Dornan Tunnel - Force Main Break Emergency Bypass Piping Date: 4/6/2023
Activity Classification VWNA Project #: 230304
Administration
Engineering Proposed by:
Planning Michael McKenzie, Veolia Water West Operating Services Design
Construction Reviewed by: Infersne ле
Construction Anderson Dil elia Water West Operating Senices Sanitary Sewer
Storm Sewer Reviewed by: Hern Thelm
Sanitary P.S. Mary helps, Aythorized City Dept. Rep. (PO verification) Storm P.S.
Wastewater X Reviewed by:
Stormwater City of Richmond, Finance Departmen
Wastewater Plant
Approved by:
Daniel Chavarria
City of Richmond, Public/Works Director
Approval Date: 4/19/23
Original Line Item Approved Cost: 246,046.43
Approved Markup/Margin 40,597.66
Approved Mark-up Total Authorized Amt.: 286,644.09
Scope of Services TA SUMMARY PAGE
Emergency Bypass piping required for Dornan Tunnel Force Main Break 12/31/2022.
Point Richmond 8" Force Main Emergency bypass work. This TA covers the scope of services provided by Myers Construction, Dig Alert Done Right and Bayhawk during the emergency night work for the Dornan Tunnel force main break. The scope included Bayhawk labor and equipment, Dig Done Right hydroexcavation labor and equipment, Myers Construction labor, equipment, bypass piping rental (12 months).
The price breakdown for this work includes the following:
1. Cost for Myers Construction: $157,376.43
2. Cost for Dig Alert Done Right: $62,875.00
3. Cost for Bayhawk: $25,795.00
4. Subtotal: $246,046.43
Veolia Markup
Proposal SUBTOTAL 16.50% TOTAL
Myers Construction $ 157,376.43 25,967.11 183,343.54
Dig Alert Done Right $ 62,875.00 10,374.38 73,249.38
Bayhawk $25,795.00 4,256.18 30.051.18
Total 246.046.43 40,597.66 286.644.09