Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and antipollution regulations. Contractor shall use cleaning methods and procedures that reduce the overall impact on human health and the natural environment by reducing the amount of disposed waste, pollution and environmental degradation. If Project is subject to LEED certification, Contractor shall ensure compliance with the applicable LEED requirements for final cleaning of the Site.

3.1.2. Contractor shall employ experienced workers or professional cleaners for final cleaning.

Clean each surface or unit to condition expected in an average commercial building cleaning and maintenance program.

3.1.2.1. Complete the following cleaning operations before requesting final inspection:

3.1.2.1.1. Clean Project Site, yard, and grounds, in areas disturbed by construction activities, including landscape development areas, of rubbish, waste material, litter, and other foreign substances.

3.1.2.1.2. Sweep paved areas broom clean. Remove petrochemical spills, stains, and other foreign deposits.

3.1.2.1.3. Rake grounds that are neither planted nor paved to a smooth, even-textured surface.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CONTRACT CLOSEOUT AND FINAL CLEANING 01 77 00 - 5

3.1.2.1.4. Remove tools, construction equipment, machinery, and surplus material from Project Site.

3.1.2.1.5. Clean exposed exterior and interior hard-surfaced finishes to a dirt-free condition, free of stains, films, and similar foreign substances

3.1.2.1.6. Clean all surfaces and other work in accordance with recommendations of the manufacturer.

3.1.2.1.7. Remove spots, mortar, plaster, soil, and paint from ceramic tile, stone, and other finish materials.

3.1.2.1.8. Sweep concrete floors broom clean in unoccupied spaces.

3.1.2.1.9. Vacuum carpet and similar soft surfaces, removing debris and excess nap; shampoo if visible soil or stains remain.

3.1.2.1.10. Clean transparent materials, including mirrors and glass in doors and windows.

3.1.2.1.11. Remove labels that are not permanent.

3.1.2.1.12. Touch up and otherwise repair and restore marred, exposed finishes and surfaces. Replace finishes and surfaces that cannot be satisfactorily repaired or restored or that already show evidence of repair or restoration.

3.1.2.1.13. Wipe surfaces of mechanical and electrical equipment and similar equipment.

3.1.2.1.14. Replace parts subject to unusual operating conditions.

3.1.2.1.15. Clean plumbing fixtures to a sanitary condition, free of stains, including stains resulting from water exposure.

3.1.2.1.16. Replace disposable air filters and clean permanent air filters.

Clean exposed surfaces of diffusers, registers, and grills.

3.1.2.1.17. Clean ducts, blowers, and coils if units were operated without filters during construction.

3.1.2.1.18. Clean light fixtures, lamps, globes, and reflectors to function with full efficiency. Replace burned-out bulbs, and those noticeably dimmed by hours of use, and defective and noisy starters in fluorescent and mercury vapor fixtures to comply with requirements for new fixtures.

3.1.2.1.19. Leave Project Site clean and ready for occupancy.

3.1.3. Pest Control: Engage an experienced, licensed exterminator to make a final inspection and rid Project of rodents, insects, and other pests.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CONTRACT CLOSEOUT AND FINAL CLEANING 01 77 00 - 6

3.1.4. Comply with safety standards for cleaning. Do not burn waste materials. Do not bury debris or excess materials on City's property. Do not discharge volatile, harmful, or dangerous materials into drainage systems. Remove waste materials from Project Site and dispose of lawfully.

END OF SECTION

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
OPERATIONS AND MAINTENANCE DATA 01 78 23 - 1
SECTION 01 78 23

OPERATION AND MAINTENANCE DATA

1. GENERAL

1.1. RELATED DOCUMENTS AND PROVISIONS
Contractor shall review all Contract Documents for applicable provisions related to the provisions in this document, including without limitation:

1.1.1. General Conditions, including, without limitation, Completion of the Work;

1.1.2. Supplementary Conditions (if any);

1.1.3. Submittals;

1.1.4. Contract Closeout and Final Cleaning;

1.1.5. Warranties;

1.1.6. Record Documents; and

1.1.7. General Commissioning Requirements.

1.2. QUALITY ASSURANCE

1.2.1. Contractor shall prepare instructions and data by personnel experienced in maintenance and operation of described products.

1.3. FORMAT

1.3.1. Contractor shall prepare data in the form of an instructional manual entitled “OPERATIONS AND MAINTENANCE MANUAL & INSTRUCTIONS” (“Manual”).

1.3.2. Binders: Contractor shall use commercial quality, 8-1/2 by 11 inch, three-side rings, with durable plastic covers; two inch maximum ring size. When multiple binders are used, Contractor shall correlate data into related consistent groupings.

1.3.3. Cover: Contractor shall identify each binder with typed or printed title "OPERATION AND MAINTENANCE MANUAL & INSTRUCTIONS"; and shall list title of Project and identify subject matter of contents.

1.3.4. Contractor shall arrange content by systems process flow under section numbers and sequence of the Table of Contents of the Contract Documents.

1.3.5. Contractor shall provide tabbed fly leaf for each separate Product and system, with typed description of Product and major component parts of equipment.

1.3.6. Text: The content shall include Manufacturer's printed data, or typewritten data on 24 pound paper.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
OPERATIONS AND MAINTENANCE DATA 01 78 23 - 2

1.3.7. Drawings: Contractor shall provide with reinforced punched binder tab and shall bind in with text; folding larger drawings to size of text pages.

1.3.8. Contractor shall also provide the O&M Manuals along with the drawings in a pdf format provided to the City on a thumb drive.

1.4. CONTENTS, EACH VOLUME

1.4.1. Table of Contents: Contractor shall provide title of Project; names, addresses, and telephone numbers of the Landscape Architect, any engineers, subconsultants, Subcontractor(s), and Contractor with name of responsible parties; and schedule of Products and systems, indexed to content of the volume.

1.4.2. For Each Product or System: Contractor shall list names, addresses, and telephone numbers of Subcontractor(s) and suppliers, including local source of supplies and replacement parts.

1.4.3. Product Data: Contractor shall mark each sheet to clearly identify specific Products and component parts, and data applicable to installation. Delete inapplicable information.

1.4.4. Drawings: Contractor shall supplement Product data to illustrate relations of component parts of equipment and systems, to show control and flow diagrams. Contractor shall not use Project Record Documents as maintenance drawings.

1.4.5. Text: The Contractor shall include any and all information as required to supplement Product data. Contractor shall provide logical sequence of instructions for each procedure, incorporating manufacturer's instructions.

1.5. MANUAL FOR MATERIALS AND FINISHES

1.5.1. Building Products, Applied Materials, and Finishes: Contractor shall include Product data, with catalog number, size, composition, and color and texture designations.

Contractor shall provide information for re-ordering custom manufactured Products.

1.5.2. Instructions for Care and Maintenance: Contractor shall include Manufacturer's recommendations for cleaning agents and methods, precautions against detrimental agents and methods, and recommended schedule for cleaning and maintenance.

1.5.3. Moisture Protection and Weather Exposed Products: Contractor shall include Product data listing applicable reference standards, chemical composition, and details of installation. Contractor shall provide recommendations for inspections, maintenance, and repair.

1.5.4. Additional Requirements: Contractor shall include all additional requirements as specified in the Specifications.

1.5.5. Contractor shall provide a listing in Table of Contents for design data, with tabbed fly sheet and space for insertion of data.

1.6. MANUAL FOR EQUIPMENT AND SYSTEMS

1.6.1. Each Item of Equipment and Each System: Contractor shall include description of unit or system, and component parts and identify function, normal operating characteristics,

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
OPERATIONS AND MAINTENANCE DATA 01 78 23 - 3
and limiting conditions. Contractor shall include performance curves, with engineering data and tests, and complete nomenclature, and commercial number of replaceable parts.

1.6.2. Panelboard Circuit Directories: Contractor shall provide electrical service characteristics, controls, and communications.

1.6.3. Contractor shall include color coded wiring diagrams as installed.

1.6.4. Operating Procedures: Contractor shall include start-up, break-in, and routine normal operating instructions and sequences. Contractor shall include regulation, control, stopping, shut-down, and emergency instructions. Contractor shall include summer, winter, and any special operating instructions.

1.6.5. Maintenance Requirements: Contractor shall include routine procedures and guide for trouble-shooting; disassembly, repair, and reassembly instructions; and alignment, adjusting, balancing, and checking instructions.

1.6.6. Contractor shall provide servicing and lubrication schedule, and list of lubricants required.

1.6.7. Contractor shall include manufacturer's printed operation and maintenance instructions.

1.6.8. Contractor shall include sequence of operation by controls manufacturer.

1.6.9. Contractor shall provide original manufacturer's parts list, illustrations, assembly drawings, and diagrams required for maintenance.

1.6.10. Contractor shall provide control diagrams by controls manufacturer as installed.

1.6.11. Contractor shall provide Contractor's coordination drawings, with color coded piping diagrams as installed.

1.6.12. Contractor shall provide charts of valve tag numbers, with location and function of each valve, keyed to flow and control diagrams.

1.6.13. Contractor shall provide list of original manufacturer's spare parts, current prices, and recommended quantities to be maintained in storage.

1.6.14. Additional Requirements: Contractor shall include all additional requirements as specified in Specification(s).

1.6.15. Contractor shall provide a listing in Table of Contents for design data, with tabbed fly sheet and space for insertion of data.

1.7. SUBMITTAL

1.7.1. Concurrent with the Schedule of Submittals as indicated in the General Conditions, Contractor shall submit to the City for review two (2) copies of a preliminary draft of proposed formats and outlines of the contents of the Manual.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
OPERATIONS AND MAINTENANCE DATA 01 78 23 - 4

1.7.2. For equipment, or component parts of equipment put into service during construction and to be operated by City, Contractor shall submit draft content for that portion of the Manual within ten (10) days after acceptance of that equipment or component.

1.7.3. On or before the Contractor submits its final application for payment, Contractor shall submit two (2) copies of a complete Manual in final form. The City will provide comments to Contractor and Contractor must revise the content of the Manual as required by City prior to City's approval of Contractor’s final Application for Payment.

1.7.4. Contractor must submit two (2) copies of revised Manual in final form within ten (10) days after receiving City’s comments. Failure to do so will be a basis for the City withholding funds sufficient to protect itself for Contractor’s failure to provide a final Manual to the City.

END OF SECTION

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
WARRANTIES 01 78 36 - 1
SECTION 01 78 36

WARRANTIES

1. GENERAL

1.1. RELATED DOCUMENTS AND PROVISIONS
Contractor shall review all Contract Documents for applicable provisions related to the provisions in this document, including without limitation:

1.1.1. General Conditions, including, without limitation, Warranty/Guarantee/Indemnity;

1.1.2. Supplementary Conditions (if any);

1.1.3. Submittals;

1.1.4. Contract Closeout and Final Cleaning;

1.1.5. Operation and Maintenance Data;

1.1.6. Record Documents; and

1.1.7. General Commissioning Requirements.

1.2. FORMAT

1.2.1. Binders: Contractor shall use commercial quality, 8-1/2 by 11 inch, three-side rings, with durable plastic covers; two inch maximum ring size. Contractor shall also provide all Warranties in pdf format on a thumb drive.

1.2.2. Cover: Contractor shall identify each binder with typed or printed title "WARRANTIES” and shall list the title of Project.

1.2.3. Table of Contents: Contractor shall provide the title of Project; name, address, and telephone number of Contractor and equipment supplier, and name of responsible principal. Contractor shall identify each item with the number and title of the specific Specification, document, provision, or section in which the name of the Product or Work item is specified.

1.2.4. Contractor shall separate each Warranty with index tab sheets keyed to the Table of Contents listing, providing full information and using separate typed sheets as necessary. Contractor shall list each applicable and/or responsible Subcontractor(s), supplier(s), and/or manufacturer(s), with name, address, and telephone number of each responsible principal(s).

1.2.5. In addition to all Warranty documentation and information required herein, Contractor shall provide its Guarantee as required by the Contract Documents.

1.3. PREPARATION

1.3.1. Contractor shall obtain Warranties, executed in duplicate by each applicable and/or responsible Subcontractor(s), supplier(s), and manufacturer(s), within ten (10) days after

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
WARRANTIES 01 78 36 - 2
completion of the applicable item or Work. Except for items put into use with City's permission, Contractor shall leave date of beginning of time of Warranty until the date of Completion is determined.

1.3.2. Contractor shall verify that Warranties.

1.3.3. are in proper form, contain full information, and are notarized, when required.

1.3.4. Contractor shall co-execute submittals when required.

1.3.5. Contractor shall retain warranties until time specified for submittal.

1.4. TIME OF SUBMITTALS

1.4.1. Schedule of Warranties. Contractor shall provide City with a Schedule of Warranties at least fourteen (14) days prior to submitting its other required submittals indicated herein. This will provide City the opportunity to review the anticipated Warranties and make any comments, suggestions or revisions the City may require.

1.4.2. For equipment or component parts of equipment put into service during construction with City's permission, Contractor shall submit a draft Warranty for that equipment or component within ten (10) days after acceptance of that equipment or component.

1.4.3. On or before the Contractor submits its final application for payment, Contractor shall submit all Warranties and related documents in final form. The City shall indicate any Warranty-related Work that is being performed and incomplete at the time Contractor submits its final application for payment. City will provide comments to Contractor and Contractor must revise the content of the Warranties as required by City prior to City's approval of Contractor’s final Application for Payment.

1.4.4. For items of Work that are not completed until after the date of Completion, Contractor shall provide an updated Warranty for those item(s) of Work within ten (10) days after acceptance, listing the date of acceptance as start of the Warranty period.

1.5. WARRANTY PERIOD

1.5.1. Prime Contractor

1.5.1.1. The blanket warranty period for all materials and workmanship for the entire project is one year (365 calendar days) from the Date of Substantial Completion as identified by the Owner.

1.5.1.2. This warranty period may be revised, modified, or enhanced by specific warranty requirements indicated within each Specification Section.

1.5.2. Subcontractors and Product Manufacturers or Suppliers

1.5.2.1. Workmanship and material warranties as indicated within each Specification Section.

END OF SECTION

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
RECORD DOCUMENTS 01 78 39 - 1
SECTION 01 78 39

RECORD DOCUMENTS

1. GENERAL

1.1. RELATED DOCUMENTS AND PROVISIONS
Contractor shall review all Contract Documents for applicable provisions related to the provisions in this document, including without limitation:

1.1.1. General Conditions, including, without limitation, Documents on Work and Completion of Work;

1.1.2. Supplementary Conditions (if any);

1.1.3. Submittals;

1.1.4. Contract Closeout and Final Cleaning;

1.1.5. Operation and Maintenance Data;

1.1.6. Warranties; and

1.1.7. General Commissioning Requirements.

2. RECORD DOCUMENTS OR DRAWINGS

2.1. GENERAL

2.1.1. “Record Documents” and “Record Drawings” may also be referred to in the Contract Documents as “As-Built Drawings.”

2.1.2. As indicated in the Contract Documents, in Procore, City will provide Contractor with one set of plans of the under Drawings Tool, for the purpose of tracking as-built modifications.

2.1.3. Contractor shall maintain at each Project Site one (1) set of marked-up Drawings and shall transfer all changes and information to those marked-up Drawings, as often as required in the Contract Documents, but in no case less than once each month, onto current version of drawings located under Drawings Tool for Project’s Listing in Procore.

Contractor shall submit to the Project Inspector one set of color copy of the Project Record Documents (“As-Builts”) showing all changes incorporated into the Work since the preceding monthly submittal. The As-Builts shall be available at the Project Site. The Contractor shall submit prints, color where necessary to distinguish, at the conclusion of the Project following review of the prints. Contractor shall also provide the “Record Drawings” or “Record Documents” in pdf format on a thumb drive.

2.1.4. Label and date each Record Document "RECORD DOCUMENT" in legibly printed letters.

2.1.5. All deviations in construction, including but not limited to pipe and conduit locations and deviations caused, without limitation, by Change Orders, Construction Directives, RFI’s, ASI’s and Addenda shall be accurately and legibly recorded by Contractor.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
RECORD DOCUMENTS 01 78 39 - 2

2.1.6. Locations and changes shall be done by Contractor in a neat and legible manner and, where applicable, indicated by drawing a "cloud" around the changed or additional information.

2.2. RECORD DOCUMENT INFORMATION

2.2.1. Contractor shall record the following information:

2.2.1.1. Locations of Work buried under or outside each building, including, without limitation, all utilities, plumbing and electrical lines, and conduits.

2.2.1.2. Actual numbering of each electrical circuit.

2.2.1.3. Locations of significant Work concealed inside each building whose general locations are changed from those shown on the Drawings.

2.2.1.4. Locations of all items, not necessarily concealed, which vary from the Contract Documents.

2.2.1.5. Installed location of all cathodic protection anodes.

2.2.1.6. Deviations from the sizes, locations, and other features of installations shown in the Contract Documents.

2.2.1.7. Locations of underground work, points of connection with existing utilities, changes in direction, valves, manholes, catch basins, capped stubouts, invert elevations, etc.

2.2.1.8. Sufficient information to locate Work concealed in each building with reasonable ease and accuracy.

2.2.2. In some instances, this information may be recorded by dimension. In other instances, it may be recorded in relation to the spaces in the building near which it was installed.

2.2.3. Contractor shall provide additional Drawings as necessary for clarification.

2.2.4. Contractor shall provide in an electronic format as indicated in the Contract Documents, a copy of the Drawings, made from final Shop Drawings marked "No Exceptions Taken" or "Approved as Noted."

2.2.4.1. With the City’s prior approval, Contractor may provide these reproducible Drawings in hard copy.

3. RECORD MATERIALS LOG

3.1.1. Materials Log shall be submitted prior to Completion.

3.1.2. Preparation: Mark Material Log to indicate the actual product installation where installation varies from that indicated in original Material Log.

3.1.3. Give particular attention to information on concealed materials and installations that cannot be readily identified and recorded later.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
RECORD DOCUMENTS 01 78 39 - 3

3.1.4. Mark copy with the proprietary name and characteristics of products, materials, and equipment furnished, including substitutions and product options selected.

3.1.5. Record the name of the manufacturer, supplier, installer, and other information necessary to provide a record of selections made.

3.1.6. The working copy of Materials Log shall be consistently maintained throughout construction, and shall be accessible at Project Site.

4. MAINTENANCE OF RECORD DOCUMENTS

4.1. Contractor shall store Record Documents apart from documents used for construction as follows:

4.1.1. Provide files and racks for storage of Record Documents.

4.1.2. Maintain Record Documents in a clean, dry, legible condition and in good order.

4.2. Contractor shall not use Record Documents for construction purposes.

END OF SECTION

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
UTILITY POTHOLING 02 20 00 - 1
SECTION 02 20 00

UTILITY POTHOLING
PART 1 -GENERAL

1.01 SUMMARY
A. Perform utility location as necessary for project improvements shown on the drawings and herein specified.

B. It is not the intent of the Plans to show the exact location of all existing or relocated utilities and the Engineer assumes no responsibility therefor. The position of the utilities shown on the Plans is derived from records of utility owners and limited utility locating services. The service connections to these utilities may be, but are not necessarily, shown on the drawings.

C. Overhead utilities including wires, poles and guys are not necessarily shown on the Plans and shall be determined from the Contractor's visit to the site.

D. It shall be the responsibility of the Contractor to determine the exact location of all utilities and service connections thereto ahead of any excavations through "potholing." The Contractor shall make his/her own investigations, including exploratory excavations, referenced herein as potholing, to determine the locations and type of existing utilities, including service connections, prior to commencing work which could result in damage to such utilities. The Contractor shall immediately notify the Engineer as to any utility discovered by him/her in a different position than shown on the drawings or which is not shown on the drawings.

1.02 RELATED WORK
A. Section 31 20 00 – Earthwork
B. Section 31 23 24 – Trench Excavation and Backfill
C. Section 33 10 00 – Water Utilities
D. Section 33 33 00 - Site Sanitary Sewerage System
E. Section 33 40 00 – Storm Drainage System

1.03 QUALITY ASSURANCE
A. Comply with all applicable local, state, and federal requirements regarding materials, methods of work, and disposal of excess and waste materials.

B. Obtain and pay of all required inspections, permits, and fees. Provide notices required by governmental authorities.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
UTILITY POTHOLING 02 20 00 - 2
PART 2 - PRODUCTS

2.01 MATERIALS
Provide materials, not specifically described but required for a complete and proper execution of work of this Section, as selected by Contractor subject to approval of Owner's Representative.

PART 3 - EXECUTION

3.01 GENERAL
A. Prior to setting grades or commencing any trenching or excavation work, the Contractor shall contact all affected utility owners and request them to locate and mark the location of their respective utilities on the ground. The Contractor shall then undertake "potholing" procedures as described herein below.

B. Methodology for potholing shall be determined by location and shall be approved by the Engineer prior to starting work. Potholing methodology shall not disturb surrounding facilities, pavements, structures, vegetation, or other existing elements beyond what is necessary for the potholing location.

