450 Civic Center Plaza, Richmond, CA 94804-1630
Telephone: (510) 620-5478 Fax: (510) 307-8195 www.ci.richmond.ca.us
PUBLIC WORKS DEPARTMENT
6/17/2025
Attachment 5 - Shields-Reid Park Improvement Project
Project Costs
City Requested Changes
- $119,471.13 = Additional electrical service
- $102,743.36 = Poured-in-place play area safety surfacing in lieu of fibar - $52,928.32 and $33,041.28 = Renovation of two existing basketball courts - $25,673.78 = Art installation
- $142,388.96 = Planting around the Community Center to be completed by Civicorps, a youth training non-profit organization
- $476,246.83 = Total City requested changes
Unforeseen Circumstances/Changes
- $5,067.25 = Irrigation modifications
- ($1,211.39) Furnishing modifications
- $80,547.30 = Restroom footing modifications =
- $15,632.78 = Additional storm drain infrastructure
- $16,718.73 = Additional manhole infrastructure
- $5,036.06 = Planting modifications
- $123,320.23 = Unforeseen Changes
Project Budget Breakdown
- $8,000,000 = CIP Budget
$4,088,240.31 = Approved Construction Contract
- $408,824 = Approved Construction Contingency
- $400,000 = Proposed Contract Amendment
- $4,897,064.31 = Proposed Total Construction Contract Authority