WWTP SODIUM BISULFITE (SBS) TANK
AMOUNT Veolia Mark-up
16.5% TOTAL
Initial Contract Original Contract Amount 4,839,888$ 798,582$ 5,638,470$
Contingency (15%) 725,983$ 65,338$
791,322$
Total amount approved by council via Resolution 97-21 5,565,871$ 863,920$ 6,429,791$
CHANGE ORDER
NUMBER DESCRIPTION AMOUNT Veolia Mark-up
(9%) TOTAL
Change Order 1 Chemical Building Skids and new doors 48,121$ 4,331$ 52,452$ Change Order 2 Time Extension (no price increase -$ -$ -$ Change Order 3 Chemical Delivery System Adjustments due to low piping issues 54,483$ 4,903$ 59,386$ Change Order 4 Multiple Design changes due to plumbing and piping issues 213,489$ 19,214$ 232,703$ Change Order 5 Unexpected underground utility conflicts and duct bank issues 76,053$ 6,845$ 82,898$ Change Order 6 Multiple change orders to accommodate chemical deliveries 238,429$ 21,459$ 259,888$ Change Order 7 Installation of new analyzers for delivery system 94,938$ 8,544$ 103,482$ Change Order 8 Programming telemetry system, installing power (not able to use solar), installation of extra safety equiment, replacing safety pumps 611,863$ 55,068$ 666,931$ $ 1,337,376 $ 120, 364 1,457,740$
7,096,210$
(666,419)$ Amount outstanding
TOTAL APPROVED CHANGE ORDERS
Total amount (Original Contract + Total Change Orders)
Attachment 3