C. If a utility owner is not equipped to provide the locating service, the Contractor shall provide for it. The location of said underground pipes and conduits shall be clearly marked on the pavement or with suitable markers if not on pavement. In addition to the location of metallic pipes and conduits, non-metallic pipe, ducts and conduits shall also be similarly located using surface indicators and shall then be similarly marked.

D. As soon as the utility survey is completed, and prior to setting grades or commencing fabrication of engineered pipe, the Contractor shall commence "potholing" to determine the actual location of the pipe, duct or conduit. The Contractor shall uncover all underground utilities, including sewers and storm drains, exercising extreme care so as to avoid drainage. It will be the Contractor’s responsibility to have repairs made to existing facilities at his/her expense in the event of damage. Underground utilities shall be uncovered to a point one (1) foot below the pipe or as directed by the Engineer, where crossing, interferences or connections are shown on the drawings, prior to the preparation of shop drawings, trenching or excavating for any pipe or structure, in order to determine actual elevations. Once uncovered, the Contractor shall record the depth of the utility at the pothole and clearly mark the depth on the pavement. Any variation in the actual elevations and the indicated elevations shall be brought to the Engineer's attention.

E. Excavations around underground electrical ducts and conduits shall be performed using extreme caution to prevent injury or damage to workers and the electrical ducts or conduits. Similar precautions shall be exercised around gas line, telephone, and television cables.

F. Where an underground utility is at variance with the Plans the contractor shall proceed as follows:

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
UTILITY POTHOLING 02 20 00 - 3
• Marked utility not shown on the Plans: If a utility is not shown on the Plans but marked in the field by the utility owner, the Contractor shall pothole the utility and proceed with the work providing the utility is not in conflict with the line or grade of the pipeline to be laid and report the discrepancy to the District.
• Utility shown on the Plans but not marked: If a utility is shown on the Plans, but not marked by the utility company or marked in a different location, then the Contractor shall consult with the utility company, pothole the utility, and then proceed with the work providing the utility is not in conflict with the foundation or grade of the pipeline to be laid.
• Unmarked utility: If a utility is not marked by the utility company and the contractor encounters it, then the contractor shall immediately notify the District and the utility company. The Contractor shall proceed with the work if the utility is not in conflict with the line or grade of the pipeline to be installed.

G. After the need for potholing is complete, the Contractor shall backfill the potholing location.

END OF SECTION 02 20 00

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
UTILITY POTHOLING 02 20 00 - 4
This Page Intentionally Left Blank

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
DEMOLITION 02 41 00 - 1
SECTION 02 41 00

DEMOLITION
PART 1 -GENERAL

1.01 SUMMARY
A. Perform demolition work as shown on the drawings and herein specified.

The work includes:

1. Protecting existing trees to remain.

2. Removing bark, grasses and other vegetation.

3. Removing designated site improvements.

4. Protection of on-site utilities.

5. Selective removal of site paving.

1.02 RELATED WORK
A. Section 31 10 13 – Site Preparation and Plant Protection B. Section 31 20 00 - Earthwork

1.03 QUALITY ASSURANCE
A. Comply with all applicable local, state, and federal requirements regarding materials, methods of work, and disposal of excess and waste materials.

B. Obtain and pay of all required inspections, permits, and fees. Provide notices required by governmental authorities.

1.04 PROJECT CONDITIONS
A. Perform demolition work before commencing site construction.

B. Locate and identify existing underground and overhead services and utilities within contract limit work areas. Provide adequate means of protection of utilities and services not designated for removal.

C. Provide necessary barricades, coverings, bracing, shorting, signs, lights and protection required to provide public safety and to prevent damage to existing improvements indicated to remain.

D. Restore to original grades and conditions, areas adjacent to site disturbed or damaged as a result of demolition work.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
DEMOLITION 02 41 00 - 2
PART 2 - PRODUCTS

2.01 MATERIALS
Provide materials, not specifically described but required for a complete and proper execution of work of this Section, as selected by Contractor subject to approval of Owner's Representative.

PART 3 - EXECUTION

3.01 INSPECTION
A. Examine the substrate under with demolition work is to be done. Notify the Owner's Representative, in writing of conditions detrimental to the proper and timely completion of the work.

B. Prior to starting demolition, make an inspection and report observable defects and structural weaknesses of structures designated for removal, of adjacent structures, and of other improvements to remain.

3.02 STRIPPING AND GRUBBING
A. Specified in Section 31 20 00 – Earthwork
B. Section 31 10 13 – Site Preparation and Plant Protection

3.03 GENERAL
A. Remove existing improvements as required to accommodate new construction whether or not indicated on the drawings and herein specified
B. Remove materials carefully, providing for neat and structurally sound junctions between existing buildings, structures, facilities, utilities, trees and other plant materials to remain at no additional cost to the Owner.

3.04 PROTECTION OF EXISTING TREES – see Section 31 10 13 A. Protect existing trees scheduled to remain against injury or damage, including cutting, breaking, or skinning of roots, trunks or branches; smothering by stockpiled construction materials, excavated materials or vehicular traffic within the dripline.

3.05 EXISTING UTILITIES
A. Arrange for disconnection, disconnect and seal or cap all utilities and services designated to be abandoned and/or removed before start of site work operations.

Perform all work in accordance with the requirements of the applicable utility company or agency involved.

B. Adjust electrical, irrigation, valve boxes or any other existing structures to meet new grades

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
DEMOLITION 02 41 00 - 3

3.06 CLEARING
A. Locate and identify trees and improvements indicated to remain.

B. Remove plants undergrowth, other vegetation, and debris, except items indicated to remain.

C. Remove fence and applicable foundations as indicated in the plan. Backfill foundation with native soil or as approved by the Engineer.

3.07 ASPHALT MILLING
A. Mill and remove existing asphalt paving as required to accommodate new asphalt paving.

B. Saw-cut existing asphaltic concrete paving in neat, straight lines to provide uniform, even transition from new to adjacent existing work.

3.08 BACKFILLING
A. Backfill any below grade voids created by demolition work as specified for backfill in Section 31 20 00 - Earthwork.

3.09 DISPOSAL OF WASTE MATERIALS
A. Stockpile, haul from site, and legally dispose of waste materials and debris.

Accumulation is not permitted.

B. Maintain disposal routes clear, clean, and free of debris.

3.10 SALVAGED EQUIPMENT - None

3.11 CLEANOUT
A. Upon completion of site preparation work, clean areas within contract limits, remove tools, and equipment. Provide site clear, clean and free of materials and debris and suitable for site work operations.

END OF SECTION 02 41 00

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
DEMOLITION 02 41 00 - 4
This Page Intentionally Left Blank

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CAST-IN-PLACE CONCRETE 03 30 00 - 1
DOCUMENT 03 30 00

CAST-IN-PLACE CONCRETE
PART 1 GENERAL

1.01 SUMMARY
A. This Section includes:
(1) Concrete flush curbs
(2) Concrete footings
(3) Concrete slab
(4) Concrete stage

1.02 RELATED WORK
A. Related Sections include the following:
(1) Section 11 68 13 “Playground Equipment”
(2) Section 12 93 00 “Site Furnishings” for benches
(3) Section 31 00 00 "Earthwork"
(4) Section 32 84 00 “Irrigation” for sleeving
(5) Section 32 18 16 “Playground Protective Surfacing”

1.03 ACTION SUBMITTALS
A. General: In addition to the following, comply with submittal requirements in ACI 301.

B. Product Data: For each type of product indicated.
(1) Curing compound: Complete technical data
C. Design Mixtures: For each concrete mixture. Submit alternate design mixtures when characteristics of materials, project conditions, weather, test results, or other circumstances warrant adjustments.
(1) Indicate amounts of mixing water to be withheld for later addition at Project site.

D. Formwork Shop Drawings: Prepared by or under the supervision of a qualified professional engineer detailing fabrication, assembly, and support of formwork.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CAST-IN-PLACE CONCRETE 03 30 00 - 2

1.04 INFORMATIONAL SUBMITTALS
A. Qualification Data: For installer and manufacturer
B. Material Certificates: For each of the following, signed by manufacturers:
(1) Cementitious materials.
(2) Admixtures.
(3) Form materials and form-release agents.
(4) Steel reinforcement and accessories.
(5) Curing compounds.
(6) Bonding agents.
(7) Vapor retarders.
(8) Semirigid joint filler.
(9) Joint-filler strips.
(10) Repair materials.

C. Field quality-control reports.

1.05 QUALITY ASSURANCE
A. Installer Qualifications: A qualified installer who employs on Project personnel qualified as ACI-certified Flatwork Technician and Finisher and a supervisor who is an ACI-certified Concrete Flatwork Technician.

B. Manufacturer Qualifications: A firm experienced in manufacturing ready-mixed concrete products and that complies with ASTM C 94/C 94M requirements for production facilities and equipment.

C. Testing Agency Qualifications: An independent agency, acceptable to authorities having jurisdiction, qualified according to ASTM C 1077 and ASTM E 329 for testing indicated.

D. Welding Qualifications: Qualify procedures and personnel according to AWS D1.4/D 1.4M.

E. Source Limitations: Obtain each type of cement of the same brand from the same manufacturer's plant, obtain aggregate from one source, and obtain admixtures through one source from a single manufacturer.

F. Comply with ACI 301, "Specification for Structural Concrete," including the following sections, unless modified by requirements in the Contract Documents:

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CAST-IN-PLACE CONCRETE 03 30 00 - 3
(1) "General Requirements."
(2) "Formwork and Formwork Accessories."
(3) "Reinforcement and Reinforcement Supports."
(4) "Concrete Mixtures."
(5) "Handling, Placing, and Constructing."
G. Comply with ACI 117, "Specifications for Tolerances for Concrete Construction and Materials."

1.06 PREINSTALLATION CONFERENCE
A. Conduct conference at Project site. Notify Landscape Architect for inspection of formwork and reinforcing steel placing a minimum of 5 working days prior to pouring concrete.

B. Review methods and procedures related to concrete cast-in-place work, including but not limited to, the following:
(1) Concrete mixture design.
(2) Quality control of concrete materials and concrete construction practices.

C. Inspect on site related to concrete cast-in-place work but on limited to, the following:
(1) Formwork and reinforcing steel placement.

1.07 PRECONSTRUCTION TESTING
A. Preconstruction Testing Service: Engage a qualified testing agency to perform preconstruction testing on concrete mixtures.

1.08 DELIVERY, STORAGE, AND HANDLING
A. Steel Reinforcement: Deliver, store, and handle steel reinforcement to prevent bending and damage. Avoid damaging coatings on steel reinforcement.

1.09 FIELD CONDITIONS
A. Cold-Weather Placement: Comply with ACI 306.1 and as follows. Protect concrete work from physical damage or reduced strength that could be caused by frost, freezing actions, or low temperatures.
(1) When average high and low temperature is expected to fall below 40 deg F for three successive days, maintain delivered concrete mixture temperature within the temperature range required by ACI 301.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CAST-IN-PLACE CONCRETE 03 30 00 - 4
(2) Do not use frozen materials or materials containing ice or snow. Do not place concrete on frozen subgrade or on subgrade containing frozen materials.
(3) Do not use calcium chloride, salt, or other materials containing antifreeze agents or chemical accelerators unless otherwise specified and approved in mixture designs.

B. Hot-Weather Placement: Comply with ACI 301 and as follows:
(1) Maintain concrete temperature below 90 deg F at time of placement.

Chilled mixing water or chopped ice may be used to control temperature, provided water equivalent of ice is calculated to total amount of mixing water. Using liquid nitrogen to cool concrete is Contractor's option. (2) Fog-spray forms, steel reinforcement, and subgrade just before placing concrete. Keep subgrade uniformly moist without standing water, soft spots, or dry areas.

PART 2 PRODUCTS

2.01 CONCRETE, GENERAL
A. ACI Publications: Comply with the following unless modified by requirements in the Contract Documents:
(1) ACI 301
(2) ACI 117

2.02 FORM-FACING MATERIALS
A. Rough-Formed Finished Concrete: Plywood, lumber, metal, or another approved material. Provide lumber dressed on at least two edges and one side for tight fit.

B. Radius Strips: Wood, metal, PVC, or rubber strips, 1/2 inch minimum.

C. Rustication Strips: Wood, metal, PVC, or rubber strips, kerfed for ease of form removal.

D. Form-Release Agent: Commercially formulated form-release agent that does not bond with, stain, or adversely affect concrete surfaces and does not impair subsequent treatments of concrete surfaces.
(1) Formulate form-release agent with rust inhibitor for steel form-facing materials.

E. Form Ties: Factory-fabricated, removable or snap-off glass-fiber-reinforced plastic or metal form ties designed to resist lateral pressure of fresh concrete on forms and to prevent spalling of concrete on removal.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CAST-IN-PLACE CONCRETE 03 30 00 - 5
(1) Furnish units that leave no corrodible metal closer than 1 inch to the plane of exposed concrete surface.

2.03 FORMWORK
A. Furnish formwork and formwork accessories according to ACI 301.

2.04 STEEL REINFORCEMENT
A. Reinforcing Bars: ASTM A 615/A 615M, Grade 60 (Grade 420), deformed.

B. Recycled Content of Steel Products: Postconsumer recycled content plus onehalf of preconsumer recycled content not less than 25 percent.

2.05 REINFORCEMENT ACCESSORIES
A. Joint Dowel Bars: ASTM A 615/A 615M, Grade 60, plain-steel bars, cut true to length with ends square and free of burrs.

B. Bar Supports: Bolsters, chairs, spacers, and other devices for spacing, supporting, and fastening reinforcing bars and welded-wire reinforcement in place. Manufacture bar supports from steel wire, plastic, or precast concrete according to CRSI's "Manual of Standard Practice," of greater compressive strength than concrete .

2.06 CONCRETE MATERIALS
A. Regional Materials: Materials: Concrete shall be manufactured within 500 miles of Project site from aggregates and cementitious materials that have been extracted, harvested, or recovered, as well as manufactured, within 500 miles of Project site.

B. Source Limitations: Obtain each type or class of cementitious material of the same brand from the same manufacturer's plant, obtain aggregate from single source, and obtain admixtures from single source from single manufacturer.

C. Cementitious Material: Use the following cementitious materials, of the same type, brand, and source throughout Project:
(1) Portland Cement: ASTM C 150/C 150M, Type I, gray.
(2) Fly Ash: ASTM C 618, Class C or F.
(3) Slag Cement: ASTM C 989/C 989M, Grade 100 or 120.
(4) Blended Hydraulic Cement: ASTM C 595/C 595M, Type IS, portland blast- furnace slag cement.
(5) Silica Fume: ASTM C 1240, amorphous silica.

D. Normal-Weight Aggregate: ASTM C 33, graded.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CAST-IN-PLACE CONCRETE 03 30 00 - 6
(1) Maximum Coarse-Aggregate Size: 3/4 inch nominal.
(2) Fine Aggregate: Free of materials with deleterious reactivity to alkali in cement.

E. Water: ASTM C 94/C 94M and potable

2.07 ADMIXTURES
A. Air-Entraining Admixture: ASTM C 260/C 260M.

B. Chemical Admixtures: Certified by manufacturer to be compatible with other admixtures and that do not contribute water-soluble chloride ions ions exceeding those permitted in hardened concrete. Do not use calcium chloride or admixtures containing calcium chloride.
(1) Water-Reducing Admixture: ASTM C 494/C 494M, Type A. (2) Retarding Admixture: ASTM C 494/C 494M, Type B.
(3) Water-Reducing and Retarding Admixture: ASTM C 494/C 494M, Type D.

C. Integral Color: Natural Gray

2.08 CURING MATERIALS
A. Evaporation Retarder: Waterborne, monomolecular film forming, manufactured for application to fresh concrete.

B. Absorptive Cover: AASHTO M 182, Class 2, burlap cloth made from jute or kenaf, weighing approximately 9 oz./sq. yd. when dry.

C. Moisture-Retaining Cover: ASTM C 171, polyethylene film or white burlappolyethylene sheet.

D. Water: Potable.

2.09 RELATED MATERIALS
A. Expansion- and Isolation-Joint-Filler Strips: ASTM D 1751, asphalt-saturated cellulosic fiber.

B. Semirigid Joint Filler: Two-component, semirigid, 100 percent solids, epoxy resin with a Type A shore durometer hardness of 80 according to ASTM D 2240.

C. Bonding Agent: ASTM C 1059/C 1059M, Type II, nonredispersible, acrylic emulsion or styrene butadiene.

D. Epoxy Bonding Adhesive: ASTM C 881, two-component epoxy resin, capable of humid curing and bonding to damp surfaces, of class suitable for application temperature and of grade to suit requirements, and as follows:

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CAST-IN-PLACE CONCRETE 03 30 00 - 7
(1) Types I and II, non-load bearing, for bonding hardened or freshly mixed concrete to hardened concrete.

E. Dovetail Anchor Slots: Hot-dip galvanized-steel sheet, not less than 0.034 inch thick, with bent tab anchors. Temporarily fill or cover face opening of slots to prevent intrusion of concrete or debris.

2.10 CONCRETE MIXTURES
A. Comply with ACI 301 requirements for concrete mixtures.

B. Normal-Weight Concrete: Prepare design mixes, proportioned according to ACI 301, as follows:
(1) Minimum Compressive Strength: 3500 psi at 28 days.
(2) Maximum W/C Ratio: 0.50
(3) Slump Limit: 5 inches, plus or minus 1 inch.
(4) Air Content: Maintain within range permitted by ACI 301. Do not allow air content of floor slabs to receive troweled finishes to exceed 3 percent.

2.11 CONCRETE MIXING
A. Ready-Mixed Concrete: Measure, batch, mix, and deliver concrete according to ASTM C 94/C 94M, and furnish batch ticket information.

B. Project-Site Mixing: Project site mixing is acceptable for fence post footings.

Measure, batch, and mix concrete materials and concrete according to ASTM C 94/C 94M. Mix concrete materials in appropriate drum-type batch machine mixer. (1) For mixer capacity of 1 cu. yd. or smaller, continue mixing at least 1-1/2 minutes, but not more than 5 minutes after ingredients are in mixer, before any part of batch is released.
(2) For mixer capacity larger than 1 cu. yd., increase mixing time by 15 seconds for each additional 1 cu. yd.
(3) Provide batch ticket for each batch discharged and used in the Work, indicating Project identification name and number, date, mix type, mix time, quantity, and amount of water added. Record approximate location of final deposit in structure.

PART 3 EXECUTION

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CAST-IN-PLACE CONCRETE 03 30 00 - 8

3.01 FORMWORK
A. Design, construct, erect, brace, and maintain formwork according to ACI 301 to support vertical, lateral, static, and dynamic loads, and construction loads that might be applied, until structure can support such loads.

B. Limit concrete surface irregularities, designated by ACI 347 as abrupt or gradual, as follows:
(1) Class A, 1/8 inch for smooth-formed finished surfaces.

C. Construct forms tight enough to prevent loss of concrete mortar.

D. Fabricate forms for easy removal without hammering or prying against concrete surfaces. Provide crush or wrecking plates where stripping may damage cast concrete surfaces. Provide top forms for inclined surfaces steeper than 1.5 horizontal to 1 vertical.
(1) Install keyways, reglets, recesses, and the like, for easy removal. (2) Do not use rust-stained steel form-facing material.

E. Set edge forms, bulkheads, and intermediate screed strips for slabs to achieve required elevations and slopes in finished concrete surfaces. Provide and secure units to support screed strips; use strike-off templates or compacting-type screeds.

F. Provide temporary openings for cleanouts and inspection ports where interior area of formwork is inaccessible. Close openings with panels tightly fitted to forms and securely braced to prevent loss of concrete mortar. Locate temporary openings in forms at inconspicuous locations.

G. Form openings, chases, offsets, sinkages, keyways, reglets, blocking, screeds, and bulkheads required in the Work. Determine sizes and locations from trades providing such items.

H. Clean forms and adjacent surfaces to receive concrete. Remove chips, wood, sawdust, dirt, and other debris just before placing concrete.

I. Retighten forms and bracing before placing concrete, as required, to prevent mortar leaks and maintain proper alignment.

J. Coat contact surfaces of forms with form-release agent, according to manufacturer's written instructions, before placing reinforcement.

3.02 REMOVING AND REUSING FORMS
A. General: Formwork for sides of beams, walls, columns, and similar parts of the Work that does not support weight of concrete may be removed after cumulatively curing at not less than 50 deg F for 24 hours after placing concrete.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CAST-IN-PLACE CONCRETE 03 30 00 - 9
Concrete has to be hard enough to not be damaged by form-removal operations and curing and protection operations need to be maintained. (1) Leave formwork for slabs and other structural elements that support weight of concrete in place until concrete has achieved at least 70 percent of its 28-day design compressive strength.
(2) Remove forms only if shores have been arranged to permit removal of forms without loosening or disturbing shores.

B. Clean and repair surfaces of forms to be reused in the Work. Split, frayed, delaminated, or otherwise damaged form-facing material are not acceptable for exposed surfaces. Apply new form-release agent.

C. When forms are reused, clean surfaces, remove fins and laitance, and tighten to close joints. Align and secure joints to avoid offsets. Do not use patched forms for exposed concrete surfaces unless approved by Landscape Architect.

