May 21, 2024
Public Works
DATE: May 21, 2024
TO: Mayor Martinez and Members of the City Council
FROM:
Daniel Chavarria, PE, Director of Public Works
Robert Armijo, PE, Deputy Director of Public Works/City Engineer
Josef Munoz, Capital Projects Manager
Subject:
Contract with Azul Works, Inc. for Construction of the
Shields-Reid Park Improvement Project
FINANCIAL IMPACT: The City has been awarded grant funding from the State of California Department of Parks and Recreation
Statewide Park Development and Community
Revitalization Program (SPP) for the Shields-Reid Park
Improvement Project that covers the cost of the project.
Account String: 10633031-400708-23028
PREVIOUS COUNCIL
ACTION:
October 19, 2022
STATEMENT OF THE
ISSUE:
The City has completed the competitive bid process for
Shields-Reid Improvement Project. City staff members
are seeking City Council’s approval of a contract with the lowest bidder, Azul Works, Inc.
RECOMMENDED ACTION:
ADOPT a resolution authorizing the award of a
construction contract to Azul Works, Inc. as the
contractor for the Shields-Reid Park Improvement
Project, in the amount of $4,088,240.31, for a term from May 22, 2024, to June 30, 2026; and AUTHORIZE the
Director of Public Works to approve change orders, if
necessary, for up to a total contingency amount not to
exceed $410,000 – Public Works Department (Robert
Armijo 510-620-5477/ Josef Munoz 510-672-2407).
AGENDA
REPORT
May 21, 2024
DISCUSSION:
In December 2021, the City was awarded grant funding from the State of California Department of Parks and Recreation Statewide Park Development and Community Revitalization Program (SPP) in the amount of $8,000,000, providing the City of Richmond funds to renovate Shields-Reid Park. Shields-Reid Park is a 5.17-acre park in the North Richmond neighborhood located at 1410 Kelsey Street, Richmond, CA 94801.
This public park project aims to improve health and wellness, safety, beauty, access to outdoor recreation, and to help catalyze community revitalization for a diversity of ages and abilities. The project includes final design, engineering, and construction of park improvements including: a stage, children’s play areas with integrated artwork, a fitness zone, community gathering areas including a shady grove of trees, bicycle pump track, a public restroom with amenities, perimeter fencing, and lighting. Sustainable design features include green infrastructure for stormwater management, energy efficient lighting, Bay-friendly landscaping, permeable paving, and the use of site furnishings and equipment that utilize recycled content. The park design features include high-quality materials and equipment for longevity/durability and low maintenance.
On March 4, 2024, City staff posted the bid documents (Attachment 3) on Planetbids.com and solicited bids for the Shields-Reid Park Improvement Project construction contractor. The deadline to submit the bids was April 3, 2024. The bids were received (Attachment 4) as follows:
Contractor Base Bid
Azul Works, Inc. $3,794,140.31
A&B Construction $3,993,000.00
S & H Construction $4,168,600.00
Buhler $4,175,656.00
Saboo $4,579,432.00
WR Forde $5,600,032.45
Based on the staff’s evaluation, Azul Works, Inc. is the lowest bidder. They have submitted all documents required by the bid document, and they are responsible. The bidder has the appropriate contractor’s license in active standing with the State of California and has completed similar projects.
As the bids came in within City’s budget, Public Works staff members are also recommending that alternates for Nature Play Area, Perimeter Fencing, and Grind, Overlay and Repaint/Restripe of existing basketball courts also be included in Azul Works, Inc. contract, for a total contract amount of $4,088,240.31.
City staff members are also requesting that City Council approve approximately 10 percent of the proposed contract amount (i.e., $410,000) as a construction contract contingency and authorize the Director of Public Works to approve supplemental work up to the contingency amount.
May 21, 2024
The approval of the contract with Azul Works will allow for the implementation of the Shields Reid Park Revitalization project, as described herein.