3.03 EMBEDDED ITEMS
A. Place and secure anchorage devices and weep holes and other embedded items required for adjoining work that is attached to or supported by cast-in-place concrete. Use setting drawings, templates, diagrams, instructions, and directions furnished with items to be embedded.

3.04 STEEL REINFORCEMENT
A. Comply with CRSI's "Manual of Standard Practice" for fabricating, placing, and supporting reinforcement. Clean reinforcement of loose rust and mill scale, earth, ice, or other bond-reducing materials.

B. Arrange, space, and securely tie bars and bar supports to hold reinforcement in position during concrete placement. Maintain minimum cover to reinforcement.

C. Accurately position, support, and secure reinforcement against displacement.

Locate and support reinforcement with bar supports to maintain minimum concrete cover. Do not tack weld crossing reinforcing bars. (1) Weld reinforcing bars according to AWS D1.4/D 1.4M, where indicated.

D. Set wire ties with ends directed into concrete, not toward exposed concrete surfaces.

E. Install welded-wire reinforcement in longest practicable lengths on bar supports spaced to minimize sagging. Lap edges and ends of adjoining sheets at least one mesh spacing. Offset laps of adjoining sheet widths to prevent continuous laps in either direction. Lace overlaps with wire.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CAST-IN-PLACE CONCRETE 03 30 00 - 10

3.05 CONCRETE PLACEMENT
A. Comply with ACI 301 for measuring, batching, mixing, transporting, and placing concrete.

B. Before test sampling and placing concrete, water may be added at Project site, subject to limitations of ACI 301.

3.06 JOINTS
A. General: Construct joints true to line with faces perpendicular to surface plane of concrete.

B. Construction Joints: Install so strength and appearance of concrete are not impaired, at locations indicated or as approved by Engineer.

C. Place joints perpendicular to main reinforcement. Continue reinforcement across construction joints unless otherwise indicated. Do not continue reinforcement through sides of strip placements of slabs.
(1) Locate horizontal joints in walls and at the top of footings or slabs. (2) Use a bonding agent at locations where fresh concrete is placed against hardened or partially hardened concrete surfaces
(3) Use epoxy bonding adhesive at locations where fresh concrete is placed against hardened or partially hardened concrete surfaces D. Contraction Joints: Form weakened-plane contraction joints, sectioning concrete into areas as indicated. Construct contraction joints for a depth equal to at least one-fourth of concrete thickness as follows:
(1) Grooved Joints: Form contraction joints after initial floating by grooving and finishing each edge of joint to a radius of 1/8 inch. Repeat grooving of contraction joints after applying surface finishes. Eliminate groover tool marks on concrete surfaces.

E. Doweled Joints: Install dowel bars and support assemblies at joints where indicated. Lubricate or asphalt coat one-half of dowel length to prevent concrete bonding to one side of joint.

3.07 JOINT FILLING
A. Prepare, clean, and install joint filler according to manufacturer's written instructions.

B. ACI 302.1R recommends joint filling be deferred as long as possible in concrete slabs. Use of polyurea joint fillers may allow joint filling to proceed earlier; verify minimum time period with manufacturer. Typically, up to 30 percent of concrete shrinkage takes place in first month, with 80 to 90 percent during first 12 months.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CAST-IN-PLACE CONCRETE 03 30 00 - 11
(1) Defer joint filling until concrete has aged at least one month. Do not fill joints until construction traffic has permanently ceased.

C. Remove dirt, debris, saw cuttings, curing compounds, and sealers from joints; leave contact faces of joints clean and dry.

D. Install semirigid joint filler full depth in saw-cut joints and at least 2 inches deep in formed joints. Overfill joint and trim joint filler flush with top of joint after hardening.

3.08 FINISHING FORMED SURFACE
A. Broom Finish: immediately after float finishing, slightly roughen trafficked surface by brooming with fiber-bristle broom perpendicular to main traffic route. Apply broom finish as indicated on drawings

3.09 CONCRETE PROTECTING AND CURING
A. General: Protect freshly placed concrete from premature drying and excessive cold or hot temperatures.

B. Comply with ACI 306.1 for cold-weather protection.

C. Evaporation Retarder: Apply evaporation retarder to concrete surfaces if hot, dry, or windy conditions cause moisture loss approaching 0.2 lb/sq. ft. x h before and during finishing operations. Apply according to manufacturer's written instructions after placing, screeding, and bull floating or darbying concrete but before float finishing.

D. Begin curing after finishing concrete but not before free water has disappeared from concrete surface.

E. Curing Methods: Cure concrete according to ACI 308.1 by moisture curing as follows:
(1) Moisture Curing: Keep surfaces continuously moist for not less than seven days with the following materials:
(a) Water.
(b) Continuous water-fog spray.
(c) Absorptive cover, water saturated and kept continuously wet.

Cover concrete surfaces and edges with 12-inch lap over adjacent absorptive covers.
(2) Curing Compound: Apply uniformly in continuous operation by power spray or roller according to manufacturer's written instructions. Recoat areas that have been subjected to heavy rainfall within three hours after initial application. Maintain continuity of coating, and repair damage during curing period.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CAST-IN-PLACE CONCRETE 03 30 00 - 12
F. General: Protect freshly placed concrete from premature drying and excessive cold or hot temperatures. Comply with ACI 306.1 for cold-weather protection and with ACI 301 for hot-weather protection during curing.

3.10 CONCRETE SURFACE REPAIRS
A. Defective Concrete: Repair and patch defective areas when approved by Landscape Architect. Remove and replace concrete that cannot be repaired and patched to Landscape Architect's approval.

B. Patching Mortar: Mix dry-pack patching mortar, consisting of 1 part portland cement to 2-1/2 parts fine aggregate passing a No. 16 sieve, using only enough water for handling and placing.

C. Repairing Formed Surfaces: Surface defects include color and texture irregularities, cracks, spalls, air bubbles, honeycombs, rock pockets, fins and other projections on the surface, and stains and other discolorations that cannot be removed by cleaning.
(1) Immediately after form removal, cut out honeycombs, rock pockets, and voids more than 1/2 inch in any dimension to solid concrete. Limit cut depth to 3/4 inch. Make edges of cuts perpendicular to concrete surface. (2) Clean, dampen with water, and brush-coat holes and voids with bonding agent. Fill and compact with patching mortar before bonding agent has dried. Fill form-tie voids with patching mortar or cone plugs secured in place with bonding agent.
(3) Repair defects on surfaces exposed to view by blending white portland cement and standard portland cement so that, when dry, patching mortar matches surrounding color. Patch a test area at inconspicuous locations to verify mixture and color match before proceeding with patching.

Compact mortar in place and strike off slightly higher than surrounding surface.
(4) Repair defects on concealed formed surfaces that affect concrete's durability and structural performance as determined by Landscape Architect.

D. Repair materials and installation not specified above may be used, subject to Landscape Architect's approval.

3.11 FIELD QUALITY CONTROL
A. Special Inspections: Engage a special inspector and qualified testing agency to perform field tests and inspections and prepare test reports as required for play equipment footings.

B. Concrete Tests: Testing of composite samples of fresh concrete obtained according to ASTM C 172/C 172M shall be performed according to the following requirements:

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
CAST-IN-PLACE CONCRETE 03 30 00 - 13
(1) Slump: ASTM C 143/C 143M; one test at point of placement for each composite sample, but not less than one test for each day's pour of each concrete mixture. Perform additional tests when concrete consistency appears to change.

C. Measure surface flatness and levelness according to ASTM E 1155 within 48 hours of finishing.

END OF SECTION 03 30 00

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SITE BOULDERS 04 41 00 - 1
SECTION 04 41 00

SITE BOULDERS
PART 1 - GENERAL

1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY
A. This Section includes the following: Supply skilled experienced labor, materials, and equipment required to install:

1. Site Boulder placements
B. Related Sections include the following:

1. Section 31 20 00 “Earthwork”

2. Section 03 30 00 “CIP Concrete” for integration with flush curbs

1.3 DEFINITIONS
A. Site Boulders, Boulders, and Stone, are all imported stone from O.R. approved quarry, stone purveyor, or local stone yard. Site Boulders, Boulders, and Stone are synonymous terms.

1.4 SUBMITTALS
A. Provide samples of all proposed stone types, sizes, color, quantities, gradation, and sources to O.R. prior to ordering. Boulder samples shall be submitted as photographs clearly depicting the size, form, surface texture, and tone.

B. Provide O.R. the source and personnel contact for site boulders 30 days prior to initial boulder selection quarry visit. Submit a complete quarry site boulder selection, procurement, delivery, and installation schedule to O.R. for review and approval prior to initial boulder selection quarry visit. See section 3.3 below.

C. Mock‐ups: Provide on‐site mock‐ups for the Site Boulder Placements, for review and approval prior to initiating site boulder installation process. Successfully approved mock‐up elements may be incorporated into the final site products if the installation meets the Plans and Specifications and if prior approval for incorporation of the mock‐up is received from O.R.:

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SITE BOULDERS 04 41 00 - 2

1.5 INSPECTION
A. The Contractor shall obtain site boulder approval from O.R. of the following prior to proceeding with installation:

1. Approval of site boulder submittal and mock-ups

2. Preparation of the sub‐grade to accept site boulders

3. Coordination of installation and scheduling between all site improvements and site boulders. Including but not limited to pavements, boardwalks, logs, site furnishings, play equipment, planting.

1.6 QUALITY ASSURANCE
A. Comply with California Department of Transportation (Caltrans) Standard Specifications, latest edition.

B. Pre‐construction Meeting: Conduct meeting at Project Site to comply with specified requirements.

C. Ensure stone placement personnel and equipment meets the requirements of the Specifications for type and experience level. Personnel shall be expert site boulder setters, with a minimum of 5 years of detail site boulder setting work. Contractor shall provide necessary equipment, per Specifications, to stage and supply the materials, and complete the specified work

1.7 DELIVERY, STORAGE, AND HANDLING
A. Deliver products to the project site in undamaged condition.

B. Store and handle site boulders and related materials to prevent deterioration or damage due to vandalism, moisture, temperature changes, contaminants, corrosion, breaking, chipping and other causes.

C. Store site boulders in an O.R. approved site area where no damage to existing soils or vegetation to remain will occur.

1.8 PROJECT CONDITIONS
A. Weather:

1. Cold—Do not initiate work if temperatures drop or are projected to drop below freezing 32 degrees F.

2. Wet Soils—Do not proceed with site boulder setting if the site subgrade has been subjected to significant rain (1/2-inch/day) or exhibits poorly drained soil conditions.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SITE BOULDERS 04 41 00 - 3
PART 2 - MATERIALS

2.1 SITE BOULDERS
A. Procuring stone from more than one source quarry or stone supply yard is not acceptable.

B. Site Boulders shall be sourced within 100 miles of the project.

C. Site Boulders shall tend to smooth angular and rounded forms and shall be selected by O.R. for suitability at the quarry. Sharp, angular, scarred, spalled, chipped, or broken boulders shall not be accepted for use.

D. Site Boulders shall be integrated into some of the site improvements flatwork as noted on the Plans and per O.R. direction.

E. Site Boulders selection site visits shall be coordinated by the quarry or stone supply yard representative, Contractor, and O.R.

F. Site Boulder sizes and quantities shall be set by the Plan requirements. O.R. reserves right to adjust locations of site boulders and site boulder sizes and size range. Boulder size range shall be determined by O.R. at source quarry, and are subject to change at the quarry. Overall site boulder tonnage shall not change without compensation to Contractor.

PART 3 - EXECUTION

3.1 SUBGRADE PREPARATION
A. Refer to Earthwork Specification
B. Areas where Site Boulders are to be placed shall be graded to elevations shown on the Plans. The soil surface shall be smooth and free from any obstructions to provide adequate contact area between the soil and site boulder or boulder base.

3.2 SITE BOULDER PLACEMENTS IN FIELD
A. Locations for boulders shown on Plan are approximate. Contractor shall notify O.R. at least 72-hours in advance of scheduled delivery and/or placement and ensure O.R. has appropriate lead time to schedule on-site layout with Contractor.

B. Site Boulder placement shall proceed only under direct observation by O.R.

Observation by O.R. shall be scheduled and facilitated for the setting of all Site Boulder placements noted on the Plans and in these Specifications. No boulders shall be placed by Contractor without direct observation by O.R.

C. Pre‐stage all Site Boulders throughout site in preparation for O.R. observation on-site.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SITE BOULDERS 04 41 00 - 4
D. Contractor shall assume a minimum of 1 working day of direct observation by O.R.

Contractor shall staff site boulder setting days with at least two complete crews of (2) laborers and (1) specified excavator. Additional days will be required if insufficient worker or machinery are staged for the placement work.

E. Prepare site to accept Site Boulders as described on the Plans and as directed by O.R. in field. Verify placement locations and site boulder specimen and size with O.R., prior to installation. Site Boulders shall be placed during rough site grading, before fine grading is initiated.

F. Contractor shall provide two experienced and skilled site boulder setting operator and crews.

G. Contractor shall provide large-scale excavator machinery capable of lifting and moving into place all specified boulders. Large-scale, track-driven excavators shall be utilized with articulating (300°) thumb attached buckets capable of lifting all specified boulders (up to 8-tons), and placing them under direction of O.R. Slings, Forklifts, backhoes, loaders, and dozers are not acceptable machines for placing site boulders.

H. Site Boulders shall be expertly set to ensure a high quality “garden level” of workmanship. O.R. reserves the right to relocate, and adjust all boulders on site within reason. Ensure tight, permanent fit between adjacent boulders and any existing bedrock.

I. Site Boulder placement work shall not disturb existing site unless approved by O.R.

Protect the existing site and vegetation as noted in the specifications.

3.3 CLEAN‐UP
A. Prepare wash‐out area away from project site as directed on‐site with O.R. No wash‐out or material dumping of any kind shall be allowed in an area designated for revegetation.

B. Keep site in a clean, orderly state throughout the work. Maintain site per O.R.’s requirements and as noted in the project Specifications.

END OF SECTION 04 41 00

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
METAL FABRICATIONS 05 50 00 - 1
SECTION 055000

METAL FABRICATIONS
PART 1 - GENERAL

1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY
A. Section Includes:

1. Architectural Steel (comply with National Association of Architectural Metal Manufacturers, NAAMM standards)

2. Guardrails
B. Products furnished, but not installed, under this Section:

1. Anchor bolts indicated to be cast into concrete or built into unit masonry.

2. Steel weld plates and angles for casting into concrete for applications where they are not specified in other Sections.

C. Related Sections:

1. Section 03 30 00 "CIP Concrete"

1.3 PERFORMANCE REQUIREMENTS
A. Design Concept: Metal Fabrication requirements shown by the drawings are intended to establish basic dimensions, alignment of members, profiles of members and relationship of items to other structural components.

1. Engineering Requirements: Engineer the designated items, including supporting members, connections and anchorage to wall structure, including any necessary additions and modifications to any specified propriety system manufacture’s standard details as may be required, to comply with specified performance requirements while maintaining the basic design concept.

B. Performance Requirements: Comply with Reference Standards, requirements of Governing Authorities and requirements specified herein.

1. Structural:

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
METAL FABRICATIONS 05 50 00 - 2
a. Wind Load: As required by Governing Authorities for applicable heights. b. Horizontal Force: 20 psf minimum, but not less than requirements of Governing Authorities.

2. Screens, fences and Similar Open Assemblies: Assume 20 psf over full height and width of screen (no open area).
a. Maximum Deflection of Members:
1) Simple Span: 1/360 of span.
2) Cantilever Members: 2L/360 maximum, where L is the length of the cantilever.
b. Seismic: As required by Governing Authorities for Seismic Zone 4.

3. Thermal: Provide for noiseless expansion and contraction of system components without causing buckling, failure or joints, etc. or excessive on components and fastenings.
a. Ambient Temperature Range: 100 Fahrenheit degrees.

4. Railing Assemblies, Handrails, and Guardrails:
a. Handrails shall resist a point load of at least 200 pounds, applied in any direction at any point.
b. Railings shall resist a uniform vertical and horizontal load of 50 pounds per lineal foot, applied at the top rail.
c. Comply with “Metal Rail Manual” of National Ornamental and Miscellaneous Metals Association (NOMMA).
d. Comply with “Pipe Railing Manual” of National Association of Architectural Metal Manufacturers (NAAMM).
e. Comply with the Americans with Disabilities Act (ADA) C. QUALITY CONTROL:

1. Statement of qualifications for fabricator, installer, and welders.

2. Control of Corrosion: Prevent galvanic action and other forms of corrosion by insulating metals and other materials from direct contact with incompatible materials.

1.4 SUBMITTALS
A. Shop Drawings: Show fabrication and installation details for metal fabrications.

1. Include plans, elevations, sections, and details of metal fabrications and their connections(including sleeves), show anchorage and accessory items for the following:
a. Guardrail
B. Embedded Steel Items Shop Drawings: Drawings that detail placement and connection of the various embedded steel items such as posts into concrete retaining

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
METAL FABRICATIONS 05 50 00 - 3
walls. Include item sizes, material, grade, spacing, dimensions and supports for the embedded items.

C. Samples

1. Provide full size mock up of the guardrail design for review and approval in field.

D. Finishes

1. Provide submittal of powder coated guard rails.

1.5 QUALITY ASSURANCE
A. Welding Qualifications: Qualify procedures and personnel according to AWS D1.1/D1.1M, "Structural Welding Code - Steel."
B. Welding Qualifications: Qualify procedures and personnel according to the following:

1. AISC “Specification for Design, Fabrication and erection of Structural Steel for Buildings”, and “Code of Practice.”

2. American Welding Society (AWS) D1.1/D1.1 M “Structural Welding Code for Structural Steel”.

3. National Association of Architectural Metal Manufacturers (NAAMM) “Metal Finishes Manual.”

4. National Association of Architectural Metal Manufacturers (NAAMM) “Pipe Railing Manual.”

1.6 PROJECT CONDITIONS
A. Field Measurements: Verify actual locations of walls and other construction contiguous with metal fabrications by field measurements before fabrication.

1.7 COORDINATION
A. Coordinate selection of shop primers with topcoats to be applied over them. Comply with paint and coating manufacturers' written recommendations to ensure that shop primers and topcoats are compatible with one another.

B. Coordinate installation of anchorages and steel weld plates and angles for casting into concrete. Furnish setting drawings, templates, and directions for installing anchorages, including sleeves, concrete inserts, anchor bolts, and items with integral anchors, that are to be embedded in concrete or masonry. Deliver such items to Project site in time for installation.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
METAL FABRICATIONS 05 50 00 - 4
PART 2 - PRODUCTS

2.1 METALS, GENERAL
A. Metal Surfaces, General: Provide materials with smooth, flat surfaces unless otherwise indicated. For metal fabrications exposed to view in the completed Work, provide materials without seam marks, roller marks, rolled trade names, or blemishes.

Materials used in metal fabrications items include, but are not necessarily limited to, the following:

1. Structural Steel Shapes, Bars, Plates: ASTM A36.

2. Steel Tubing: ASTM A500, Grade B. Use seamless tubing at exposed locations.

3. Sheet Steel: ASTM A611.

4. Steel Pipe: ASTM A53, Grade “B”.

5. Bolts and Nuts: ASTM A307, Bolts and nuts used for supporting the steel plate wall shall be ASTM A325.

6. Welding Materials: Class E70 electrodes unless otherwise recommended by Reference Standards.

7. Non-Shrink Grout: Expansion producing non-metallic grout, pre-mixed, MasterBuilders “Masterflow 713”, or equal.

8. Anchor Cement: Bonsal “Anchor Cement” or equal.

9. Sealants: As specified in Section 09720, “Joint Sealants.”

2.2 MISCELLANEOUS MATERIALS
A. Welding Rods and Bare Electrodes: Select according to AWS specifications for metal alloy welded.

B. Hardware: Furnish bolts, screws, and connectors of standard manufacturer required to complete work with all metal guardrail.

1. All hardware shall be hot-dipped galvanized, unless otherwise noted.

2. Refer to plans and details for additional information.

2.3 STEEL AND IRON FINISHES
A. Galvanizing: Hot-dip galvanize items as indicated to comply with ASTM A 153/A 153M for steel and iron hardware and with ASTM A 123/A 123M for other steel and iron products.

1. Do not quench or apply post galvanizing treatments that might interfere with paint adhesion.

B. Shop prime iron and steel items not indicated to be galvanized unless they are to be embedded in concrete, sprayed-on fireproofing, or masonry, or unless otherwise indicated.

1. Shop prime with universal shop primer.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
METAL FABRICATIONS 05 50 00 - 5
C. Preparation for Shop Priming: Prepare surfaces to comply with SSPC-SP 6/NACE No. 3, "Commercial Blast Cleaning" requirements indicated below:

1. Exterior Items: SSPC-SP 6/NACE No. 3, "Commercial Blast Cleaning."

2. Items Indicated to Receive Zinc-Rich Primer: SSPC-SP 6/NACE No. 3, "Commercial Blast Cleaning."

3. Items Indicated to Receive Primers Specified in Division 09 Section "HighPerformance Coatings": SSPC-SP 6/NACE No. 3, "Commercial Blast Cleaning."

4. Other Items: SSPC-SP 3, "Power Tool Cleaning."
D. Shop Priming: Apply shop primer to comply with SSPC-PA 1, "Paint Application Specification No. 1: Shop, Field, and Maintenance Painting of Steel," for shop painting.

1. Stripe paint corners, crevices, bolts, welds, and sharp edges.

2.4 FABRICATION, GENERAL
A. Shop Assembly: Preassemble items in the shop to greatest extent possible.

Disassemble units only as necessary for shipping and handling limitations. Use connections that maintain structural value of joined pieces. Clearly mark units for reassembly and coordinated installation.

B. Cut, drill, and punch metals cleanly and accurately. Remove burrs and ease edges to a radius of approximately 1/32 inch (1 mm) unless otherwise indicated. Remove sharp or rough areas on exposed surfaces.

C. Form bent-metal corners to smallest radius possible without causing grain separation or otherwise impairing work.

D. Form exposed work with accurate angles and surfaces and straight edges.

E. Weld corners and seams continuously to comply with the following:

1. Use materials and methods that minimize distortion and develop strength and corrosion resistance of base metals.

2. Obtain fusion without undercut or overlap.

3. Remove welding flux immediately.

4. At exposed connections, finish exposed welds and surfaces smooth and blended so no roughness shows after finishing and contour of welded surface matches that of adjacent surface.

F. Form exposed connections with hairline joints, flush and smooth, using concealed fasteners or welds where possible. Where exposed fasteners are required, use Phillips flat-head (countersunk) fasteners unless otherwise indicated. Locate joints where least conspicuous.

G. Fabricate seams and other connections that will be exposed to weather in a manner to exclude water. Provide weep holes where water may accumulate.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
METAL FABRICATIONS 05 50 00 - 6
H. Cut, reinforce, drill, and tap metal fabrications as indicated to receive finish hardware, screws, and similar items.

I. Provide for anchorage of type indicated; coordinate with supporting structure. Space anchoring devices to secure metal fabrications rigidly in place and to support indicated loads.

2.5 PROTECTIVE COATINGS
A. Comply with NAAMM's "Metal Finishes Manual for Architectural and Metal Products" for recommendations for applying and designating finishes.

B. Finish metal fabrications after assembly.

C. Finish exposed surfaces to remove tool and die marks and stretch lines, and to blend into surrounding surface.

D. Prepare steel per SSPC SP-6 or SP-7 for AESS prior to galvanizing and prior to shop priming.

E. Galvanizing: Hot-dip galvanize items as indicated to comply with ASTM A 153/A 153M for steel and iron hardware and with ASTM A 123/A 123M for other steel and iron products. Hot-dip galvanize all items fabricated from ferrous metals that will be in permanent contact with concrete below grade, immersed in water, or in a location that will be permanently exposed to weather or moist conditions, and not specified as painted. For shop-fabricated assemblies, i.e. railing assemblies, hot-dip galvanize after fabrication is complete as much as feasible per assembly size/ dipping tank size limitations.

1. Shapes, Plates, Bars, Strips: Comply with ASTM A123.

2. Hardware Items: Comply with ASTM A153.

3. Sheets: Comply with ASTM A525.

4. Sequence: Insofar as practicable, galvanize after fabrication. Conform to requirements of ASTM A384, A385, A386.

5. Pressure Relief: Provide holes in closed ends of tube or pipe for relief of pressure during galvanizing process.

6. Touch-up: Where galvanizing is removed by welding or other assembly procedure, touch up abraded areas with molten zinc or zinc-rich paint.

PART 3 - EXECUTION

3.1 PRE-CONDITIONS
A. Examination: Examine surfaces to receive metal fabrications and conditions under which they are to be installed. Correct unsatisfactory surfaces and conditions prior to commencement of installation.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
METAL FABRICATIONS 05 50 00 - 7

3.2 INSTALLATION, GENERAL
A. Cutting, Fitting, and Placement: Perform cutting, drilling, and fitting required for installing metal fabrications. Set metal fabrications accurately in location, alignment, and elevation; with edges and surfaces level, plumb, true, and free of rack; and measured from established lines and levels.

B. Fit exposed connections accurately together to form hairline joints. All welds shall be shop welded prior to being brought to the site for assembly. Do not weld, cut, or abrade surfaces of exterior units that have been hot-dip galvanized after fabrication and are for bolted or screwed field connections.

C. Fastening to In-Place Construction: Provide anchorage devices and fasteners where metal fabrications are required to be fastened to in-place construction. Provide threaded fasteners for use with concrete and masonry inserts, toggle bolts, through bolts, lag screws, wood screws, and other connectors.

D. Provide temporary bracing or anchors in formwork for items that are to be built into concrete, masonry, or similar construction.

3.3 ADJUSTING AND CLEANING
A. Galvanized Surfaces: Clean field welds, bolted connections, and abraded areas and repair galvanizing to comply with ASTM A 780.

END OF SECTION 05 50 00

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SIGNAGE 10 14 00 - 1
SECTION 10 14 00

SIGNAGE
PART 1 – GENERAL

1.1 RELATED DOCUMENTS
A. The drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY
A. This Section includes all services, labor, materials, transportation, and equipment necessary to perform the Work indicated on the Contract Drawings and specified herein this Section, as required to furnish and install signage.

1.3 RELATED WORK
A. Related Sections can include, but may not be limited to:

1. Section 03 30 00 "Cast-in-Place Concrete" for footings.

1.4 DEFINITIONS
A. Graphic Panels: sign component containing graphic content.

B. Sign hardware: structure holding graphic panels.

C. Custom High Pressure Laminate (CHPL): graphic sign material composed of several layers of phenolic resin impregnated kraft filler paper, a digitally imaged graphic, a layer of melamine resin, surfaced by a layer of translucent exterior UV / graffiti overlay protection.

1.5 QUALITY ASSURANCE
A. Fabricator Qualifications: Shop that employs skilled workers who custom-fabricate products similar to those required for this Project and whose products have a record of successful in-service performance. The CHPL graphics must be warrantied for a minimum of 10 years against fading, de-lamination and weather deterioration. There should be no warranty requirements for an annual application of water sealant, no exclusions for panels used in “extreme temperatures” and no clause that warranties can can be denied due to “improper maintenance”. Panels must be able to be cleaned with any solvent and not restrict use of products containing lacquer thinner or acetone.

All cutting and finishing to be done using a CNC router. Graphics must be made using

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SIGNAGE 10 14 00 - 2
12-Color High Definition printing technology. Vendor shall provide a sample from a supplied file to confirm quality. Panels must be entirely made in the U.S.A.

B. Source Limitations for Signs: Obtain each sign type indicated from one source from a single manufacturer.

1.6 SUBMITTALS
A. Product Data: submit manufacturer's product data of sign panel materials and fabrication.

B. Shop Drawings: Show fabrication and installation details for signs.

C. Show sign mounting heights, locations of supplementary supports to be provided by others, and accessories.

D. Samples for Verification: For each of the following products and for the full range of color, texture, and sign material indicated, of sizes indicated:

1.7 PROJECT CONDITIONS
A. Weather Limitations: Proceed with installation only when existing and forecasted weather conditions permit installation of signs in exterior locations to be performed according to manufacturers' written instructions and warranty requirements.

B. Field Measurements: Verify all signage placement by field measurements before fabrication and indicate measurements on Shop Drawings.

1.8 COORDINATION
A. Coordinate with other trades to ensure installation does not conflict with other work.

PART 2 – PRODUCTS

2.1 SIGNS
A. INTERPRETIVE SIGN

1. Cantilever In-Ground Supports - Part #CDG224

2. Mounting Plate: Standard Mounting Plate

3. Tamper Resistant Bolt: button-head anti-vandal screws; ½" long x ¼"; 20 thread count; stainless steel.

4. In Ground Mount +

5. Finish/Color: Powder Coated Aluminum/color as noted on plans

6. Rep. Rhiannon Andrews
a. Fossil Industries - or approved equal
44 Jefryn Blvd
Deer Park NY 11729
Phone: 631-998-6148

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SIGNAGE 10 14 00 - 3
B. PUMP TRACK ACCESSIBILITY AND ETIQUETTE SIGN

1. Double Post In-Ground Pedestal Even Mount 8 brackets - Part #UDGE8

2. Mounting Plate: Standard Mounting Plate

3. Tamper Resistant Bolt: button-head anti-vandal screws; ½" long x ¼"; 20 thread count; stainless steel.

4. In Ground Mount +

5. Finish/Color: Powder Coated Aluminum/color as noted on plans

6. Rep. Rhiannon Andrews
a. Fossil Industries - or approved equal
44 Jefryn Blvd
Deer Park NY 11729
Phone: 631-998-6148

2.2 FABRICATION
A. Graphic Panels:

1. Graphics panels must be LEED, GREENGUARD and FSC Certified and be manufactured as Custom High Pressure Laminate (CHPL).

2. The entire panel, including exterior overlay, must be bonded under heat and extreme pressure to form a composite panel.

B. Hardware:

1. Posts shall be powder coated aluminum. All welding and powder coating shall take place in the shop by the sign manufacture.

2. Welded Connections: Comply with AWS standards for recommended practices in shop welding. Provide welds behind finished surfaces without distortion or discoloration of exposed side. Clean exposed welded surfaces of welding flux and dress exposed and contact surfaces.

3. Mill joints to tight, hairline fit. Form joints exposed to weather to exclude water penetration.

4. Conceal fasteners if possible; otherwise, locate fasteners where they will be inconspicuous.

5. Attachments shall be steel, vandal-resistant.

2.3 FINISHES GENERAL
A. The finish of the graphic panels must be smoothly textured with reflectivity of 30 + or – 5 gloss units.

PART 3 – EXECUTION

3.1 EXAMINATION
A. Examine substrates, areas, and conditions, with Installer present, for compliance with requirements for installation tolerances and other conditions affecting performance of work.

B. Verify that items are sized and located to accommodate signs.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SIGNAGE 10 14 00 - 4
C. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 INSTALLATION
A. Locate signs and accessories per field direction from City Representative, using mounting methods of types described and complying with manufacturer's written instructions.

1. Install signs level, plumb, straight, accurately fitted, located and at heights indicated, with sign surfaces free of distortion and other defects in appearance.

2. Contractor shall do all necessary drilling, tapping, cutting or other preparation of surrounding construction in the field accurately neatly and as necessary for the attachment and support of signage. Obtain approval of Engineer prior to such preparations to work of others where cutting or other preparations may affect structural integrity or exposed finish.

3. All footings, anchorage, and mounting hardware, as applicable, shall be installed in strict accordance with manufacturer's instructions and contract drawings. The Contractor shall use vandal resistant hardware or industry standard epoxy resin application to nut.

B. Concrete footings: Per City of Richmond Standard Specifications, concrete mixture for all signage footings shall meet the following requirements, unless otherwise approved by the Owner's Representative:

1. Minimum compressive strength at 28 days: 30 MPa

2. Maximum nominal aggregate size: 28mm

3. Maximum W/C ratio by mass 0.45

4. Air content 4 to 6%

5. Slump 30mm to 70mm

3.3 CLEANING AND PROTECTION
A. Protect all signage and graphics work from damage during transportation, storage at job site, during erection, and during subsequent construction activities. Exposed metal surfaces shall be wrapped with heavy reinforced, non-staining paper or non-staining strippable coatings or protected by other approved methods. After installation, provide additional temporary protection as required to protect work of this Section from damage during subsequent construction activities.

B. After installation, clean soiled sign surfaces, leaving surfaces free of smears, scratches and abrasions to the satisfaction of the Engineer and according to manufacturer's written instructions. Protect signs from damage until acceptance by Engineer. Any damages to finishes shall be repaired at no additional cost to the City. In the event damage is not repairable, remove and replace such items at no additional cost to the City.

C. If Touch-up Painting is required, the Contractor shall clean field welds, bolted connections, and abraded areas of the work immediately after erection and paint exposed areas with paint or galvanizing material as supplied by the manufacturer.

Apply by brush, to thickness recommended by paint manufacturer.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SIGNAGE 10 14 00 - 5
END OF SECTION 10 14 00

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
PLAYGROUND EQUIPMENT 11 68 13 - 1
DOCUMENT 11 68 13

PLAYGROUND EQUIPMENT
PART 1 GENERAL

1.01 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and supplementary Conditions and Division 1 Specification Sections, apply to this Section.

1.02 SUMMARY
A. All playground equipment indicated on the drawings and/or herein specified, including all footings, anchorages, accessories and play surfaces required to provide complete, safe, and usable play equipment to the satisfaction of the Landscape Architect.

B. Shop prime coat, painting and galvanized finishes for all metal and wood not having finishes.

1.03 RELATED WORK
A. Related Sections can include, but may not be limited to:
(1) Section 03 30 13 "Cast-In-Place Concrete"
(2) Section 31 00 00 “Earthwork”
(3) Section 32 18 16 "Playground Protective Surfacing"

1.04 REFERENCES AND STANDARDS
A. Standard Consumer Safety Performance Specifications for Playground Equipment for Public Use, American Society for Testing and Materials, ASTM F 1487-98 & California Assembly Bill 1144.

B. Standard Specification for Determination of Accessibility of Surface Systems Under and Around Playground Equipment, ASTM F 1959-99.

C. Standard Specification for Impact Attenuation of Surface Systems Under and Around Playground Equipment, ASTM F 1292-99.

D. Handbook for Public Playground Safety, U.S. Consumer Products Safety Commission (USCPSC).

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
PLAYGROUND EQUIPMENT 11 68 13 - 2
E. Manufacturer’s printed specification, instructions and shop details for Installation of the indicated and/for specified play equipment.

F. All equipment must conform to the Consumer Product Safety Improvement Act of 2008.

1.05 QUALITY ASSURANCE
A. Playground equipment work shall comply with these specifications and all applicable sections of the above-named References and Standards.

1.06 SUBMITTALS
A. Submit manufacturer’s product data, specifications, and installation instructions and shop details for factory fabricated items.

B. Submit shop drawings. Include plans, elevations, and details of sections and connections. Show anchorage and accessory items.
(1) Plans shall include safety zone and play structures shown within the required play areas as shown on the drawings.

C. Submit samples of selected colors and finishes.

D. Submit samples and manufacturer’s product specifications for all play surfaces.

E. Submit playground safety inspection report as submitted by the certified playground safety inspector.

1.07 DELIVERY, STORAGE, AND HANDLING
A. Deliver, store and handle play equipment items to prevent damage and deterioration.

B. Stack assembled items off the ground.

1.08 PROJECT CONDITIONS
A. Coordinate play equipment work with trades furnishing adjacent work related to play equipment installation.

B. Provide sleeves, anchors, inserts, clips and other items furnished under this Section and built in with work of other trades.

C. No work shall be installed until shop drawings for the work have been reviewed and approved in writing by the Landscape Architect and final grading and surfacing is completed.

D. Manufacturer shall provide footing depths.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
PLAYGROUND EQUIPMENT 11 68 13 - 3
PART 2 PRODUCTS

2.01 MATERIALS
A. Play Structures
(1) Refer to the drawings for Manufacturers and play equipment and play surfacing model numbers.
(2) The use of a manufacturer’s name and model number is for purposes of establishing type and quality, other manufacturer’s equipment may be submitted for approval by the Landscape Architect. Said substitution must be equal in design, materials, strength, safety and function to equipment specified.

B. CONCRETE FOOTINGS
(1) Per manufacturers recommendation.

PART 3 EXECUTION

3.01 INSPECTION
A. Examine the substrate under which playground equipment and surfaces are to be installed. Notify the Landscape Architect, in writing, of conditions detrimental to the proper and timely completion of the work. Do not proceed with the work until unsatisfactory conditions have been corrected.

3.02 PREPARATION
A. Provide footings, sleeves, and anchorages. Furnish templates, setting drawings, and instructions for installation of sleeves and anchorages built into other work.

B. Locate and layout all play field markings and equipment items. Obtain the Landscape Architect’s written approval of the layout prior to installation.

3.03 INSTALLATION
A. Assemble and install play equipment in accordance with approved and shop drawings and manufacturer’s printed instructions.

B. Perform fitting required for installation. Set the work accurately in location, alignment, and elevation free of rack, measured from established lines and levels.

Assembled play equipment shall be firm, rigid, free of rattle, and provide maximum protection against tampering and vandalism.

C. Compact and finish grade the subgrade prior to installing sand and bark play surfaces.

D. Set equipment at proper relationship to finish play surfacing in accordance with approved shop drawings, provide any hardware necessary to solidly attach equipment to footings, while allowing for the thickness of play surfacing.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
PLAYGROUND EQUIPMENT 11 68 13 - 4

3.04 CERTIFICATION
A. Per California Assembly Bill 1144, a playground safety inspector, certified by the National Playground Safety Institute, is to be attained to conduct an inspection of the installed playground. The resulting inspection report is to be submitted to the Owner at the completion of the project.

3.05 CLEANING
A. Perform cleaning during installation of the work and upon completion of the work.

Remove from site all excess materials, debris and equipment. Repair any damage to adjacent work resulting from playground equipment work.

B. Upon completion of installation, clean factory-finished items in accordance with manufacturer’s cleaning instructions. Exercise care to avoid damage to the finish coating.

PART 4 - MEASUREMENT AND PAYMENT
Measurement and payment for the following bid items shall be set as set forth on the BID SCHEDULE and are as follows:

1. XXXXXX
The price bid for the XXXXXX items shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals, and for doing all the work involved with construction of the items listed above, as shown and noted on the plans, as specified herein, and as directed by the Engineer.

END OF SECTION 11 68 13

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SITE FURNISHINGS 12 93 00-1
SECTION 12 93 00

SITE FURNISHINGS
PART 1 - GENERAL
A. Section Includes: All labor, materials, supplies, tools and transportation to perform all operations in connection with and reasonably incidental to the complete installation of the site furnishings as shown on the Drawings, and specified herein.

B. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.

1.2 SUBMITTALS
A. Product Data: For each type of product indicated.

B. Submit shop drawings to the City for approval before installing any manufactured items. Plans shall include dimensions, color, finish, structural design (custom items), connection details, and installation instructions.

C. Submit catalog cuts, samples and manufacturers literature of all manufactured items in this section to the City for approval before installation.

1. Provide color samples, brushouts, or charts for all items. Final colors to be selected by City and a sample submitted for approval.

D. Product Schedule: For site furnishings. Use same designations indicated on Drawings.

E. Material Certificates: For site furnishings, signed by manufacturers.

F. Maintenance Data: For site furnishings to include in maintenance manuals.

PART 2 - PRODUCTS

2.1 MANUFACTURED ITEMS
A. Trash Receptacle: See Plans
B. Log Seating: See Plans
C. Picnic Table: See Plans
D. Bike Rack: See Plans
E. Bike Repair Station: See Plans
F. Terraced Seating: See Plans
G. Removeable Bollard: See Plans
H. Drinking Fountain: See Plans
I. Isle Seating: See Plans

2.2 CONCRETE FOOTINGS
A. Per manufacturers recommendation.

2.3 FINISHES, GENERAL
A. Comply with NAAMM's "Metal Finishes Manual for Architectural and Metal Products" for recommendations for applying and designating finishes.

B. Appearance of Finished Work: Variations in appearance of abutting or adjacent pieces are acceptable if they are within one-half of the range of approved Samples.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SITE FURNISHINGS 12 93 00-2
Noticeable variations in the same piece are not acceptable. Variations in appearance of other components are acceptable if they are within the range of approved Samples and are assembled or installed to minimize contrast.

PART 3 - EXECUTION

3.1 EXAMINATION
A. Examine areas and conditions for compliance with requirements for correct and level finished grade, mounting surfaces, installation tolerances, and other conditions affecting performance.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 INSTALLATION, GENERAL
A. Install products per manufacturer's recommendations, provide embedded installation where specified in plans and details, materials shall be square, plumb, level, accurately aligned, and securely anchored at locations as indicated on Drawings. Use extensions where required.

B. Coordinate anchor screws in concrete with site furnishing manufacturers.

C. Unless otherwise indicated, install site furnishings after landscaping and paving have been completed.

3.3 CLEANING
A. After completing site furnishing installation, inspect components. Remove spots, dirt, and debris.

3.4 GUARANTEE
A. At completion of project, Contractor shall provide City with written guarantee from each manufacturer identifying the nature of warranty for each product component.

PART 4 - MEASUREMENT AND PAYMENT
Measurement and payment for the following bid items shall be set as set forth on the BID SCHEDULE and are as follows:

1. XXXXXX
The price bid for the XXXXXX items shall include full compensation for furnishing all labor, materials, tools, equipment and incidentals, and for doing all the work involved with construction of the items listed above, as shown and noted on the plans, as specified herein, and as directed by the Engineer.

END OF SECTION 12 93 00

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
PRE-ENGINEERED STRUCTURES 13 30 00 - 1
SECTION 13 30 00

PRE-ENGINEERED STRUCTURES
PART 1 – GENERAL

1.1 RELATED DOCUMENTS
A. The drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY
A. Contractor shall obtain complete architectural and structural plans from the manufacturers, apply for permit, coordinate City plan check, make corrections and resubmit if needed, and pay all permit fees for all pre-engineered structures.

Contractor shall furnish all materials, labor and supervision necessary to completely install and finish the structures in accordance with current and applicable building codes including but not limited to State of California building code, UBC, and installation instructions from manufacturers, and plans and specifications.

B. This Section includes the following:

1. Restroom Building

2. Stage Shade Structure
C. Related Work:

1. Section 03 30 00 “CIP Concrete”

2. Section 26 05 00 “Electrical Basic Materials and Methods”

3. Section 26 50 00 “Lighting”

4. Section 31 23 00 “Earthwork”

5. Section 32 84 00 “Irrigation System” for irrigation controller located in restroom

6. Section 33 10 00 “Water Utilities”

7. Section 33 30 00 “Sanitary Sewage System”

1.3 QUALITY ASSURANCE
A. Materials, equipment, and methods of installation shall comply with the following codes and standards:

1. 2013 California Building Code, including disabled access requirements.

2. Unified Plumbing Code and National Electrical Code.

3. American Society for Testing and Materials, (ASTM).

4. National Sanitation Foundation, (NSF).

5. Uniform Building Code, (UBC).

6. ASTM C33 Concrete Aggregates

7. ASTM C39 Method of Test for Compressive Strength of Cylindrical Concrete Specimens

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
PRE-ENGINEERED STRUCTURES 13 30 00 - 2

8. ASTM C94 Standard Specification for Ready-Mixed Concrete

9. ASTM C143 Method of Test for Slump of Concrete

10. ASTM C150 Standard Specification for Portland Cement

11. ASTM A185 Standard Specification for Steel Welded Wire Reinforcement, Plain, or Concrete

12. ASTM C192 Method of Making and Curing Test Specimens in the Laboratory

13. ASTM C231 Standard Test Method for Air Content of Freshly Mixed Concrete by the Pressure Method

14. ASTM C309 Standard Specifications for Liquid Membrane-Forming Compounds for Curing

15. Concrete ASTM C494 Standard Specification for Chemical Admixtures for Concrete

16. ASTM A615 Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement

17. ASTM C979 Standard Specification for Pigments for Integrally Colored Concrete

18. ACI 211.1 Standard Practice for Selecting Proportions for Normal, Heavyweight, and Mass Concrete

19. ACI 306 Cold Weather Concreting

20. ACI 318 Building Code Requirements Structural Concrete and Commentary (includes Errata)

21. PCI MNL 116 Quality Control for Plants and Production of Precast Prestressed Concrete Products
B. Reference Standard: Equipment manufacturer’s specifications and recommendations.

C. Manufacturer Criteria:

1. Manufacturer must have the proper licenses for California:
a. California Department of Housing and Development Commercial Modular “Manufacturers License (Must be “Active” prior to bidding “No Exceptions”). b. Selling through a Commercial Modular Dealer/Dealer Salesperson licensed by the California Department of Housing and Community development. (Must be Current prior to bidding “No Exceptions”).

1.4 PERFORMANCE REQUIREMENTS
A. Building manufacturer shall provide a warranty against defects in material workmanship for a period of five (5) years; with the exception of any goods which have been repaired or altered without manufacturer’s express written consent, any goods which have been subject to misuse, negligence, acts of God or accidents, or any goods which have not been installed to manufacturer’s specifications and guidelines, improperly maintained, or used outside of the specifications for which such goods were designed.

1.5 SUBMITTALS
A. Design and installation drawings signed and stamped by California licensed engineer with floor plans, roof plans, elevations, foundation and anchor bolt plans shall be furnished by the building supplier. Where applicable, plans shall be fully dimensioned

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
PRE-ENGINEERED STRUCTURES 13 30 00 - 3
to show compliance with disabled access requirements of the 2013 California Building Code.

B. Contractor shall submit plans to the Owners Representative for review and approval prior to order and delivery of materials. Contractor shall coordinate with manufacturer to ensure no delays in manufacture and delivery of materials.

C. The following sections shall be included in the building supplier’s Scope of Supply and Design Submittal.

1. INTRODUCTION
a. About this document
b. How to use this document
c. Typical building supplier process
d. Documents to return to building supplier

2. SCOPE OF SUPPLY – PRODUCTS & SERVICES
a. Scope of supply - products
b. Scope of supply - services

3. PRODUCTS & SERVICES NOT SUPPLIED BY BUILDING SUPPLIER a. Products not supplied by building supplier
b. Services not supplied by building supplier

4. PROJECT SITE
a. Site considerations
b. Site layout drawings
c. Delivery procedures and helpful information
d. Operation & maintenance manuals
e. Construction phase – special circumstances

5. WARRANTY & LIMITATIONS
a. Building supplier limited warranty
b. Limitations of building supplier responsibilities
c. Copyright

6. PROJECT DESIGN
a. Plan Set
b. Structural Calculations

7. PRODUCT DATA SHEETS (AS APPLICABLE)
a. Staging explanation
b. Stage 1: Frame
c. Stage 2: Roofing, vents, & windows
d. Stage 3: Exterior
e. Stage 4A: Plumbing and partitions
f. Stage 4B: Electrical components
g. Stage 4C: Accessories

1.6 WARRANTY
A. The buildings and structures and all associated components shall be warranted against defects in materials and workmanship for a period of not less than five (5) years from date of final acceptance.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
PRE-ENGINEERED STRUCTURES 13 30 00 - 4

1.7 MAINTENANCE
A. The Contractor shall provide maintenance for the pre-engineered structures until the project is accepted.

PART 2 – PRODUCTS

2.1 STRUCTURES
A. Refer to Plans and Appendices for quantities, dimensions, locations, and installation methods for the materials and items described in this section.

B. Dimensions shall match what is indicated on drawings. Plans shown in Appendices shall be amended and modified as necessary to match dimensions shown on plan.

Contractor to coordinate with on-site conditions as needed.

C. All elements including walls, beams, and roofing to be designed and supplied by the supplier.

D. Structures Include:

1. Restroom Building
a. Prefabricated Restroom described on the plans and in Appendix 4 of these specifications.

2. Stage Shade Structure
a. Prefabricated Restroom described on the plans and in Appendix 5 of these specifications.

2.2 CAST IN PLACE CONCRETE
A. All equipment, labor, trades and materials shall be supplied by Contractor.

1. Includes all materials and labor for foundations/footings, interior slabs, exterior/entry slabs, and sidewalks.

B. Engineered fill, vapor barrier, reinforcement and other accessories shall be as specified on the final permit drawings and specifications.

C. The Contractor shall prepare pad based on approved permit drawings. The Contractor shall be responsible for ensuring that the concrete foundation is adequate for the site conditions and the purpose for which the building and foundation/slab are intended.

D. Engineered Fill. Bedding material to be per approved permit plans and specifications.

2.3 PLUMBING
A. Plumbing, where specified, rough-in, installation and trim shall be supplied by the contractor.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
PRE-ENGINEERED STRUCTURES 13 30 00 - 5

1. All underground water service and sewer drain(s) from building to be as specified in final site plan.

2. All floor drains shall be as shown on final building plans.

3. Building water shutoff valve, drain, and all rough piping shall be as shown on final building plans. Final location to be set onsite.

4. Minimum water pressure at toilet and urinal flush valves shall be 50 psi. with minimum pipe sizing as per 2009 Uniform Plumbing Code Section 610.

5. Install the supplied fixtures and all other plumbing supplies as specified in final plans.

B. Floor drain shall be supplied by Contractor.

C. Water line drain valve shall be supplied by Contractor.

D. Sewer line backflow check valve shall be Contractor supplied, per City and code requirements.

2.4 RESTROOM FIXTURES
A. Restroom fixtures shall be supplied by building supplier and shall be as specified on the final permit drawings and specifications.

2.5 ELECTRICAL
A. Electrical rough-in, installation and trim shall be supplied by Contractor.

1. All underground service to building shall be as shown on the plans. Electric meter base, panel board, timers, enclosure, security system and all rough wiring, switches, plugs and circuit breakers shall be furnished and installed by the Contractor as shown on the plans.

2. Contractor is responsible for all necessary wire, connectors, grounding, conduit etc. to install the components and meet national and local code. The installation of these components shall comply with all state and/or local codes. See Div 26 specifications for complete requirements.

B. Restroom

1. Accessories including light fixtures, hand dryers, shall be provided by the supplier, per approved permit plans and specifications.

2. Contractor to supply and install irrigation controller where shown on plans inside the restroom including conduits, power, and wires.

3. Contractor to supply and install rain sensor on top of restroom with conduit between the controller and sensor.

C. Stage

1. Building supplier shall provide posts for wiring and cutouts for electrical equipment.

2. Contractor shall provide lighting and power supply per the electrical plans.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
PRE-ENGINEERED STRUCTURES 13 30 00 - 6

2.6 CONTRACTOR SUPPLIED COMPONENTS
Contractor is responsible for supply and installation of all other items indicated on final plans or required by building codes.

PART 3 – EXECUTION
Contractor shall furnish all materials, labor and supervision necessary to completely install and finish the structure foundations and/or building pad, coordinate with manufacturer and supplier, and install structures in accordance with installation instructions from building manufacturer and plans and specifications and the provisions of the building permit.

3.1 EXAMINATION
A. Examine areas and conditions for compliance with requirements for correct and level finished grade, mounting surfaces, installation tolerances, and other conditions affecting performance.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 SPECIAL INSPECTION
A. Contractor shall schedule and coordinate all inspections required on the project including regulatory and special inspections.

3.3 DELIVERY, STORAGE, AND HANDLING
A. Packing, Shipping, and Handling

1. Before the packaged restroom building arrives on-site, delivery instructions with an attached parts list will be sent to the owner and/or Contractor.

2. These lists need to be given to the personnel receiving and offloading the building kits prior to delivery so that an inventory of materials can be performed.

B. Storage and Protection

1. Upon delivery, Contractor will assume responsibility for adequate protection of materials from weather, damage, and pilferage or all warranties, expressed or implied may be voided.

3.4 INSTALLATION
A. All components to be installed according to the plan sets and/or manufacturer’s instructions.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
PRE-ENGINEERED STRUCTURES 13 30 00 - 7

3.5 OPERATION & MAINTENANCE MANUALS
A. Upon installation, provide the Operations & Maintenance manuals that are provided by some manufacturers in their packaging to the City. Requests for additional copies from the building supplier will result in subsequent charges to the Contractor.

END OF SECTION 13 30 00

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
BASIC MATERIALS AND METHODS 26 05 00 - 1
SECTION 26 05 00

BASIC MATERIALS AND METHODS
PART 1 - GENERAL

1.01 SECTION INCLUDES
A. Specifications for basic materials and methods for all work included under Division 26.

Additional specifications requirements for electrical work are specified under other sections of Division 26 and where those requirements differ from the requirements of this Section, they shall govern.

1.02 SUBMITTALS
A. Submit product data for all material for approval.

B. Submit shop drawings detailing new electrical facilities and connection to existing facilties.

PART 2 - PRODUCTS

2.01 CONDUIT
A. Rigid Steel Conduit: Standard weight, mild steel pipe, zinc coated on both inside and outside by a hot dipping or sherardizing process. Inside and outside of conduit shall be finished with a protective coating. All threads galvanized after cutting. Meets UL 6, UL Card #DYIX, and ANSI C80.1.

B. Intermediate Metal Conduit (IMC): For exposed, above grade applications use Intermediate weight, mild steel pipe, meeting same requirements for finish and material as rigid steel conduit. Meets UL 1242, UL Card #DYIX, and ANSI C80.6.

C. PVC Conduit

1. Type 40, 90 C, UL listed, composed of polyvinyl chloride, conforming to NEMA TC2, Fed Spec WC1094A, UL651 Standards. Material shall have minimum tensile strength of 6,500 psi at 73.4 F, flexural strength of 12,500 psi and compressive strength of 9,000 psi per ASTM testing. PVC conduit shall be suitable for direct burial without concrete encasement. Fittings shall be of same manufacture. All joints shall be solvent welded.

2. Only manufactured elbows/bends shall be used. Where field bends have to be made, obtain prior approval by the engineer.

D. Metallic conduits and fittings shall be listed and approved as a grounding means.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
BASIC MATERIALS AND METHODS 26 05 00 - 2

2.02 WIRES
A. Conductors shall be copper and comply with Section 86-1.02F of the Standard Specfications.

B. Bring wire to job in original unbroken packages. Obtain approval of inspector or Engineer before installation of wires.

2.03 CONVENIENCE OUTLETS
A. Shall be "Specification" grade rated 15 amperes at 125 volts, duplex, composition base with slots to accommodate parallel plug caps with grounding peg. Contact shall grip both sides of plug prongs. Where only one receptacle is connected to a 20 ampere circuit, a 20 ampere receptacle shall be used. Outlet shall be UL listed.

Receptacle Hubbell A-H P & S Leviton
20A GFI GF5352 GF5342 2091 6899
B. Provide a separate GFI duplex receptacle at each location identified on the drawings and as specified. Through wiring is not acceptable.

2.04 PRECAST CONCRETE PULLBOXES/HANDHOLES
A. Boxes shall be size as indicated on the drawings. Design loads shall consist of live, dead, impact, hydrostatic, and other loads. Live loads shall be for H-20 and/or H-20-S16-44, or as required, per A.A.S.H.O. standard specifications for highway bridges with revisions.

Design loads shall be sixteen KIPS. Concrete shall be per ASTM-C-33-64. Lightweight concrete shall conform to ASTM-C-33-64T. Cement shall be Portland Cement meeting ASTM-C-150 Type II standards. Compressive strength shall be minimum 4,000 psi at 28 days.

B. Boxes: Precast high-density reinforced concrete with end and side knockouts, and extension as required. Minimum 1.5 inches wall thickness. Acceptable manufacturers shall be Forni, Christy or equal.

C. Covers: All covers shall be reinforce concrete with hold down bolts. Where susceptible to vehicular traffic, use H 20 rated traffic cover. All covers shall be factory marked, see drawings for marking/label required.

D. Installation

1. Excavate around area to accept box, a minimum of four inches around all sides for ease of installation. Provide 12 inches of compacted pea gravel for bedding and/or to facilitate drainage.

2. Backfill shall consist of sand or fine earth, compacted. Saturated soil or large rocks shall not be used. No voids shall remain between walls and native soil.

3. Grout and seal conduits at box entry with cement. Provide with conduit end bells.

E. Utility Co. boxes shall be per their requirements. Provide with ground rod as required.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
BASIC MATERIALS AND METHODS 26 05 00 - 3
F. The metal covers of lighting and power pull boxes shall be ground bonded to the circuit grounding conductor(s) in the pull box. The size of the bonding conductor shall be the same size as the associated circuit ground conductors.

2.05 GROUND RODS
A. Ground rods shall be 3/4 inch diameter x 8 foot copper clad steel.

2.06 SUBPANEL AND RECEPTACLES FOR STAGE
A. As indicated in plans, provide outdoor, steel, tamper-proof 200AMP subpanel (120/240 Volt, 1-Phase). Enclosure rating, NEMA size shall be 3R. Surface finish shall be baked enamel gray or as approved by the Engineer. Number of circuits shall be 24. Number of spaces shall be 12.

B. Receptacles shall be as indicated in plans.

2.07 ENCLOUSED CIRCUIT BREAKERS
A. Thermal-magnetic for 100A and smaller, or solid state for larger than 200A. CutlerHammer, General Electric, Square D, or equal. Enclosure to suit, similar to disconnect switches.

2.08 CONDUCTOR CABLE
A. Conductor Material: ICEA stranded copper meeting requirements of ASTM B3, soft drawn.

B. Conductor Type: Unless specified otherwise, conductor types shall be as follows:

1. Size 14 AWG to Size 1/0 AWG: California Electrical Code, Type THHN or THWN, polyvinyl chloride (PVC) thermoplastic insulated in accordance with NEMA WC70. Cable shall be jacketed with clear polyamide nylon over the insulation.

2. Size 2/0 AWG and Larger: California Electrical Code, Type THWN or THHN, ethylene-propylene-rubber-insulated in accordance with NEMA WC70.

C. Temperature Rating: Temperature ratings of all cables shall be not less than 90 degrees C.

2.09 SUPPORT, ANCHORAGE, AND ATTACHMENT COMPONENTS
A. Conduit and Cable Support Devices: Steel hangers, clamps, and associated fittings, designed for types and sizes of conduit to be supported.

B. Support for Conductors in Vertical Conduit: Factory-fabricated assembly consisting of threaded body and insulating wedging plug or plugs for non-armored electrical conductors or cables in riser conduits. Plugs shall have number, size, and shape of conductor gripping pieces as required to suit individual conductors or cables supported. Body shall be malleable iron.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
BASIC MATERIALS AND METHODS 26 05 00 - 4
C. Structural Steel for Fabricated Supports and Restraints: ASTM A36, steel plates, shapes, and bars; black and galvanized.

D. Mounting, Anchoring, and Attachment Components: Items for fastening electrical items or their supports to building surfaces include the following:

1. Powder-Actuated Fasteners: Threaded-steel stud, for use in hardened portland cement concrete, steel, or wood, with tension, shear, and pullout capacities appropriate for supported loads and building materials where used. a. Manufacturers: Subject to compliance with requirements, provide products of the following, or equal approved as a comparable product:
1) Hilti, Inc.
2) ITW Ramset/Red Head, div. Illinois Tool Works, Inc.
3) MKT Fastening.
4) Simpson Strong-Tie Co., Inc.

2. Mechanical-Expansion Anchors: Insert-wedge-type, zinc-coated steel, for use in hardened portland cement concrete with tension, shear, and pullout capacities appropriate for supported loads and building materials in which used. a. Manufacturers: Subject to compliance with requirements, provide products of the following, or equal approved as a comparable product:
1) Cooper B-Line, Inc., div. Cooper Industries.
2) Hilti, Inc.
3) ITW Ramset/Red Head, div. Illinois Tool Works, Inc.
4) MKT Fastening.

3. Concrete Inserts: Steel or malleable-iron, slotted support system units similar to MSS Type 18; complying with MFMA-4 or MSS SP-58.

4. Clamps for Attachment to Steel Structural Elements: MSS SP-58, type suitable for attached structural element.

5. Through Bolts: Structural type, hex head, and high strength.

Comply with ASTM A325.

6. Toggle Bolts: All-steel springhead type.

7. Hanger Rods: Threaded steel.

2.10 FABRICATED METAL EQUIPMENT SUPPORT ASSEMBLIES
A. Description: Shop welded or bolted, structural-steel shapes, shop or field fabricated to fit dimensions of supported equipment.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
BASIC MATERIALS AND METHODS 26 05 00 - 5

2.11 SECURITY SYSTEM
Provide pole mounted Flock Safety Camera with License Plate and Facial Recognition will be provided by the City. Contractor shall be responsible for providing power to security camera. Existing pole record information provided below. Contractor shall provide shop drawings with mounting details of new camera to existing pole for approval by the Engineer.

A. Ethernet Cable shall be Cat 5E or as approved by the Engineer.

B. Video Management and Recording System shall manage the IP Cameras, record the video, provide video storage, display real-time video, and review of historic video recordings. The Contractor shall provide a network video recorder, including computer and software, or an approved equivalent by the Engineer. Hardware shall be located in the Community Center as directed by the Engineer.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
BASIC MATERIALS AND METHODS 26 05 00 - 6
PART 3 - EXECUTION

3.01 CONSTRUCTION METHOD
A. Horizontal Directional Boring

1. The Contractor shall install conduit using the horizontal directional bore method.

As approved by the Engineer, the Contractor can install the conduit by open trenching. Prior to commencing construction, the contractor shall contact Underground Service Alert to have all underground utilities marked as noted in the Utility Locating Section of these Special Provisions. During the potholing operation, the contractor should review the characteristics of the existing soils so as to plan for the directional bore operation. Should the contractor find soil that may not be satisfactory for directional drilling, they shall notify the Engineer immediately.

2. The contractor shall prepare a profile of each bore indicating the proposed route, depth, and available clearance to existing utilities. The profile should be submitted to the Engineer prior to the commencement of the bore operation for approval.

3. All drilling units should be equipped with an electrical strike safety package. The package should at a minimum contain a warning sound alarm. All members of the contractor’s crew shall wear die-electric boots at all times.

4. The contractor shall place bore and receive pits at intervals based on site characteristics. After completion of the pilot bore, the path shall be reamed as necessary to safety pull back conduits without damaging the existing infrastructure.

The contractor shall determine the required drilling fluid fixture to properly suspend the bore hole. The bore path shall be as straight as practical in both the horizontal and vertical plane.

B. Open Trenching

1. In certain locations, underground obstructions or other conflicts may require the conduit to be installed by open trenching. If this occurs, the Contractor shall notify the Engineer prior to performing the work. No additional payment will be made for installation of conduit by open trench.

2. The Contractor shall restore all asphatl, concrete, and landscape surface to existing or better condition.

3.02 CONDUITS
A. Conduits installed by trenchless methods shall be SDR11 high density polyethylene or fusible PVC.

B. Conduits installed in contact with ground shall be PVC 40 conduit.

1. Provide a minimum two inches of sand bedding at the bottom of the trench before laying conduits. Maintain two inches separation between conduits. Maintain 12 inches separation between power conduits and low voltage signal conduits.

2. Backfill shall be sand, from bottom to 12 inches below finished grade. Fine earth native backfill to be used for the last 12 inches.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
BASIC MATERIALS AND METHODS 26 05 00 - 7

3. Risers, including elbows, shall be double-wrapped rigid steel or PVC coated rigid steel conduit; except that risers, including elbows and bends, at in-ground pull box locations shall be PVC-40 terminated with endbells.

4. When installing underground conduits to specified depth, depth shall be taken from the top of the conduit to the finished grade level. Unless otherwise specified, underground conduits outside of foundation line shall be installed with top side not less than 24 inches below finished grade.

5. Utility Company (electric, telephone, cable TV, etc.) conduits shall be installed per their depth and backfill requirements. Minimum depth shall be 24 inches below finished grade. Minimum conduit shall be PVC-40. Where the utility company allows use of a "lesser" grade conduit, i.e. DB120, PVC-40 shall be used.

6. The minimum size of conduits outside the foundation line shall be one inch.

7. Bends shall be wide sweeping type with minimum 24 inch radius bends.

8. Manufactured elbows are required to be used for all 22.5 and 45 degree bends, and 90 degree elbows, and combinations thereof. Field bends may be used for other bends with approved field benders specifically for such purpose and such bends shall not compromise the integrity and nominal thickness of the conduit wall.

9. For all trenches, provide a six inch-wide non-biodegradable metal-detectable polyethylene tape at 12 inches below grade, five mil. thick, labeled "CAUTION ELECTRIC LINE BURIED BELOW." Fluorescent red for electric power conduits.

C. Although circuiting is shown as diagrammatic, their point-to-point destinations and their indication of above/below ground route shall be followed as much as possible. Where site conditions dictate that an alternate means of routing will alleviate conflicts, the alternate means will be considered with prior approval by the Engineer.

3.03 CAPPING
A. Cap conduits during construction with manufactured seals. Swab out conduits before wires are pulled in.

B. Cap all empty conduits below grade and in pull boxes with manufacturer's caps to prevent entrance of water and debris, attach pull string to cap.

3.04 CONDUCTORS
A. Conductors shall be coppye and comply with Section 86-1.02F of the Standard Specfications.

B. Use only UL approved wire pulling compound as lubricant.

C. #12 AWG wire shall be minimum size wire used for lighting and power circuits.

D. All conductors shall be in conduit unless otherwise indicated.

E. Conduit sizes shall be based on code fill table for THW insulated wires to accommodate the number, size, and type of wires shown or specified.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
BASIC MATERIALS AND METHODS 26 05 00 - 8
F. Wiring installed in pull boxes or junction boxes, where wire is pulled through without terminations (except splices), shall have a service loop around the interior of the box for 360 degrees utilizing the largest circumference.

G. Where conductors are increased in size and number (such as for voltage drop reasons), such that conductors will not fit the standard breaker or panel lugs, terminate conductors in one of the following means:

1. Provide larger breaker frame or panelboard.

2. Provide oversized lugs.

3. Last Option only with approval from Engineer: Terminate wires in multiport connector and provide pigtail. Splice to be made in panel or switchboard if space is available, or in separate splice box. This option will not be normally granted.

3.05 GROUNDING
A. Grounding and ground bonding of the electrical installation shall be in accordance with CEC Article 250, and any applicable codes. Ground fittings shall be approved manufactured type, installed and connected to conform with Code requirements.

B. Neutral conductors and noncurrent-carrying parts of equipment at each installation shall be grounded in accordance with applicable code. Ground conductor shall be copper having a current capacity sized in accordance with CEC.

C. All equipment cases, etc., shall be completely grounded to satisfy requirements of CEC.

Install bond wire in flexible conduit. Install copper bond wire, sized in accordance with CEC, in all nonmetallic raceways and bond to all metallic parts using approved fittings.

D. Service ground conductor shall be connected to a "Ufer" encased ground and bonded to the metallic cold water pipe system and to the metallic natural gas line.

E. Total ground resistance shall not exceed 25 ohms.

F. All connections shall be made with solderless connectors or molded fusion-welding process.

3.06 PULL BOXES
A. All conduits entering boxes through the bottom shall extend a minimum of 1 ½” and not more than 3” into the inside of the boxes. All conduits shall be grouped to one end of the box and plugged with conduit caps immediately after installation and prior to backfill.

B. Excavation for pull boxes shall include excavation for transitions and flares as necessary for project improvements. Pull boxes shall conform to the representative agency requirements and these specifications.

C. Boxes and lids in paved areas shall be capable of withstanding traffic loads.

D. Boxes in sidewalk area shall have skid-resistant covers suitable for foot traffic.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
BASIC MATERIALS AND METHODS 26 05 00 - 9
E. Boxes shall be installed to be flush with the finish surface at the locations shown on the plans and shall be placed on a minimum 6” bed of crushed rock which shall extend a minimum 6” outside the exterior edges of the box.

F. All conduits in pull boxes shall be duct sealed.

G. Pull boxes shall include saw-cut existing curb, gutter sidewalk/street, excavation, supply, installation, backfill and repair of said curb, gutter, and sidewalk/street. Traffic cover shall be provided and installed by the Contractor for pull boxes located in street/driveway areas.

3.07 APPLICATION
A. Comply with NECA 1 and NECA 101 for application of hangers and supports for electrical equipment and systems except if requirements in this section are stricter.

B. Maximum Support Spacing and Minimum Hanger Rod Size for Raceway: Space supports for EMT, IMC, and RMC as required by NFPA 70. Minimum rod size shall be 1/4 inch in diameter.

3.08 SUPPORT INSTALLATION
A. Comply with NECA 1 and NECA 101 for installation requirements except as specified in this Article.

B. Strength of Support Assemblies: Where not indicated, select sizes of components so strength will be adequate to carry present and future static loads within specified loading limits. Minimum static design load used for strength determination shall be weight of supported components plus 200 lb.

C. Mounting and Anchorage of Surface-Mounted Equipment and Components: Anchor and fasten electrical items and their supports to building structural elements by the following methods unless otherwise indicated by code:

1. To Wood: Fasten with lag screws or through bolts.

2. To New Concrete: Bolt to concrete inserts.

3. To Masonry: Approved toggle-type bolts on hollow masonry units and expansion anchor fasteners on solid masonry units.

4. To Existing Concrete: Expansion anchor fasteners.

5. Instead of expansion anchors, powder-actuated driven threaded studs provided with lock washers and nuts may be used in existing standard-weight concrete 4 inches thick or greater. Do not use for anchorage to lightweight-aggregate concrete or for slabs less than 4 inches thick.

6. To Steel: Welded threaded studs complying with AWS D1.1, with lock washers and nuts, or beam clamps (MSS Type 19, 21, 23, 25, or 27) complying with MSS SP69.

7. To Light Steel: Sheet metal screws.

8. Items Mounted on Hollow Walls and Nonstructural Building Surfaces: Mount cabinets, panelboards, disconnect switches, control enclosures, pull and junction

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
BASIC MATERIALS AND METHODS 26 05 00 - 10
boxes, transformers, and other devices on slotted-channel racks attached to substrate by means that meet seismic-restraint strength and anchorage requirements.

D. Drill holes for expansion anchors in concrete at locations and to depths that avoid reinforcing bars.

3.09 INSTALLATION OF FABRICATED METAL SUPPORTS
A. Cut, fit, and place miscellaneous metal supports accurately in location, alignment, and elevation to support and anchor electrical materials and equipment.

B. Field Welding: Comply with AWS D1.1.

3.10 FIELD TESTS
A. General: Perform field test in the presence of the Engineer except as otherwise specified.

Provide required labor, materials, equipment and connections to perform tests. Document results and submit them to the Engineer. Repair or replace all defective work.

B. Each ground rod shall be tested. A ground rod which does not have a resistance to ground of 25 ohms or less shall be augmented by one additional ground rod at no less than eight feet from each other.

3.11 CLEANING
A. Brush and clean work prior to concealing, painting and acceptance. Performed in stages if directed.

B. Clean and repair soiled or damaged painted exposed work and match adjoining work before final acceptance.

C. Remove debris from inside and outside of material, equipment and structures.

3.12 WARRANTY
A. All materials and installation shall be provided with a one (1) year warranty which shall include replacement parts, labor, retesting, and travel to and from the job site. The warranty period shall begin after final acceptance of the project.

END OF SECTION 33 30 00

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
LIGHTING 26 50 00 - 1
SECTION 26 50 00

LIGHTING
PART 1 - GENERAL

1.01 SECTION INCLUDES
A. Furnish and install a complete lighting system consisting of high intensity discharge (HID), luminaires, lamps, ballasts, and appurtenances as shown on drawings and specified.

1.02 WORK INCLUDED
A. Furnish and install all necessary labor, material, tools and equipment to perform and completely finish the work according to the intent of this specification, and the accompanying drawings.

1.03 QUALITY ASSURANCE
A. All materials shall comply with applicable standards of the Underwriter's Laboratories, Inc.

1.04 SUBMITTALS
A. Manufacturer's product data and materials. Include technical specification information, photometric data, fixture efficiency, ballasts information, lamp information, weights, accessories, etc.

PART 2 - PRODUCTS

2.01 LUMINAIRES
A. Weatherproof fixtures shall have neoprene gaskets on fixture trim and door assemblies. Fixture shall be UL listed for wet locations.

B. Provide lamps, of wattage and type as shown on the drawings, for all fixtures or as approved by the Engineer.

2.02 LIGHT POLES
A. Provide light pole, ground lug handhole cover, and attachment hardware as indicated in plans or as approved by the Engineer..

B. Poles shall meet the loading based on the wind rating of the Wind Velocity Map as published by AASHTO with a 1.3 gust factor.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
LIGHTING 26 50 00 - 2
C. Reflector optical systems shall be high reflectance prefinished sheet or fabricated construction; no hydroforming, no spinning.

2.03 WIRING
A. Fixtures shall be wired with conductors having insulation suitable for the environmental conditions, current, voltage, and temperature to which the conductors are subjected.

2.04 FOUNDATION
A. Luminaire pole foundations shall be per Caltrans standard plan ES-6C.

PART 3 - EXECUTION

3.01 INSTALLATION
A. All dirt, plaster, paint, etc., on luminaires and lenses shall be removed before work will be accepted. Mounting of luminaires shall be in strict accordance with the CEC Section 410.

3.02 WARRANTY
A. All materials and installation shall be provided with a one (1) year warranty which shall include replacement parts, labor, retesting, and travel to and from the job site. The warranty period shall begin after final acceptance of the project.

END OF SECTION 26 50 00

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
LIGHTING 26 50 00 - 3

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SITE PREPARATION & PLANT PROTECTION 31 10 13 - 1
SECTION 31 10 13

SITE PREPARATION & PLANT PROTECTION
PART 1 - GENERAL

1.01 DESCRIPTION
A. Protecting improvements and vegetation to remain.

B. Clearing and grubbing.

C. Removal of existing site improvements including but not limited to asphalt pavement, site bollards, and signage.

1. Provide watering for all planting within Contract limit and any adjacent areas affected by the work. Coordinate shut off of irrigation systems with the Owner and be responsible for any damage caused to adjacent landscaping by Contract work.

2. A qualified arborist shall be retained by the Contractor to determine the condition of trees in question as to their ability to survive. Comply with recommendations to rehabilitate or to replace in accordance with paragraph above.

C. Preserve and protect adjoining properties during removal work, site preparation work and construction.

1.02 RELATED SECTIONS
A. Section 02 41 00 - Demolition
B. Section 31 20 00 - Earthwork

1.03 DEFINITIONS
A. Tree Protection Zone: All construction activity (grading, filling, paving, landscaping) will respect a Tree Protection Zone (TPZ) around trees to be protected. The TPZ will be a distance of one-foot radial distance from the trunk for each one-inch of trunk diameter.

Exceptions to this standard may occur depending upon the age and condition of individual trees.

B. TREE PROTECTION FENCING

1. Fencing at a minimum of four feet in height and clearly marked to prevent inadvertent encroachment by heavy machinery should be installed either at the edge of the Tree Protection Zone (TPZ), crown drip line (whichever is further from the trunk), or at the edge of the construction zone if the construction zone protrudes into the TPZ. The Supervising Arborist, or County designated representative, should approve location of fencing. All fencing should be in place prior to any site grading.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SITE PREPARATION & PLANT PROTECTION 31 10 13 - 2

2. Contractor should maintain the protection fencing and prohibit all access to fenced areas by construction personnel or equipment until all site work is completed.

3. All structures including construction trailers, equipment storage areas and any other construction traffic are prohibited within fenced areas. Burning or debris piles are prohibited within fenced areas. No materials, equipment, spoil, waste, or washout water should be deposited or stored within fenced areas. Fences may not be moved without written permission of the Supervising Arborist or Owner designated representative.

4. If temporary access within a fenced area is determined to be necessary, then a six-inch layer of bark mulch should be placed in all areas requiring access. This requirement for mulching should apply to all areas within the fenced area and subject to access. If equipment access is required, then the mulch should be overlaid with metal plates of sufficient thickness to adequately distribute bearing load.

1.04 QUALITY ASSURANCE
A. Stipulations

1. Site Preparation and Demolition
a. Work is in accordance with the Drawings and specifications and includes but is not necessarily limited to the following:
1) Clearing and grubbing.
2) Identification and protection of improvements indicated to remain. 3) Removal of existing site improvements, such as, asphalt pavement, site bollards, and signage.
a. Locate and identify existing utility services and protect or disconnect, remove and cap as required for new work.
b. Remove, clean, store and protect all items designated and directed to be salvaged to owner.
c. Remove, store and protect all items designated and directed to be reinstalled.
d. Obtain and pay for permits required for execution of this work.

1.05 SUBMITTALS
A. Photographs or videotape, sufficiently detailed, of existing conditions of adjacent streets, adjacent parking areas, trees and plantings, adjoining construction, and site improvements that might be misconstrued as damage caused by site demolition.

B. The Contractor is to submit a letter with the relevant material submittals certifying that the products used by the Contractor are consistent with the Environmental Safety Policy of the City of Richmond.

1.06 PROJECT CONDITIONS

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SITE PREPARATION & PLANT PROTECTION 31 10 13 - 3
A. Nuisances: Keep dirt, dust, noise, and other objectionable nuisance to a minimum. Use temporary enclosures, coverings and sprinkling, and combinations thereof, as necessary to limit dust to lowest practicable level, except do not use water to the extent that it causes flooding or contaminated run-off.

B. Traffic: Conduct work to ensure minimum interference with vehicular or pedestrian traffic, and to permit unencumbered access to the school property located outside of the project areas.

1. Do not close or obstruct streets, sidewalks, or other public passageways without permission from authorities having jurisdiction.

2. If required, by governing authorities, provide alternate routes around closed and obstructed traffic ways.

3. Do not drive any type of vehicle or store products on the existing track surfacing or on asphalt that is curing unless the area has been protected per California Track instructions. Vehicles and storage areas are limited to the areas of thickened asphalt pavement section as shown on the drawings or as designated by the Owner Representative. Protect existing track surfacing per manufacturer’s instructions. Submit a protection plan to the Owner for approval prior to start of demolition work.

C. Dispose of cleared, grubbed and removed material that will not be salvaged or recycled on site.

D. Salvable Improvements: Carefully remove items indicated to be salvaged and store where designed by Owner. Avoid damaging salvage material.

E. Protections:

1. Prevent movement and settlement of adjacent structures. Install temporary barriers, fences, guard rails, enclosures, shoring, bracing, planking, warning signs and other protections required to protect structures, utilities, landscaping and other items that are to remain in place.

2. Protect benchmarks, monuments, and reference points from displacement and damage; and if displaced or damaged, replace at no cost to the Owner.

3. Install and maintain required bracing, shoring, and supports when removing structural elements and be responsible for safety and support of structure. If safety of structure appears to be endangered, cease operations and immediately notify the Owner. Do not resume operations until safety is restored.

PART 2 - PRODUCTS

2.01 SOILS MATERIALS
A. Satisfactory Soil Materials. See Section 31 05 13, soils for Earthwork for satisfactory soil material for backfilling excavations and depressions resulting from site clearing.

PART 3 - EXECUTION

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SITE PREPARATION & PLANT PROTECTION 31 10 13 - 4

3.01 EXAMINATION
A. Examine areas in which work is to be performed. Report in writing to the Owner’s Representative all prevailing conditions that will adversely affect satisfactory execution of work. Do not proceed with work until unsatisfactory conditions have been corrected.

B. Starting work constitutes acceptance of the existing conditions and the Contractor shall then, at his expense, be responsible for correcting all unsatisfactory and defective work encountered.

C. For the duration of the project, secure the perimeter of the project(s) as required to secure the project from trespass and provide a safe construction site. Field verify the perimeter and gate locations with the Construction Manager. The fence location may be adjusted as the project progresses based on the approval of the Construction Manager.

3.02 CONSTRUCTION OBSERVATIONS AND SUPERVISION
A. As directed by the Engineer, all arboricultural and related soil work shall be performed under the observation of an International Society of Arboriculture (ISA) Certified Arborist.

B. All specified arboricultural work should be completed prior to site grading (root pruning, canopy pruning, fencing, etc.).

C. The Contractor is required to meet with the Supervising Arborist to review all the tree protection requirements.

D. Landscape Architect shall be notified in advance of all work occurring within the TPZ areas. One week notice is required to schedule on-site supervision.

3.03 CLEARING, SITE GRADING, TRENCHING, AND ROOT PRUNING A. In areas to remain planting, remove designated trees, stumps, rubbish, undergrowth and deadwood as well as fences and incidental structures that interfere with the construction as shown on the Drawings and as specified. Obtain verification from Project Inspector prior to removal.

B. Excavations, site grading, and trenching shall be kept within designated construction zones. Excavations, grading cuts, or trenching within the TPZ of a retained tree trunk require special trenching, root pruning, and/or excavation procedures. Trenches shall be dug manually or with the use of an air spade. Alternatively, a root cutting machine, rock saw, or other approved root pruning equipment can be used outside the trenching or excavation area. This root-pruning trench should be placed one foot outside the edge of the grading cut or trench edge. The depth of the trench should equal the depth of the grading cut (or trench depth) to a maximum depth of 40 inches. Spoils from trenching or other excavation work shall be stored outside TPZ areas. Temporary storage of spoils is not permitted within TPZ areas.

C. A trench may be mechanically dug toward a tree until the edge of the TPZ is reached.

From the edge of the TPZ, the special trenching procedures should apply as described in above.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SITE PREPARATION & PLANT PROTECTION 31 10 13 - 5
D. Underground utilities, drain, and irrigation lines should be routed outside the TPZ. When lines must cross the TPZ, the lines are recommended to be bored or tunneled through the area at a depth approved by the Landscape Architect. In these instances, a single shared utility conduit should be used to reduce impacts to trees.

E. Any roots one inch in diameter or larger requiring removal should be cut cleanly in sound tissue. The roots and surrounding soil should be moistened and covered with a thick mulch (4”) to prevent desiccation. No pruning seals or paints should be used on wounds.

Cut and exposed roots should be protected from drying. A water absorbent material (i.e. burlap) should be secured at the top of the trench and draped over the exposed roots.

This material should be kept moistened and soil should be replaced as soon as practicable.

F. Keep site grading within designated construction zones. Grading cuts or trenching within the TPZ of a retained tree trunk requires special trenching procedures. Trenches should be dug manually with an air spade or the use of a root cutting machine, rock cutter, or other approved root-pruning equipment. This root-pruning trench should be placed one foot inside the edge of the grading cut or trench edge. The depth of the trench should equal the depth of the grading cut to a maximum depth of 40 inches.

G. A trench may be mechanically dug toward a tree until the edge of the TPZ is reached.

From the edge of the TPZ, the special trenching procedures should apply.

H. Underground utilities, drain, and irrigation lines should be routed outside the TPZs.

When lines must cross the TPZ, the lines should be directionally drilled, bored or tunneled through the area at a depth approved by the supervising arborist. In these instances, a single shared utility conduit should be used to reduce impacts to trees.

I. Any roots one inch in diameter or larger requiring removal should be cut cleanly in sound tissue. The roots and surrounding soil should be moistened and covered with a thick mulch (4”) to prevent desiccation. No pruning seals or paints should be used on wounds.

Cut and exposed roots should be protected from drying. A water absorbent material (i.e. burlap) should be secured at the top of the trench and should be draped over the exposed roots. This material should be kept moistened and soil should be replaced as soon as practicable.

J. Porous pavements are recommended for use within the TPZ. Construction of the pavement sub-base should avoid grading cuts where possible.

3.04 TREE AND SHRUB PRUNING
A. Any tree pruning, or other similar activity, which may be required as part of site construction, shall be reviewed by the Landscape Architect. Tying of branches may be required to provide temporary access for equipment.

B. Pruning methods shall conform to the ANSI A 300 Pruning Standards and be performed by an ISA Certified Arborist or Certified Tree Worker. No pruning by construction personnel is permitted.

3.05 PRUNING AND CABLING

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SITE PREPARATION & PLANT PROTECTION 31 10 13 - 6
A. Any tree pruning, cabling, or another similar activity which may be proposed as part of site construction will be included on site plans and be reviewed by a qualified arborist provided by the Contractor.

B. Pruning methods shall conform to the ANSI A 300-2008 Pruning Standard Practices and be performed by an ISA Certified Arborist or Certified Tree Worker. Cabling or other support systems shall conform to the ANSI A 300 (part 3) – 2008 Standard Practices.

3.06 DEMOLITION/SITE CLEARING
A. A qualified arborist should review any tree removal work within 50 feet of a TPZ. Trees requiring removal should be felled away from protected trees. Roots of trees to be removed may require pruning with approved root cutting equipment prior to felling if intermingled with roots of retained trees.

B. Excavation equipment should operate from outside the TPZ. Brush and wood chips generated from tree and brush removal should be placed in the TPZ To a maximum depth of six inches.

C. All required pruning should conform to the pruning section of these guidelines.

D. All vegetation removal should be performed with hand equipment when within a TPZ.

3.07 SITE DRAINAGE
A. All grading shall be designed to provide positive drainage away from the base of the tree trunk, and not create ponding within the TPZ.

3.08 IRRIGATION
A. Provide watering for all planting within Contract limit and any adjacent areas affected by the work. Coordinate shut off of irrigation systems with the Owner and be responsible for any damage caused to adjacent landscaping by Contract work. Request As-Built plans for review and information. Locate and preserve irrigation main line in place at all times.

3.09 REPLACEMENT
A. Replace trees cut or severely damaged. Determine tree value by formula adopted by the National Shade Tree Conference 1951 and 1955. Replace in cash value.

3.10 GRUBBING
A. In areas that will remain planting, remove all stumps and roots in their entirety, brush, organic materials and debris. Such materials as topsoil and leaf mold, or other organic materials above the ground surface suitable for use as mulch or topsoil, shall be salvaged or stockpiled.

B. Topsoil and other organic materials above the ground surface suitable for use as mulch or topsoil, shall be salvaged or stockpiled on site separately from subsoil.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SITE PREPARATION & PLANT PROTECTION 31 10 13 - 7
C. Remove grasses and weeds. Apply systemic weed killer and confirm weed kill prior to removal.

3.11 UTILITIES
A. Contact local utility companies 48 hours minimum prior to start of demolition work.

Confirm verbal notices and written notices. Verify locations of all utilities entering site and their locations on site.

3.12 REMOVAL
A. General:

1. Remove materials in an orderly and careful manner.

2. Repair or replace all removal work performed in excess to that required at no cost to the Owner. Repair or replacement shall match and equal construction, condition, and finish existing at time of award of Contract.

B. Remove the following locations to the extent required or directed for new construction.

1. Fencing, including posts, fabric and footings. Backfill voids if required from removed footings with clean fill as defined in Section 310513, Soils for Earthwork. Be careful of soil caving due presence of groundwater intrusion.

2. Electric underground wires and conduits occurring within removal areas except those shown as reused on Electrical Drawings. Refer to Utility Drawings and Specifications.

3. Miscellaneous structural elements that interfere with the new construction and as directed.

4. Paving. Remove asphalt and concrete paving including aggregate base rock completely to the minimum depth required for sub-grade of new improvements.

Dispose of the demolished concrete, asphalt and base rock at a material recycling facility. Existing aggregate base may be reused on site if it meets the requirements and approval of the Geotechnical Engineer.

5. Underground Pipes and Utilities.

6. Other items noted on the drawings and required to be removed to install the new improvements.

C. Cutting asphalt, concrete curbs and concrete pavement:

1. All lines shall be marked and accepted by Owner’s Representative before the cutting operation.

2. Cut edges of pavement at a 90-degree angle to surface in a true and straight line in accordance with dimensions shown on the Drawings. Make cuts with a concrete saw, to a 1-1/2” minimum depth.

D. Backfill and compact areas excavated and open pits and holes resulting from removal operations. Comply with requirements specified in Section 312317 for backfill materials, compaction and installation methods.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SITE PREPARATION & PLANT PROTECTION 31 10 13 - 8
E. Rough grade site removal areas to meet adjacent contours and to provide positive drainage. Leave site in clean condition acceptable for performance of subsequent construction operations.

3.13 TREE DAMAGE MITIGATION
A. Trees damaged during construction shall be evaluated by the Supervising Arborist or Owner representative. Proper mitigation measures shall be specified and may include:

1. Pruning of damaged and dead wood.

2. Installation of a drip irrigation system to provide supplemental irrigation for three to five seasons following damage.

3. Proper low nitrogen fertilization timed to growth response and phonological development of the tree.

4. Periodic hazard evaluation of tree.

5. Replacement of tree per Owner requirements.

6. Alleviation of severe compaction by vertical mulching with augers or hydraulic soil probes.

7. Alleviation of surface compaction by light cultivation or raking and the application of a mulch.

3.14 CLEANUP AND DISPOSAL
A. Transport trash, rubbish, and debris daily from site and legally dispose of:

1. Demolished and waste materials encountered.

2. Remove and promptly dispose of contaminated, vermin-infested and dangerous materials encountered.

3. Do not burn or bury materials on site.

B. Clean excess soil may be distributed on site as accepted by Inspector, if it does not adversely affect specified finished grades. Coordinate with Section 310513 Soils for Earthwork, and the Drawings.

C. Excess soil may need to be legally disposed of off-site. Coordinate with the Drawings, and the following specifications: Section 310513, Soils for Earthwork; Section 312316, Excavation; and Section 312317 Trenching.

D. Upon completion of work under this Section, remove all tools, equipment, and temporary enclosures and structures.

END OF SECTION 31 10 13

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
SITE PREPARATION & PLANT PROTECTION 31 10 13 - 9
This Page Intentionally Left Blank

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
EARTHWORK 32 10 00 - 1
SECTION 31 20 00

EARTHWORK
PART 1 - GENERAL

1.01 SUMMARY
A. Section Includes (but Is Not Necessarily Limited to):

1. Excavations, fill, and finish grading.

2. Removal and legal disposal off the site of all debris, rubbish, and other materials resulting from earthwork operations.

3. Compaction of fill.

B. All work shall conform to the requirements and/or recommendations listed in the Geotechnical Investigation Report (A3GEO Oct-2023) or as approved by the Engineer.

1.02 SYSTEM DESCRIPTION
A. Design Requirements:

1. Grades and elevations are established with reference to bench marks referenced on the Drawings.

2. Maintain engineering markers such as monuments, bench marks, and location stakes.

B. Performance Requirements:

1. Excavations and finished grades shall not exceed 1/10-foot variation from dimensions and elevations shown or noted, unless otherwise approved by Owner’s Representative.

2. Grading under pavements shall be graded within tolerance of 0 to -1/10 foot.

1.03 DEFINITIONS
A. Native Material: That obtained from required on site excavation.

B. Import Material: Hauled in from off-site borrow areas.

C. Relative Compaction: In-place dry density of soil expressed as percentage of maximum dry density of same material, as determined by laboratory test procedure ASTM D-1557.

1.04 QUALITY ASSURANCE
A. The following reference is hereby made part of this Specification and all work of this Section shall conform to the requirements therein, except as herein modified.

1. “Standard Specifications,” State of California, Department of Transportation (CALTRANS), current edition; hereinafter called Standard Specifications.

Delete all references to statistical testing and measurement and payment.

2. In case of conflict between Standard Specifications and this Specification, this Specification governs.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
EARTHWORK 32 10 00 - 2
B. California Code of Regulations (C.C.R.), Title 24.

C. Work shall comply with rules and regulations of local and state agencies having jurisdiction.

D. State and local code requirements shall control disposal of debris.

1.05 PROJECT CONDITIONS
A. Environmental Requirements:

1. When precipitation necessitates interrupting filling and grading operations, prepare areas by compaction of surface and grading to avoid collection of water.

2. Provide adequate temporary drainage and other acceptable measures to prevent erosion.

3. After interruption, reestablish compaction specified in last layer before resuming work.

B. Locate active utilities traversing site, and protect them from damage.

C. Tree Protection:

1. Contractor shall exercise the outmost caution in working near existing trees & vegetation so as not to damage them. Contractor to refer to project drawings for information on existing tree locations.

1.06 RELATED WORK
A. Section 02 41 00 – Demolition
B. Section 31 10 13 – Site Preparation and Plant Protection PART 2 - PRODUCTS

2.01 GENERAL
A. Fill materials shall be reviewed and found acceptable by the Owner’s Representative.

2.02 AGGREGATE BASE MATERIALS
A. Aggregate Base: Class 2, Standard Specification Section 26-1.02A, free from vegetable matter and other deleterious substances, and shall be of such nature that it can be compacted readily under watering and rolling to form a firm, stable base.

2.03 WATER
A. Clean and free from deleterious amounts of acids, alkalis, salts, and organic matter.

PART 3 - EXECUTION

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
EARTHWORK 32 10 00 - 3

3.01 GENERAL
A. Prior to commencement of earthwork, become thoroughly familiar with site conditions.

B. When discrepancies are found, immediately notify the Owner’s Representative with a follow-up in writing, indicating the nature and extent of differing conditions.

C. Whenever acceptance of the Owner’s Representative is required by these Specifications, notify the Owner’s Representative at least twenty-four hours prior to commencing any phase of earthwork.

1. No phase of work shall proceed until prior phase has been accepted by the Owner’s Representative.

2. Work shall not be covered up or continued until acceptance of the Owner’s Representative has been obtained.

D. Field Tests:

1. Location and frequency of field density tests shall be determined by the Owner’s Representative.

2. Results of test and compliance with these Specifications shall be basis for determining satisfactory completion of work.

E. Compacting:

1. Compact by power tamping, rolling, or combinations thereof as accepted by the Owner’s Representative.
a. Where impractical to use rollers in close proximity to adjacent construction, trees, etc., compact by mechanical tamping.
b. Scarify and recompact any layer not attaining compaction until required density is obtained.

2. Compaction by flooding, ponding, or jetting will not be permitted.

3.02 SITE PREPARATION
A. Cleaning:

1. Remove from area of designated project earthwork all obstructions, asphalt pavement and other matter determined to be deleterious.

2. Removed material shall become property of the Contractor and shall be removed from site.

3. Existing trees remain: trees damaged during construction shall be replaced without additional expense to the owner.

B. Stripping:

1. Where vegetation exists, the site shall be stripped to a depth of 1 to 3 inches or to such greater depth as the Owner’s Representative in the field may consider as being advisable to remove all surface vegetation and organicladen topsoil.

2. Stripped topsoil shall be stockpiled clear of construction area for use in landscaped areas at a location as designated by the Owner’s Representative. a. Take reasonable care to prevent topsoil from being mixed with subsoil.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
EARTHWORK 32 10 00 - 4

3.03 SITE EXCAVATION
A. Perform all excavations to lines and grades and within the tolerance specified on the Drawings or as directed in the field as required to accomplish the work.

3.04 GRADING
A. Finish-grade elevations as indicated on the Drawings or otherwise required for proper completion of the Work.

B. Grade to at least a tolerance of 0.1 foot.

3.05 FIELD QUALITY CONTROL
A. Soil Compaction Tests:

1. Maximum dry-density determination shall conform with ASTM D-1557.

2. Field density testing shall conform with ASTM D-556 (sand-cone method) or ASTM D-2922 (nuclear-gauge method).

B. Number and location of tests shall be at option of the Engineer and as indicated in the Geotechnical Investigation Report (A3Geo Oct-2023).

3.06 CLEANING
A. Remove debris and surplus materials from site upon completion of the Work, and dispose of in legal manner.

3.07 SUBGRADE PREPARATION
A. Subgrades beneath slabs, or pavement (including sidewalks) should be checked for the presence of soils with a Plasticity Index (PI) greater than 15, which is generally indicative of soil that is potentially expansive. Any subgrade soils with a PI greater than 15 should be over-excavated and replaced with compacted Select Fill, as indicated in the Geotechnical Investigation Report (A3Geo Oct-2023).

B. Subgrade preparation for project improvements should be according to the following:
• Fill – prior to placement of new fill, scarify to a depth of six inches, moisture condition, and re-compact to create a firm and unyielding subgrade. • Utility Trenches – bottom of trench should be firm and unyielding subgrade. Soft or yielding subgrade soils should be compacted or excavated to a depth adequate to expose firm, non-yielding materials. Alternatively, unsuitable subgrade may be replaced with CLSM or a 6-inch thick layer of 3/4-inch drain rock wrapped in filter fabric.
• Exterior Flatwork and Pavements – scarify to a depth of six inches, or the full depth of any existing shrinkage cracks, moisture condition, and re-compact to create a firm and unyielding subgrade. Where an 18-inch-thick zone of Select Fill will be placed beneath flatwork or pavement, the scarification can be omitted and instead subgrade preparation should consist of proof rolling or similar method to

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
EARTHWORK 32 10 00 - 5
demonstrate firm and unyielding subgrade prior to placement of the Select Fill.

3.08 NEW FILL PLACEMENT
A. New fills (including General Fill and Select Fill) should be spread in lifts not exceeding 8 inches in uncompacted thickness on surfaces that are approximately level, moisture conditioned as appropriate, and compacted by mechanical means to the required levels of compaction. It is the responsibility of the contractor to select a compaction method compatible with the type of soil being placed (e.g. clayey soils may require different compaction methods than Select Fill). It is possible that fill and/or subgrade materials may be excessively wet or dry depending on the moisture content at the time of construction. If the fill soils are too wet, they may be dried by aeration or by mixing with drier materials. If the fill soils are too dry, water will need to be added. The Engineer shall observe and test, as appropriate, compaction during fill placement to verify that specified compaction and moisture conditioning requirements are met.

New fills should be firm, unyielding, and compacted to the following requirements (per ASTM D-1557 Test Methods):
• General Fill: moisture content between 2 and 5 percent over optimum and compacted to at least 90 percent relative compaction.
• Select Fill: moisture content near optimum and compacted to at least 95 percent relative compaction.
• Aggregate Base: moisture content near optimum and compacted to at least 95 percent relative compaction.

For permanent fill slopes in soil, we recommend a maximum inclination of 2:1 (H:V).

When constructing permanent fill slopes, the contractor shall excavate a series of horizontal benches in competent soil approved by the Engineer as filling proceeds.

The final slopes shall be constructed as terraced fills upon a stable subgrade. Upon completion of the fill construction, the outboard face of the fill should be cut back to provide a firm, uniform slope.

3.09 UTILITIES AND TRENCH BACKFILL
A. Trench excavation bottoms should be stable and unyielding. Utility trenches should be backfilled with fill placed in lifts not exceeding 8 inches in uncompacted thickness.

Trenches should be filled by placing a granular shading layer beneath and around the pipe, and then 6 to 12 inches of shading should be carefully placed and tamped above the pipe. The remaining portion of the trench should be backfilled with as indicated in the plans. If imported granular soil is used, sufficient water should be added during the trench backfilling operations to prevent the soil from “bulking” during compaction. All compaction operations should be performed by mechanical means only. Jetting is not allowed.

The Engineer shall observe utility trench subgrade and backfilling and test compaction, as appropriate, to confirm and document that the work was performed in accordance with the specifications and the intent of the geotechnical investigation report.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
EARTHWORK 32 10 00 - 6
END OF SECTION 32 10 00

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
TRENCH EXCAVATION AND BACKFILL 31 23 24 - 1
SECTION 31 23 24

TRENCH EXCAVATION AND BACKFILL
PART 1 - GENERAL

1.01 SUMMARY
A. Section Includes: Perform all excavation, shoring, dewatering, backfilling, compaction, pavement restoration, and grading necessary or required for the construction of the work as covered by these Specifications, Geotechnical Report, and indicated in the Drawings.

The excavation shall include, without classification, the removal and disposal of all materials of whatever nature encountered, including water and all other obstructions that would interfere with the proper construction and completion of the required work.

B. Related Sections

1. Section 33 10 00 Water Utilities

2. Section 33 30 00 Site Sanitary Sewerage System

3. Section 33 40 00 Storm Drainage System

1.02 REFERENCES
A. American Society for Testing and Materials (ASTM).

B. State of California, Department of Transportation, Standard Specifications (Standard Specifications) July 1992.

C. State of California, Department of Transportation, Manual of Test (California Test).

1.03 SUBMITTALS
A. Submit the following:

1. Samples and Test Results: Furnish, without additional cost to the Owner, such quantities of import materials as may be required by the Owner’s Representative for test purposes. Cooperate with the Owner’s Representative and furnish necessary facilities for sampling and testing of all materials and workmanship.

Submit test results for import materials. Tests shall have been performed within 60 days of submission. All material furnished and all work performed shall be subject to rigid inspection, and no material shall be delivered to the site until it has been favorably reviewed by the Owner’s Representative, or used in the construction work until it has been inspected in the field by Inspector of Record.

1.04 QUALITY ASSURANCE
A. Source Quality Control: Test import materials proposed for use to demonstrate that the materials conform to the specified requirements. Tests shall be performed by an independent testing laboratory.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
TRENCH EXCAVATION AND BACKFILL 31 23 24 - 2
B. Field Quality Control:

1. The Owner will:
a. Review and test materials proposed for use.
b. Inspect placement and compaction of fill.
c. Test soils during placement of fill.

2. Contractor shall excavate holes for in-place soil sampling. Contractor shall be responsible for costs of additional inspection and re-resting resulting from noncompliance.

C. Testing Methods:

1. Durability Index: Manual of Test, State of California, Department of Transportation.

2. Specific Gravity: ASTM D854.

3. Laboratory Compaction: ASTM D1557, Method A or C.

4. In-Place Density: ASTM D2922.

5. Particle Size Analysis of Soils: ASTM D422.

6. Plastic Limit and Plasticity Index: ASTM D4318.

7. Soil Classification: ASTM D2487.

8. In-Place Moisture Content: ASTM D3017.

1.05 EXCAVATION AND TRENCHING
A. General Protection: Pursuant to Labor Code Sections 6705 and 6707, Contractor shall include in its base bid all costs incident to the provision of adequate sheeting, shoring, bracing or equivalent method for the protection of life and limb which shall conform to the applicable Federal and State Safety Orders.

B. Before beginning any excavation five (5) feet or more in depth, submit to the Owner's Representative a detailed plan showing the design of shoring, bracing, sloping or other provisions to be made for worker protection from the hazard of caving ground during excavations. Comply with the Standards established by the State of California Construction Safety Orders Title 24 of the California Administrative Code. If the detailed plan varies from such shoring system Standards it shall be prepared by a registered civil or structural engineer whose name and registration number shall be indicated on the Drawing. If a dispute arises as to whether the plan must be prepared by a registered civil or structural engineer, the Owner's Representative's determination of the matter shall be final and conclusive. The cost of required engineering services shall be borne by the Contractor and shall be deemed to have been included in the amount of bid for the work as stated in the Agreement.

C. Neither the review nor approval of any plan showing design of shoring, bracing, sloping or other provisions for worker protection shall relieve Contractor from his obligations to comply with Construction Safety order Standards and Title 24 CAC for design and construction of such protective work, and Contractor shall indemnify Owner and Owner's Representative from any and all claims, liability, costs, actions and a cause of action arising out of or related to the failure of such protective system. The Contractor shall defend the Owner, its officers, employees and agents and the Owner's Representative in any litigation or proceeding brought with respect to the failure of such protective systems.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
TRENCH EXCAVATION AND BACKFILL 31 23 24 - 3
D. The Contractor shall comply with Section 382 of the Civil Code of the State of California relating to lateral, general and sub-adjacent supports wherever structures or improvements adjacent to an excavation may be damaged by such excavation.

E. Contractors must still comply with the State of California Construction Safety Orders, Article 6 – Excavations, Trenches, Earthwork. The requirements of Article 6 apply whether the excavation, trench or earthwork is less than 5’, or 5’ or more.

F. The Contractor shall select, install and maintain shoring, sheeting, bracing, and sloping as necessary to maintain safe excavations. The Contractor shall be responsible for ensuring such measures: (1) comply fully with 29 CFR Part 1926 OSHA Subpart P Excavations and Trenches requirements, (2) provide necessary support to the sides of excavations, (3) provide safe access to the Engineer’s sampling and testing within the excavation, (4) provide safe access for backfill, compaction, and compaction testings, and (5) otherwise maintain excavations in a safe manner that shall not endanger property, life, health, or the project schedule. All earthwork shall be performed in strict accordance with applicable law, including local ordinances, applicable OSHA, CalOSHA, California Civil Code, and California Department of Industrial Safety requirements.

PART 2 - PRODUCTS

2.01 MATERIALS
A. Crushed Rock: ¾-inch maximum crushed virgin drain rock with a minimum durability rating of 58.

B. Import Backfill: Class 2, ¾-inch maximum aggregate base, Standard Specifications Section 26. Paragraphs 26-1.06 and 26-1.07 are not applicable.

C. Geotextile Fabric: Mirafi FW300 or equivalent
D. Water: The water used shall be potable and free of objectionable quantities of silt, oil, organic matter, alkali, salts and other impurities. Water quality must be acceptable to the Owner’s Representative.

E. Sandy Clay Loam: Provide sandy clay loam backfill in the top 18 inches in unpaved areas, 85% compaction.

1. Sandy Clay Loam Analysis: Submit a sample of sandy clay loam proposed for use to an accredited Soils Laboratory for “agricultural suitability” analysis report, including particle size, and evaluation of physical and chemical properties of soil and recommendations for adding amendments and fertilizers to the soil.

2. Upon approval of the Laboratory’s report by the Owner’s Representative, the recommendations in the report shall become a part of the Specifications and the quantities of soil amendment, fertilizer and other additives shall be adjusted to conform with the report at no additional cost to the Owner. Request Testing Laboratory to send one copy of test results directly to Owner’s Representative.

3. Test Laboratory: Soil and Plant Laboratory, Inc. 352 Matthew Street (PO Box 153), Santa Clara, CA 95052, Tel. (408) 727-0330; or Root Zone Associates, PO Box 18911, San Jose, CA 95118, Tel. (408) 264-7024.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
TRENCH EXCAVATION AND BACKFILL 31 23 24 - 4
F. Controlled Density Fill (CDF):

1. Materials:
a. Cement: ASTM C150, Type II or V. A maximum of twenty (20) lbs. of cement per cubic yard.
b. Aggregate shall consist of fine aggregate, with our without coarse aggregate, with a maximum size of 1-inch, free of clay, organics, and other deleterious materials. Less than 10 percent by weight shall pass the No. 200 sieve, and materials passing the No. 40 sieve shall be nonplastic as determined in accordance with ASTM D4318.
c. Water: Potable.
d. Fly Ash: ASTM C618, Class F unless otherwise approved.

2. Mix Design:
a. Performance Requirements: The CDF shall be proportioned to be a nonsegregating, free flowing, self-consolidating, low shrink slurry. b. Mix Design Requirements: The Contractor and its supplier shall determine the materials and proportions used to meet the requirements of these Specifications. Design the mixes far enough ahead of placement to allow completion of trail mix testing and submittal of test results. The mix design(s) shall be prepared for the range of aggregate gradations that is expected to be used. The Contractor shall make daily checks of the aggregate gradation and adjust the mix design as required to meet these Specifications. c. Material Strength Requirements: The unconfirmed compressive strength at 28 days shall be 100 psi as per ASTM D4832.

G. Trench Plugs: Clayey soils as approved by the Engineer PART 3 - EXECUTION

3.01 CONTROL OF WATER
A. All excavations shall be kept free from water and all construction shall be in the dry.

1. It should be presumed that the presence of groundwater will require dewatering operations. Furnish, install, maintain, and operate all necessary pumping and other equipment for dewatering all excavations. At all times have on the project sufficient pumping equipment for immediate use, including standby pumps for use in case other pumps become inoperable.

2. Provide a sufficient number of pumps so as to hold the groundwater level at an elevation of not less than 1 foot below the lowest elevation of the pipe, duct or other material to be placed.

3. Dispose of water in such a manner as to cause no injury or nuisance to public or private property, or be a menace to the public health.

4. The dewatering operation shall be continuous, so that the excavated areas shall be kept free from water during construction, while concrete is setting and achieves full strength, and until backfill has been placed to a sufficient height to anchor the work against possible flotation.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
TRENCH EXCAVATION AND BACKFILL 31 23 24 - 5

5. Continue dewatering during backfilling operations such that the groundwater is at least 1 foot below the level of the compaction effort at all times. No compaction of saturated materials will be allowed.

6. Dewatering devices must be adequately filtered to prevent the removal of fines from the soil.

7. The Contractor shall be responsible for any damage to the foundations or any other parts of existing structures or of the new work caused by failure of any part of the Contractor's protective works. After temporary protective works are no longer needed for dewatering purposes, they shall be removed by the Contractor.

8. If pumping is required on a 24-hour basis, requiring engine drives, then engines shall be equipped in a manner to keep noise to a minimum.

9. Prevent disposal of sediments from the soils to adjacent lands or waterways by employing whatever methods are necessary, including settling basins and holding tanks for disposal off site
B. The Contractor shall be responsible for furnishing temporary drainage facilities to convey and dispose of surface water falling on or passing over the site.

3.02 EXISTING UTILITIES
A. General: The known existing buried utilities and pipelines except building connections are shown on the Drawings in their approximate location. The Contractor shall exercise care in avoiding damage to all utilities, as they will be held responsible for their repair if damaged. There is no guarantee that all utilities or obstructions are shown, or that locations indicated are accurate. Utilities are piping, conduits, wire, cable, ducts, manholes, pull boxes and the like.

B. Check on Locations (Potholing):

1. The Owner performed a limited investigation and has recorded those findings on the Contract Documents. The Contractor shall be responsible for all additional potholing to verify location of existing utilities as needed to complete the work indicated in the Contract Documents.

2. The Contractor shall clearly paint the location of all affected utility underground pipes, conduits and other utilities on the pavement or identify the location with suitable markers if not on pavement. In addition to the location of metallic pipes and conduits, non-metallic pipe, ducts and conduits shall also be similarly located using surface indicators and detection tape if present and shall then be similarly marked.

3. After the utility survey is completed, commence "potholing" to determine the actual location and elevation of all utilities where crossings, interferences, or connections to the new pipelines are shown on the Drawings, or indicated by surface signs.

Prior to the preparation of piping shop drawings, or the excavating for any new pipelines or structures, the Contractor shall locate and uncover these existing utilities to a point 1-foot below the utility. Submit a report identifying each underground utility and its depth and station. Any variation in the actual elevations and the indicated elevations shall be brought to the Owner’s Representative's attention.

4. Excavations around underground electrical ducts and conduits shall be performed using extreme caution to prevent injury to workmen or damage to electrical ducts

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
TRENCH EXCAVATION AND BACKFILL 31 23 24 - 6
or conduits. Similar precautions shall be exercised around gas lines, telephone and television cables. Contractor shall be responsible for all coordination with the applicable utility agencies for work in and around existing utility mains.

5. Excavations shall have surface dimensions of no more than 18" x 18". Air spades and vacuum excavators shall be used to limit the size of excavations and damage to adjacent facilities. Backfill after completing potholing. In existing streets, repave with project typical pavement section or match existing pavement section, whichever is greater.

C. Interferences:

1. If interferences occur at locations other than shown on the Drawings, the Contractor shall notify the Owner’s Representative, and a method for correcting said interferences shall be supplied by the Owner’s Representative. Payment for interferences that are not shown on the plans, nor which may be inferred from surface indications, shall be in accordance with the provisions of the General Conditions. If the Contractor does not expose all required utilities prior to shop drawing preparation, he shall not be entitled to additional compensation for work necessary to avoid interferences, nor for repair to damaged utilities.

2. Any necessary relocations of utilities, whether shown on the Drawings or not, shall be coordinated with the Owner if instructed to do so in writing from the Owner’s Representative.

D. Overhead Facilities: There may be existing overhead electric and telephone transmission lines on the site. These overhead utilities are not shown on the Drawings. Extreme caution shall be used when working in the vicinity of overhead utilities so as to prevent injury to workmen or damage to the utilities. The Contractor shall be required to comply with the applicable provisions of the California Construction Safety Orders when working anywhere on this project.

E. Existing gas, water, sewer and communications laterals are not specifically shown on the Drawings but do exist along the existing utility corridors. Protect all service laterals from damage due to construction operations. If any laterals are damaged, notify the Owner’s Representative immediately. The cost of repair shall be borne by the Contractor.

3.03 GENERAL CONSTRUCTION REQUIREMENTS
A. Site Access: Access to the site will be over public and private roads. Exercise care in the use of such roads and repair at the Contractor’s expense any damage thereto caused by Contractor’s operations. Such repair shall be to the satisfaction of the Owner or agency having jurisdiction over the road. Take whatever means are necessary to prevent tracking of mud onto existing roads and keep roads free of debris. Contractor shall provide access plan for all phases of work for approval by Owner's Representative prior to trenching operations.

B. Traffic Regulation: Provide such flagmen, lighted barricades, flares, lights, warning signs, and safety devices as may be required for control of traffic adjacent to all areas of work.

A minimum of one 12-foot-wide lane of traffic shall be kept open at all times.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
TRENCH EXCAVATION AND BACKFILL 31 23 24 - 7
C. Open Excavations: Provide chain link fence around all excavations left open during nonworking hours in unpaved areas. In all paved areas (walkways and fire lanes) excavations left open during non-working hours shall be covered with steel plates.

D. Access: Free access must be maintained to all fire hydrants, water valves and meters, and driveways.

E. Open Trench Limitations: The Owner’s Representative shall have the authority to limit the amount of trench to be opened or left open at any one time. In roads, excavation and pipe laying shall be coordinated to the end that a minimum of interference with public traffic will result. Trenches in streets and pathways shall be covered with trench plates at the end of each day. An open trench in existing streets shall be defined as any trench that has not been completely backfilled, satisfactorily compacted, and capped with the permanent pavement.

F. Demolition of Pavement: Where trenching or excavation occurs in paved areas, the pavement shall be scored and broken ahead of the trenching or excavation operation.

The extent of paving removed shall be limited to the minimum necessary for the excavation. The final trench repair shall have sawcut edges.

G. Dust Control: Take proper and efficient steps to control dust.

3.04 TRENCH EXCAVATION
A. There is no room on site for storing excavated material. All excavated material shall be disposed of off campus. All backfill material shall be imported.

B. Excavation to the extent shown on the drawings and under the drip line of trees shall be hand excavated to a level below the root zone of the trees – NO EXCEPTIONS.

C. Excavation for pipe and duct shall be in open cut. The trench shall be as wide as necessary for sheeting and bracing and the proper performance of the work up to the maximum width permitted by the typical cross-sections shown on the Drawings. The sides of the trenches shall be vertical in existing streets. The bottom of the trench shall be constructed to the grades and shapes indicated on the Drawings. Should the Contractor desire to use other equivalent methods, he shall submit his method of construction to the Owner’s Representative for favorable review prior to its use.

D. Take care not to overexcavate. Accurately grade the bottom of the trenches to provide uniform bearing and support for each section of the pipe at every point along its entire length, except for the portions of the pipe sections where it is necessary to excavate for bell holes and for the proper sealing of pipe joints, and as hereinafter specified. Dig bell holes and depressions for joints after the trench bottom has been graded, and, in order that the pipe rest on the bedding for as nearly its full length as practicable, bell holes and depressions shall be only of such length, depth and width as required for properly making the joint. Remove stones as necessary to avoid point bearing.

E. Backfill and compact overexcavations to 95% of its maximum dry density with Class II Aggregate Base material. Provide filter fabric (Mirafi, or equal) above, below, and on both sides of aggregate base as directed by the Owner’s Representative. There shall be no additional payment to the Contractor for overexcavations not directed by the Owner’s

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
TRENCH EXCAVATION AND BACKFILL 31 23 24 - 8
Representative. Remove unsatisfactory material encountered below the grades shown as directed by the Owner’s Representative and replace as directed. Payment for removal and replacement of such unsatisfactory material directed by the Owner’s Representative shall be made in accordance with the provisions of the General Conditions.

F. Grade trenches so that they are uniformly sloped between the pipe elevations shown on the Drawings. Comply with the minimum and maximum trench widths shown on the Drawings. Notify the Owner’s Representative if the trench width exceeds the maximum allowable width for any reason.

G. For all piping or conduits to be placed in any excavated and backfilled area, such as at manholes or for building connections, the structural backfill shall be first compacted to a level at least 3 feet above the top of the piping or conduit elevation and then retrenched to pipe grade.

H. Provide ladders for access to the trench by construction and inspection personnel.

3.05 SAFETY BARRICADES AND LIGHTS
A. Where required for protection of workmen, public safety, or as required by State Laws, substantial barricades shall be provided for the areas where excavation, trenching, construction and demolition work are being performed. Safety Barricades shall not be used in lieu of required guardrails on temporary bridges crossing trenches, excavations or other openings. For protection of the Visually Impaired, safety barricades shall be joined together with 3” yellow Caution tape as follows:

1. Two strands of caution tape running continuous from barricade to barricade, one at the tops of the barricades and one at a height of from 4” to 12” above grade or mounting level.

2. In addition battery-operated warning lights shall be maintained on such barricades, whenever visibility is restricted, and at night.

3.06 BACKFILL AND COMPACTION
A. Place bedding and backfill materials true to the lines, grades, and cross-sections indicated on the Drawings and compacted to the degree specified on the Drawings. Place bedding and backfill materials in horizontal lifts not to exceed 8 inches in thickness measured before compaction. The difference in level on either side of a pipe or duct shall not exceed 4 inches.

B. Backfill material shall not be placed over the pipe or duct until after it has been inspected by the Owner’s Representative.

C. It shall be incumbent upon the Contractor to protect the pipe or duct from damage during the construction period. It shall be the Contractor's responsibility to repair broken or damaged pipe or duct at no extra cost to the Owner. Tamping of backfill over the pipe shall be done with tampers, vibratory rollers and other machines that will not injure or disturb the pipe or duct. Carefully place backfill around and over the pipe or duct.

D. Do not allow construction traffic nor highway traffic over the pipe trench until the trench backfill has been brought back even with existing adjacent grade.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
TRENCH EXCAVATION AND BACKFILL 31 23 24 - 9
E. Add water to the backfill material or dry the material as necessary to obtain the optimum moisture content for the compaction shown on the Drawings or specified. If the Owner’s Representative determines that the nature of the ground in which the trench lies precludes compaction of the backfill to the specified density, the backfill shall be compacted to the maximum practicable density. Employ such means as may be necessary to secure a uniform moisture content throughout the material of each layer being compacted. After the material has been moisture conditioned, compact it with compaction equipment approved by the Owner’s Representative to achieve specified compaction. The Contractor shall be responsible for obtaining the densities specified. Should the Contractor fail, through negligence or otherwise, to compact to specified density, or to backfill and compact to surface grade, thus permitting saturation of the backfill material from rains or from any other source, the faulty material shall be removed and replaced with approved material which shall be compacted to the specified density at optimum moisture content, and no additional payment will be made for doing such work or removal and replacement.

F. Compaction by flooding, ponding or jetting will not be permitted.

3.07 CONTROLLED DENSITY FILL (CDF)
A. Trench Backfill:

1. Contractor can choose to backfill trench with CDF in place of Class II Aggregate Base. (See trench sections on drawings.)

2. CDF shall be placed into the trench so that the CDF is placed evenly to prevent uneven loading of the pipe. CDF shall not be placed directly onto the pipe. The maximum depth of the first lift of CDF shall not allow the pipe to move or float.

Subsequent lifts of CDF shall be placed so that that pipe does not shift or float.

CDF placed in trenches with steep slopes shall be placed in lifts to prevent flotation of the pipe, and the Contractor shall install approved sand bags as needed to secure the pipe in place during placement of the CDF.

3. The maximum temperature of the CDF shall be 74°F at the time of placement. The minimum temperature of the CDF shall be 40°F at the time of placement. CDF shall be placed in lifts not exceeding 6 inches. Each lift shall be allowed to cure long enough to lose its fluid properties before placing the next lift.

3.08 SUPPORT OF EXCAVATIONS
A. Adequately support excavation for trenches and structures to meet all applicable requirements in the current rules, orders and regulations. Excavation shall be adequately shored, braced and sheeted so that the earth will not slide or settle and so that all existing structures and all new pipe and structures will be fully protected from damage. Keep vehicles, equipment and materials far enough from the excavation to prevent instability.

B. Take all necessary measures to protect excavations and adjacent improvements from running, caving, boiling, settling, or sliding soil resulting from the high groundwater table and the nature of the soil excavated. Attention is directed to Section 832 of the Civil Code of the State of California relating to lateral and subjacent supports, and wherever structures or improvements adjacent to the excavation may be damaged by such excavation, the Contractor shall comply with this law.

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
TRENCH EXCAVATION AND BACKFILL 31 23 24 - 10
C. The support for excavation shall remain in place until the pipeline, duct or structure has been completed. During the backfilling of the pipeline or structure, the shoring, sheeting and bracing shall be carefully removed so that there shall be no voids created and no caving, lateral movement or flowing of the subsoils.

3.09 FINISH GRADING
A. Except where shown otherwise in the Drawings, restore the finish grade to the original contours and to the original drainage patterns. Grade surfaces to drain away from structures. The finished surfaces shall be smooth and compacted.

3.10 DISPOSAL OF EXCAVATED MATERIAL
A. Dispose of all excavated material offsite in a legal manner.

END OF SECTION 31 23 24

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
EROSION CONTROLS 31 25 13 - 1
SECTION 31 25 13

EROSION CONTROL
PART 1 - GENERAL

1.01 SUMMARY
A. Section Includes: Slope protection, erosion control, and shall consist of all permanent and temporary erosion control features as indicated for the purpose of preventing on-site erosion and maintaining all sediments within the project boundaries and comply with the requirements of the Contra Costa County Clean Water Program, as indicated in the plans, and as specified herein.

1.02 SCHEDULING
A. Apply erosion control features within five days after completion of all other work in each area.

B. Apply erosion control features as necessary for wet weather conditions and as directed by the Engineer.

1.03 REPLACEMENT
A. Any area in excess of 100 square feet of dead or damaged erosion control material shall be replaced.

B. The replaced erosion control shall be of the same formulation and quality as the original.

PART 2 - PRODUCTS

2.01 FIBER ROLLS
A. Use biodegradable fiber rolls as a perimeter control measure, along contours of slopes, around soil stockpiles, and as indicated in plans. On slopes space rolls 10 to 20 feet apart (using closer spacing on steeper slopes). Install parallel to contour. If more than one roll is used in a row overlap roll do not abut. J-hook end of roll upslope. Install rolls per either Type 1 (stake rolls into small trenches) or Type 2 (stake in front and behind roll and lash with rope). Use wildlife-friendly fiber rolls made of biodegradable natural materials. Avoid using fiber rolls made with plastic netting or fixed aperture netting. See:
http://www.coastal.ca.gov/nps/Wildlife-Friendly_Products.pdf. Manufactured linear sediment control or compost socks may be used in lieu of fiber rolls. CASQA: SE-5 (Type 1); SE-12, SE-13; or Caltrans: SC-5 (Type 1 and Type 2).

SHIELDS REID PARK IMPROVEMENTS

CITY OF RICHMOND
EROSION CONTROLS 31 25 13 - 2

2.02 SOIL COVER
A. Cover all exposed soil with straw mulch and tackifier (or equivalent). CASQA: EC-3, EC5, EC-6, EC-7, EC-8, EC-14, and EC-16. Caltrans: SS-2, SS-4, SS-5, SS-6, SS-7, SS-8.

2.03 REVEGETATION
A. Re-vegetate areas of disturbed soil or vegetation as soon as practical. CASQA: EC-4.

Caltrans: SS-4.

2.04 DRAIN INLET PROTECTION
A. Use gravel bags, (or similar product) around drain inlets located both onsite and in gutter as a last line of defense. Bags should be made of a woven fabric resistant to photodegradation filled with 0.5-1-in washed crushed rock. Do not use sand bags or silt fence fabric for drain inlet protection. CASQA: SE-10; or. Caltrans: SC-10.

2.05 CONCRETE WASHOUT
A. As indicated in the plans, construct a lined concrete washout site away from storm drains, waterbodies, or other drainages. Ideally, place adjacent to stabilized entrance. Clean as needed and remove at end of project. CASQA: WM-8. Caltrans: WM-8.

2.06 STOCKPILE MANAGEMENT
A. Cover all stockpiles and landscape material and berm properly with fiber rolls or sand bags. Keep behind the site perimeter control and away from waterbodies. CASQA: WM3. Caltrans: WM-3.

2.07 HAZARDOUS MATERIAL MANAGEMENT
A. Hazardous materials must be kept in closed containers that are covered and within secondary containment, do not place containers directly on soil. CASQA: WM-6. Caltrans:

WM-6.

2.08 SANITARY WASTE MANAGEMENT
A. Place portable toilets near stabilized site entrance, behind the curb and away from gutters, storm drain inlets, and waterbodies. Tie or stake portable toilets to prevent tipping and equip units with overflow pan/tray (most vendors provide these). CASQA: WM-9. Caltrans:

WM-9.

2.09 LITTER AND WASTE MANAGEMENT
A. Designate waste collection areas on site. Use watertight dumpsters and trash cans; inspect for leaks. Cover at the end of each work day and when it is raining or windy.

Arrange for regular waste collection. Pick up site litter daily. CASQA: WM-5; or Caltrans:

WM-5.

SHIELDS REID PARK IMPROVEMENTS